Title: Project Management
1Project Management
2Project Management
3(No Transcript)
4Build this structure
5Build this structure
10 block lengths wide
10 block heights high
6Observations?
- What self-organizing behaviors (if any) did the
first team use? - What primary factors determined the length of
time it took to assemble the structure? - What was the critical work item that limited the
speed with which it could be built? - Is there a faster way to build the structure?
7(No Transcript)
8Build this structure
10 block lengths wide
10 block heights high
9Process to Use
assemble diagonal post
assemble vertical post
1
2
3
start
assemble horizontal bridge
assemble pieces
4
5
done!
10Build this structure
10 block lengths wide
10 block heights high
11Observations?
- Did the second team follow the imposed project
plan? - Did the project plan help or hurt?
- What primary factors determined the length of
time it took to assemble the structure? - What was the critical work item that limited the
speed with which it could be built? - Is there a still faster way to build the
structure?
12Another Process?
assemble diagonal post
assemble vertical post
1
2
3
assemble pieces
start
done!
first?
assemble horizontal bridge
4
5
13Project Management
- Simple Putting dinner on the table 2 people,
each preparing a number of dishes, each requiring
numerous steps which must be executed in an
orderly fashion
14Project Management
- Complex You have a hardware project with
hundreds of vendors, each providing dozens of
components on their own production schedules,
with inter-relationships among the components in
how they are to be assembled and tested. - Example automobile assembly
- Complex You have a software project with
hundreds of software engineers and quality
assurance personnel, writing millions of lines of
code, with inter-relationships among the
components - Example modern application (e.g. Microsoft Word)
15Project Management
- For a complex project.
- Which components and/or vendors are most likely
to cause schedule problems? - What is the magnitude of the possible schedule
problem? - Does any problem threaten the projects
completion? - What can be done to minimize the impact of a
problem?
16Project Management
- The question your boss is most likely to ask
- What can be done to bring-in the schedule?
17Elements of Project Management
- Project team
- Individuals from different departments within
company - Matrix organization
- Team structure with members from different
functional areas depending on skills needed - Project manager
- Leader of project team
18Project Planning
- Statement of work
- Written description of goals, work time frame
of project - Activities require labor, resources time
- Precedence relationship shows sequential
relationship of project activities
19Elements of Project Planning
- Define project objective(s)
- Identify activities
- Establish precedence relationships
- Make time estimates
- Determine project completion time
- Compare project schedule objectives
- Determine resource requirements to meet objective
20Work Breakdown Structure
- Hierarchical organization of work to be done on a
project - Project broken down into modules
- Modules subdivided into subcomponents,
activities, and tasks - Identifies individual tasks, workloads, and
resource requirements
21Work Breakdown Structure
Work Breakdown Structure
- Hierarchical organization of work to be done on a
project - Project broken down into modules
- Modules subdivided into subcomponents,
activities, and tasks - Identifies individual tasks, workloads, and
resource requirements
22Project Control
- All activities identified and included
- Completed in proper sequence
- Resource needs identified
- Schedule adjusted
- Maintain schedule and budget
- Complete on time
23A Gantt Chart
- Popular tool for project scheduling
- Graph with bar for representing the time for each
task - Provides visual display of project schedule
- Also shows slack for activities
- Amount of time activity can be delayed without
delaying project
24A Simplified Gantt Chart
25A Simplified Gantt Chart
RED lines indicate mandatory order of events
26A Simplified Gantt Chart
Month
0 2 4 6 8 10
Activity Design house and obtain financing Lay
foundation Order and receive materials Build
house Select paint Select carpet Finish work
Possible slack time of one month
one month
or as late as month 4
Could start as early as month 3
1 3 5 7 9
Month
27A Simplified Gantt Chart
Items that could be specified earlier
28CPM/PERT
- Critical Path Method (CPM)
- DuPont Remington-Rand (1956)
- Deterministic task times
- Project Evaluation Review Technique (PERT)
- US Navy, Booz, Allen Hamilton
- Multiple task time estimates
29The Project Network
- Network consists of branches nodes
Node
1
3
2
Branch
30Project Network
- Nodes are numbered in sequential order, typically
left-to-right - Branch is a work item, with time required
Node
Design House 12 weeks
1
3
2
Branch
31Project Network for a House
32Project Network for a House With Work Times (in
months)
33Concurrent Activities
34Critical Path
- A path is a sequence of connected activities
running from start to end node in network - The critical path is the path with the longest
duration in the network - Project cannot be completed in less than the
time of the critical path
35How many possible paths (left-to-right) are
there?
36The Critical Path
- Path Length
- A 1-2-3-4-6-73 2 0 3 1 9 months
- B 1-2-3-4-5-6-73 2 0 1 1 1 8 months
- C 1-2-4-6-73 1 3 1 8 months
- D 1-2-4-5-6-73 1 1 1 1 7 months
37The Critical Path
- A 1-2-3-4-6-73 2 0 3 1 9 months
- B 1-2-3-4-5-6-73 2 0 1 1 1 8 months
- C 1-2-4-6-73 1 3 1 8 months
- D 1-2-4-5-6-73 1 1 1 1 7 months
Critical Path
38The Critical Path
3
Lay foundation
Dummy
Finish work
Build house
2
0
3
1
3
1
Design house and obtain financing
Order and receive materials
1
1
Select carpet
Select paint
5
- A 1-2-3-4-6-73 2 0 3 1 9 months
- B 1-2-3-4-5-6-73 2 0 1 1 1 8 months
- C 1-2-4-6-73 1 3 1 8 months
- D 1-2-4-5-6-73 1 1 1 1 7 months
Critical Path
39(No Transcript)
40Reduced version of Gantt Chart for building a
home
41Four months later
- In the construction project
42(No Transcript)
43(No Transcript)
44Postal Office Letter Package Sorting
- How many paths are there?
- What is the longest path item (critical path)?
- How long is it?
READ Zip?
1 second
Manual READ
20 seconds
SORT
Letter Package
10 seconds
READ Zip?
20 seconds
Manual READ
60 seconds
45Floral Shop
- A floral shop has two employees, the florist and
a clerk. When a phone order comes in, the clerk
spends 3 minutes taking the order, passes it off
to the florist, and then spends 5 minutes
verifying the credit card while the floral
arrangement is made. The florist spends 3
minutes cutting, then 9 minutes arranging the
flowers. - Draw the flow diagram
- What is the critical path of filling an order?
- How long does an order take?
46Floral Shop
Clerk in white, florist in blue
3 mins
9 mins
Cut flowers
Arrange flowers
Take order
Credit card
3 mins
5 mins
47Problem 1 Floral Shop
3 mins
9 mins
Cut flowers
Arrange flowers
Take order
Credit card
3 mins
5 mins
Critical path order?cut?arrange
Order time 339 15 minutes
capacity 1 order/15 minutes 4 orders/hour
48Problem 1 Floral Shop
3 mins
9 mins
Cut flowers
Arrange flowers
Take order
Credit card
3 mins
5 mins
Critical path order?cut?arrange
capacity 1 order/15 minutes 4 orders/hour
How might we speed up floral orders?
49Problem 1 Floral Shop
3 mins
9 mins
Cut flowers
Arrange flowers
Take order
Credit card
3 mins
Assist in arranging
5 mins
helpTime
If Clerk helps in arrangements (helpTime
minutes) florist time 3 (9
helpTime) clerk 3 5 helpTime
Optimal utilization is when both spend equal
time 3 9 - helpTime 8 helpTime ? 12 - HT
8 HT Or helpTime 2 minutes
50Team Project
- After HTM302 today, Meredith must
- meet with her team, Bill and Mary, in the Library
for 1 hour - then write her section of a report (1 hour)
- while she is writing her section, Bills section
is being written (2 hours) - after both sections are completed, Mary must
assemble and finalize the report (1 hour) - then Mary must email report to the instructor (5
minutes) - Draw the network diagram and find the critical
path
51Team Project
- Critical path Meet ? Bill writes ? Mary
assembles ? Mary emails - Path length 4 hours 5 minutes
52Critical Path
- The critical path not only tells us how long the
project will take, it also tells us which work
items are on the critical path - If critical path items are late, the project will
be late - If critical path items can be completed early, it
may be possible to shorten the project schedule - The project manager should monitor and analyze
the critical path items to ensure timely
completion
53Critical Path
- Analysis of the critical path is done by looking
at the - Earliest possible start times
- Latest possible start times
- Earliest possible finish times
- Latest possible finish times
- of each work item as well as the work personnel
and resources assigned to each
54Team Project
- What is the
- Earliest start time for Bill and Merediths
writing? - Earliest start time for Marys assembly?
- Do either Bill or Meredith have any slack time?
- How might we speed up the project completion?
55The Critical Path
Activity Start Times
4 Start at 5 months
2
0
3
1
3
1
1
2 Can start at 3 months
56Informal feedback
- Write a 2 minute journal to be handed in
immediately - The journal should briefly summarize
- Major points learned
- Areas not understood or requiring clarification