Project Scheduling - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Project Scheduling

Description:

Project Scheduling Probabilistic PERT PERT Probability Approach to Project Scheduling Activity completion times are seldom known with cetainty. PERT is a technique ... – PowerPoint PPT presentation

Number of Views:189
Avg rating:3.0/5.0
Slides: 24
Provided by: businessF4
Category:

less

Transcript and Presenter's Notes

Title: Project Scheduling


1
Project Scheduling
  • Probabilistic PERT

2
PERT Probability Approach to Project Scheduling
  • Activity completion times are seldom known with
    cetainty.
  • PERT is a technique that treats activity
    completion times as random variables.
  • Completion time estimates can be estimated using
    the Three Time Estimate approach. In this
    approach, three time estimates are required for
    each activity
  • Results from statistical studies
  • Subjective best estimates

a an optimistic time to perform the activity
P(Finish lt a) lt ?.01 m the most likely time to
perform the activity (mode) b a pessimistic
time to perform the activity P(Finish gt b) lt ?.01
3
3-Time Estimate ApproachProbability Distribution
  • With three time estimates, the activity
    completion time can be approximated by a Beta
    distribution.
  • Beta distributions can come in a variety of
    shapes

4
Mean and Standard Deviation forActivity
Completion Times
  • The best estimate for the mean is a weighted
    average of the three time estimates with weights
    1/6, 4/6, and 1/6 respectively on a, m, and b.
  • Since most of the area is with the range from a
    to b (b-a), and since most of the area lies 3
    standard deviations on either side of the mean (6
    standard deviations total), then the standard
    deviation is approximated by Range/6.

5
PERT Assumptions
  • Assumption 1
  • A critical path can be determined by using the
    mean completion times for the activities.
  • The project mean completion time is determined
    solely by the completion time of the activities
    on the critical path.
  • Assumption 2
  • There are enough activities on the critical path
    so that the distribution of the overall project
    completion time can be approximated by the normal
    distribution.
  • Assumption 3
  • The time to complete one activity is independent
    of the completion time of any other activity.

6
The Project Completion Time Distribution
  • The three assumptions imply that the overall
    project completion time is normally distributed,
    with

? Sum of the ?s on the critical path ??2
Sum of the ??2 s on the critical path
7
The Probability Approach
8
Distribution For Klone Computers
  • The project has a normal distribution.
  • The critical path is A-F-G-D-J.

9
Standard Probability Questions
  • What is the probability the project will be
    finished within 194 days?
  • P(X lt 194)
  • Give an interval within which we are 95 sure of
    completing the project.
  • X values, xL, the lower confidnce limit, and xU,
    the upper confidnce limit, such that P(XltxL)
    .025 and P(XgtxU) .025
  • What is the probability the project will be
    completed within 180 days?
  • P(X lt 180)
  • What is the probability the project will take
    longer than 210 days.
  • P(X gt 210)
  • By what time are we 99 sure of completing the
    project?
  • X value such that P(X lt x) .99

10
Excel Solutions
11
Using the PERT-CPM Template for Probabilistic
Models
  • Instead of calculating µ and ? by hand, the Excel
    template may be used.
  • Instead of entering data in the µ and ? columns,
    input the estimates for a, m , and b into columns
    C, D, and E.
  • The template does all the required calculations
  • After the problem has been solved, probability
    analyses may be performed.

12
Call Solver Click Solve Go to PERT OUTPUT
worksheet
13
Call Solver Click Solve
14
(No Transcript)
15
(No Transcript)
16
Cost Analysis Using theExpected Value Approach
  • Spending extra money, in general should decrease
    project duration.
  • But is this operation cost effective?
  • The expected value criterion can be used as a
    guide for answering this question.

17
Cost Analyses Using Probabilities
  • Suppose an analysis of the competition
    indicated
  • If the project is completed within 180 days,
    this would yields an
    additional profit of 1 million.
  • If the project is completed in 180 days to 200
    days, this would yield an additional profit of
    400,000.

18
KLONE COMPUTERS - Cost analysis using
probabilities
  • Completion time reduction can be achieved by
    additional training.
  • Two possible activities are being considered.
  • Sales personnel training (Activity H)
  • Cost 200,000
  • New time estimates are a 19, m 21, and b
    23 days.
  • Technical staff training (Activity F)
  • Cost 250,000
  • New time estimates are a 12, m 14, and b
    16.
  • Which, if either option, should be pursued?

19
Analysis of Additional Sales Personnel Training
  • Sales personnel training (Activity H) is not a
    critical activity.
  • Thus any reduction in Activity H will not affect
    the critical path and hence the distribution of
    the project completion time.

This option should not be pursued at any cost.
20
Analysis of Additional Technical Staff Training
  • Technical Staff Training (Activity F) is on the
    critical path so this option should be analyzed.
  • One of three things will happen
  • The project will finish within 180 days
  • Klonepalm will net an additional 1 million
  • The project will finish in the period from 180 to
    200 days
  • Klonepalm will net an additional 400,000
  • The project will take longer than 200 days
  • Klonepalm will not make any additional profit.

21
The Expected Value Approach
  • Find the P(X lt 180), P(180 lt X lt 200), and
    P(X gt 200) under the scenarios that
  • No additional staff training is done
  • Additional staff is done
  • For each scenario find the expected profit
  • Subtract the two expected values.
    If the
    difference is less than the cost of the training,
    do not perform the additional training.
  • Caution These are expected values (long run
    average values). But this approach serves as a
    good indicator for the decision maker to
    consider.

Expected Additional Profit 1000000(P(Xlt180))
400000(P(180ltXlt200)) 0(P(Xgt200))
22
The Calculations
  • The PERT-CPM template can be used to calculate
    the probabilities.

µ 189 ? 9.0185
µ 194 ? 9.255
Total 450,976
Total 335,751
Net increase 450,976-335,751 115,225 This
is less than the 250,000 required for training.
Do not perform the additional training!
23
Review
  • 3-Time Estimate Approach for PERT
  • Each activity has a Beta distribution
  • Calculation of Mean of each activity
  • Calculation Variance and Standard Deviation for
    each activity
  • Assumptions for using PERT approach
  • Distribution of Project CompletionTime
  • Normal
  • Mean Sum of means on critical path
  • Variance Sum of variances on critical path
  • Using the PERT-CPM template
  • Using PERT in cost analyses
Write a Comment
User Comments (0)
About PowerShow.com