Title: Cacac
1Status and Perspectives
Request CMS status in general, mainly the
tracker and calorimeter, an overview of the
physics challenges that we have to face and life
after the start of LHC ( super LHC)
T. S. Virdee CERN/Imperial College Mont St Odile,
29 March 2006
2Outline of Talk
- Current Construction Status to the Endgame
- Assembly at point 5, Bat 904Commissioning and
Burn-in of electronics, Trigger/DAQ - ECAL and Tracker
- MTCC Shakedown of hardware chains - end-to-end
- Lowering of the Experiment and Hardware
Commissioning - Commissioning for Physics
- Software Readiness Reviews, MTCC preparation
- Computing (CSA06, T0/T1/T2..)
- Physics TDRs, Startup, Trigger Tables, HLT,
- 2007 FEDs ? Desktop, Cosmics data ? Desktop,
Pilot Physics Run - Physics
- 2008 onwards - first rediscover SM, then make
discoveries ! Latter is what we built the
detector for ! - Longer Term Future
- Completion of High Luminosity Detector, SLHC
upgrades
3Construction Progress
- Commissioning in large sub-parts (checking
systems aspects!) is underway. - Civil Engineering UX will be ready to receive
CMS elements by mid-2006. Forward shielding
blockhouses lowered. Gantry crane erected - Magnet coil is state of the art - now cold.
Close yoke in May, Energize in June. - Tracker TIB, TID well advanced, TEC, TEC-,
TOB integration all started, cabling simplified,
TIB,TOB,TEC in Support Tube by Nov. Tracker to be
taken to Pt 5 end-Jan07 - ECAL 75 of barrel crystals delivered, 6 out of
36 SM integrated with electronics. Lower 30-32
out of 36 equipped SMs in Oct/Nov 2006. - HCAL source calibration completed of HB, HE, 1
HF, Lower HF in July - Muon system Over 3 out of 5 wheels worth of DTs
installed, cabling proceeding apace, cosmics
being taken, Most of CSCs commissioned with
cosmics. Over half of RPCs installed. - Trigger-DAQ L1-Trigger core being tested in EIC
(also tests back-end electronics, burn-in power
supplies) 1/8th DAQ at Point 5. - CPT Submitted Physics TDR Vol1 to LHCC in Jan.
Preparing for Cosmic Challenge and CSA06 in
Q406 using new Framework. Submit Physics TDR Vol2
in for June LHCC, Vol 3 (HLT and Startup) for Jan
07 LHCC.
CMS initial detector will be ready for collisions
in 2007.
4CMS Solenoid
Magnet reached nominal operating temperature for
the first time on 25 Feb. Cooldown took 24 days.
Energize in June. Cool-down achieved by pumping
helium gas at liquid nitrogen temperature
(-196oC) and then as liquid helium. Coil 14.5t
sc cable, 74t pure Al, 126t high strength Al
300
K
max
210
min
120
0
15/2
3/2
25/2
5Barrel DT/RPC Muon Ch in YB0
Lower YB0 in Oct06
6Endcaps
Lower in September
RPCs on YE2
CSCs and RPCs on YE1
7Cabling on YB1
8HB Readied to be Inserted into Coil
Lower HB in Oct/Nov
Barrel Yoke wheels YB2 and YB1 80 (out of
210) DT/RPC Ch. Installed 40 Ch. commissioned
9Testing ECAL SM insertion
10Tracker TIF Rod Insertion in TOB
TOB completion is on Critical path TOB Aug 06,
TOB - Oct 06 Move Tested Tracker to Point 5 in
Jan07
11Tracker TIB - Layer 4 (Pisa)
TIB/TID at CERN May06 TIB/TID- at CERN Aug06
12Tracker Endcaps
TEC at Aachen
TEC- at CERN TECs also on CP
TEC at CERN Sep 06 Accelerate ?
TEC- ready at CERN Nov 06 Accelerate ?
13ECAL SM Electronics Integration
Lower 90 of barrel SMs in November
14ECAL Barrel Dashboard
05
06
07
SM0
SM17
SM35
15Electronics Integration Centre
16Trigger Integration in Bat 904
- Large scale successful integration tests in
central racks using common TTC infrastructure
involving trigger primitives, regional global
processing - Calorimeter Trigger
- Muon Trigger
- Global Trigger
17CMS Master Schedule
Magnet closed May 06 Magnet
test/cosmic challenge May-Aug 06 EB
installation Aug 06 SX5 USC ready for
crates April-May 06 UXC cable chains
installed April 06-Jun 06 HF lowering
July 06 YE/YB cable chains cabled June
06 YE3 lowering start Aug 06 UXC ready for
crates Jul 06 First connection to USC
Aug-Sep 06 YB0 lowering start Oct 06 EB-
installation Oct 06 SX5 May07 UXC Tracker
installation Jan-Feb 07 ECAL/Tracker
cabling complete Apr-May 07 Heavy lowering
complete Feb-Mar 07 Initial CMS ready to
close 30 Jul 07 No Contingency Study
options to recover 2 months during YB0 cabling,
tracker insertion and beam pipe installation (EE
and pixels installed in 2008).
18Commissioning For Physics
- 2006 year of installation and commissioning
for computing, software and analysis procedures - Cosmic Challenge in May/June
- Install new software computing for CSA06
- Integrated test (without online)
- Software Computing Commissioning
- phase 1 CSA2006
- phase 2 HLT work by end 2006
- Physics Commissioning
- phase 1 move to new SC start in April/May
- phase 2 Volume III
- phase 3 end-to-end tests in 2007
- Data from P5 to desktop (FEDs, cosmics,
19Physics TDR Vol. III
- High-Level trigger
- Software (both the algorithms and steering)
- Timing (broken by trigger type also for
ensemble) - Trigger tables for
- Pilot run (43x43 1029-1031)
- Startup (936x936 75 ns 1032)
- 1033 (25 ns operation)
- Primary datasets
- Definitions
- Size estimates
- First definition of online streams
- Rest of Vol III
- Startup procedures, etc
20Preparing for Physics
Startup - Pilot Physics Run cosmics, beam halo,
single beam-gas, pp collisions debug detector,
synchronization, calibration, alignment, s/w
checkout, reconstruction, work out object
reconstruction efficiencies from data, min
bias, jets, b production etc. 2008
re-discover SM ( b, W/Z, jets, ?, top, .) and
understand performance of CMS (W/Z production
predicted to few ), omnipresent backgrounds for
a large number of searches - need to be
understood in all detail Discover new physics
SUSY, BSM (look for new heavy objects) End-2008
Heavy Ion run Communication and collaboration
Organise the community at home Identify
small number of physics subjects or themes, each
with enough people to be competitive, incl young
RAs, students Identify their leaders, fold them
into CMS International (coordinated efforts)
21Cross-Sections and Rates
Relative Rate MinBias
1 Jet (ETgt25 GeV) 10-2 b bar
10-3 ? Jet (ETgt20 GeV)
10-5 Jet (ETgt140 GeV) 10-6 W ? l?
10-8 Z ? l l
10-9 t tbar ? l? 10-10
22Machine Startup I
23Consequences for Startup
- Relative Rate
- MinBias 1
- Jet (ETgt25 GeV) 10-2
- b bar 10-3
- Jet (ETgt20 GeV) 10-5
- Jet (ETgt140 GeV) 10-6
- W ? l? 10-8
- Z ? l l 10-9
- t tbar ? l? 10-10
24Machine Startup II
25Machine Startup III
26Creating Infrastructure for CMS Nerve Centre
- Build a Remote Control Room for CMS on Meyrin
Site (CCAR) - The lack of infrastructure at P5 (people)
- In the beginning, this will be the Remote
Monitoring Room for CMS - Initially Data Quality Monitoring High-Level
Trigger - Should/will run Offline shifts
- These will be really necessary to ensure
- That the data are processed correctly
- Short turn-around time in identifying problems
- That the actual Tier-0 production line is always
full - To monitor and follow up in general what the
GRID is doing for CMS - Tier-1 centers data distribution
- Above all, to operate the CAF
- Single most important element in the chain from
P5 to the Tier0 output
27Creating Infrastructure for CMS Nerve Centre
- (CCAR)
- In this case, this facility would be the CMS
Operations Center/Room - Like a portal to all things CMS
- The Trigger
- The Data
- The Grid
- Huge component the human aspect communication
- This will be the ideal place to cluster the CMS
effort - Really advantageous to have the experiment
screens, and people monitoring the data-taking in
the same area with the people processing the
data/obtaining the calibration constants - In association with a well equipped CAF enable a
powerful analysis capability
28CMS Computing Model
Nominal Size Tier-1 Tier-2 CPU
(kSI2000) 2500 900 Disk (TB) 1200 200 Tape
(TB) 2800 0
White Paper for May LHCC
29SLHC Inner Tracking Pixels
- Pixels to much larger radius
- Technology and Pixel size vary with radius
- Not too large an extrapolation in sensor
technology - Cost/Geometry optimization
- BUT RD required for pixels lt 15 cm
Physics Potential and Experimental Challenges of
the LHC Luminosity Upgrade, Eds. F. Gianotti,
M.Mangano, T. S. Virdee, EPJ C39(2004)293
30SLHC Level-1 Trigger
- RD Opportunities
- The Trigger/DAQ system of CMS will require an
upgrade to cope with the higher occupancies and
data rates at SLHC - Will need an improved muon and calorimeter
Level-1 trigger system - A key issue - can we include some tracking in
the Level 1 Trigger ? - Change qualitatively and quantitatively physics
retained - There may not be enough rejection power using the
muon and calorimeter triggers to handle the
higher luminosity conditions at SLHC - Using the studies for HLT applications gives an
idea of what could be gained using elements of
the tracker in the Level 1
31Tracking Trigger
- Why not use the inner tracking devices in the
trigger? - Number of hits in tracking devices on each
trigger is enormous - Impossible to get all the data out in order to
form a trigger inside - How to correlate information internally in order
to form segments? - Possible topic for future RD
- Stacked pixels which can measure Pt of track
segments locally - Two layers about 1mm apart that could communicate
32Upgrade Strategy
- Within 5 years of LHC start
- New layers within the volume of the current Pixel
tracker which incorporate some tracking
information for Level 1 Trigger - Upgrade to full new tracker system by SLHC (8-10
years from LHC Startup) - Systems design right from the start (detectors,
f.e., hybrids, optical links, power distribution,
cooling, support structures, - Includes full upgrade of trigger system
33Discovery Physics
34CMS Master Schedule
Magnet closed May 06 Magnet
test/cosmic challenge May-Aug 06 EB
installation Aug 06 SX5 USC ready for
crates April-May 06 UXC cable chains
installed April 06-Jun 06 HF lowering
July 06 YE/YB cable chains cabled June
06 YE3 lowering start Aug 06 UXC ready for
crates Jul 06 First connection to USC
Aug-Sep 06 YB0 lowering start Oct 06 EB-
installation Oct 06 SX5 May07 UXC Tracker
installation Jan-Feb 07 ECAL/Tracker
cabling complete Apr-May 07 Heavy lowering
complete Feb-Mar 07 Initial CMS ready to
close 30 Jul 07 No Contingency Study
options to recover 2 months during YB0 cabling,
tracker insertion and beam pipe installation. (EE
and pixels installed in 2008).
35Conclusions
- CMS Construction is making good progress
- Towards MTCC, lowering and hardware commissioning
in UXC, USC - Commissioning for Physics
- Putting in place final software Software
Readiness Reviews, CSA06 (T0/T1/T2..) - Physics TDRs, Startup
- Exercise more and more complete systems (
increased payloads) - In 2007 FEDs ? Desktop, Cosmics data ? Desktop,
Pilot Physics Run - Physics
- 2008 onwards - first rediscover SM, then make
discoveries ! Latter is what we built the
detector for ! - Longer Term Future
- Completion of High Luminosity Detector, SLHC
upgrades - Initial CMS should be ready for collisions in
2007 - Future will Surely be Exciting