Title: Building Commissioning
1Building Commissioning
- Ron Major
- Resource Conservation Manager
2What will be covered?
- Definitions of commissioning, retro-commissioning
and re-commissioning - New building commissioning
- Retro-Commissioning
3What will be covered?
- Commissioning and LEED
- Commissioning and the Washington Sustainable
Schools Protocol
4What is building commissioning?
- ASHRAE definition Commissioning is the process
of ensuring that systems are designed, installed,
functionally tested, and capable of being
operated and maintained to perform in conformity
with the design intent.
5What is building commissioning?
- Washington State Department of General
Administrations definition Building
Commissioning is a systematic and documented
process of ensuring that the owners operational
needs are met, building systems perform
efficiently, and building operators are properly
trained. -
6Definitions
- Building commissioning typically involves four
distinct phases for new construction. - Pre-design
- Design
- Construction
- Warranty
7Definitions
- Re-commissioning is applied to an existing
building that was originally commissioned. - Retro-commissioning is applied to an existing
building that was never commissioned.
8What is the goal of building commissioning?
- To deliver a facility that operates as it was
intended. - To provide a facility that meets the needs of the
building owner and occupants. - To provide appropriate training for facility
operators on the operation and maintenance of the
building systems.
9When should the building commissioning process
start?
- Building commissioning can be started near the
end of construction. (good) - Building commissioning can be started at the
start of construction. (better) - Building commissioning can be started during
schematic design. (best)
10When should the building commissioning process
start?
- Benefits of early involvement
- Design review.
- Better building commissioning specifications.
- Clear building commissioning expectations.
- Better bids.
11When should the building commissioning process
start?
- Early involvement by the commissioning agent may
not carry a cost premium. It will reduce project
design problems and will introduce building
commissioning expectations early.
12Develop building commissioning scope of work
- Before meeting with the commissioning agent
develop a draft commissioning scope of work. - Start by asking the facility owner and operators
what problems they encountered on previous
construction projects.
13Develop building commissioning scope of work
- Do not limit your commissioning to just HVAC and
controls. Envelope, lighting controls, security,
lab spaces, medical gas systems, and other
complex systems should be considered.
14Develop building commissioning scope of work
- Then use the Commissioning Guidelines for
systems to be commissioned. - HVAC systems
- Air distribution systems
- Plumbing and piping systems
- Heating and cooling plant equipment
- Control systems
- Electrical systems
- Metering strategy and equipment
15What should be budgeted for building
commissioning?
- The following rules of thumb can help a client
budget for building commissioning services. - 1.00 to 2.00 per square foot depending on the
complexity, size and location of the building. - 1.0 to 2.5 of the total construction cost.
16Cost savings for building commissioning
- 8 - 20 reduction in operating costs for a
building that is commissioned. - 1.5 5.5 year simple payback on commissioning.
- Based on
- fewer change orders.
- lower energy usage.
- reduced operational problems.
17What does building commissioning involve?
- Verifying and documenting building systems
performance through all phases of a project from
concept to occupancy. - Testing HVAC systems performance to ensure that
they meet the needs of the building throughout
the full range of operating parameters that may
be encountered.
18Expected Deliverables
- 1. Commissioning plan and schedule detailing each
step of the commissioning process and each team
members role and responsibilities. - 2. A diagnostic and functional test plan
detailing how each test will be accomplished and
noting expected performance parameters.
19Expected Deliverables
- 3. A list of findings and potential improvements
identified by the commissioning provider for
design phase and construction phase activities - 4. A training plan recommending specific topics
and training schedules
20Expected Deliverables
- 5. At the completion of the project, a final
commissioning report detailing all of the
commissioning providers findings and
recommendations including copies of all
functional performance testing data.
21Expected Deliverables
- 6. A systems concepts and operations manual which
gives a description of each system with specific
information about how to optimally operate and
control the system during all modes of operation
such as during fire, power outage, shutdown,
etc., including special instructions for energy
efficient operation and
re-commissioning.
22Expected Deliverables
- 7. Energy savings and implementation cost
estimates for recommendations developed in the
process are also deliverables for
retro-commissioning projects.
23Retro-commissioning
- Is a systematic, documented process that
identifies low cost OM improvements in an
existing building and brings that building up to
the design intentions of its current usage.
24What are the goals of retro-commissioning?
- To identify and fix existing problems, such as
indoor air quality. - To improve the energy efficiency of the building.
- To provide a facility that meets the current
needs of the building owner and occupants. - To provide training for facility operators on the
operation and maintenance of the existing
building systems.
25What is the cost of retro-commissioning?
- 0.40 to 1.20 per square foot depending on the
complexity, size, and location of the building. - This includes the first phase and the second
phase after corrections are made. - General housekeeping done before commissioning is
started can help reduce costs. - Assigning maintenance staff to assist the
commissioning agent can also help reduce the cost
while providing a good training opportunity.
26What does retro-commissioning involve?
- Verifying and documenting the existing building
systems performance. - Testing HVAC systems performance to ensure that
they meet the current needs. - Identifying and recommending solutions to
existing building problems.
27When to retro-commission
- If the building has never been commissioned.
- If the original usage of the building has
changed. - If the building is experiencing
- occupant comfort complaints.
- indoor air quality problems.
- higher energy costs.
- numerous operation and maintenance problems.
28Why use retro-commissioning?
- Low first cost for the building owner. The cost
for the first phase is typically in the 0.25 to
0.75 per square foot range. - The commissioning agent fully tests all of the
systems. - Simple repairs can be done during the
retro-commissioning investigation.
29Why use retro-commissioning?
- To make sure the equipment is operating
correctly. - To improve indoor air quality.
- To reduce occupant complaints.
- To increase occupant comfort.
- To reduce energy and demand costs.
30Why use retro-commissioning?
- The commissioning agent can subcontract and
oversee the repairs. - The commissioning agent commissions the repairs
after the work is completed to make sure the
systems are working correctly. - The retro-commissioning process is fully
documented.
31Developing the retro-commissioning scope of work
- Ask the facility owner and operator what problems
they are encountering. - Interview building staff to find out what
problems they are experiencing. - Based upon what was learned, draft the
retro-commissioning scope of work before meeting
with the commissioning agent.
32Cost savings for retro-commissioning
- 5 - 20 reduction in annual operating costs.
- 1.5 7.5 year simple payback is typical.
- This is based on
- lower energy usage.
- reduced operational problems.
- improved occupant comfort.
33Selecting theright commissioning agent
- It is important to select a commissioning agent
that has hands on experience with controls and
HVAC systems. - It is important to select a commissioning agent
that has good troubleshooting and problem solving
skills.
34How Does Commissioning fit into the LEED Version
2.2 Process?
- There are two levels of building commissioning
for the LEED process. - The first is what is called Fundamental
Commissioning and it is a pre-requisite
requirement for all LEED projects. - The second is Enhanced Commissioning and provides
one point under energy and atmosphere credit
number 3.
35LEED V2.2 Pre-Requisite Commissioning
Requirements
- REQUIRED SYSTEMS HVAC controls, lighting
controls, domestic water heating and any
renewable energy systems - The project team must designate a specific
individual as the commissioning authority (CA).
This individual must be qualified. Projects
larger than 50K SF project must be commissioned
by a third party
36LEED V2.2 Pre-Requisite Commissioning
Requirements
- The owner shall develop and CA shall review
owners project requirements (OPR) document. - The A/E shall develop and CA shall review the
basis of design (BOD) documents for the
commissioned systems
37LEED V2.2 Pre-Requisite Commissioning
Requirements
- The project documents must include the
commissioning requirements (Specs) - A commissioning plan must be developed and
implemented - The CA must verify the installation and
functional performance of all commissioned
systems
38LEED V2.2 Pre-Requisite Commissioning
Requirements
- The CA must complete a final summary
commissioning report
39LEED Enhanced Commissioning Requirements (EA
Credit 3)
- The CA must complete a review of the construction
documents at approximately the 50 complete stage - The CA must complete a review of the contractors
standard submittals related to commissioned
systems
40LEED Enhanced Commissioning Requirements (EA
Credit 3)
- The CA must verify all specified training
- The CA must develop a systems manual for all
commissioned systems - The CA must review operation and performance of
commissioned systems with the owner within 10
months after substantial completion
41Additional (Highly) Recommended Commissioning
Scope
- The CA meets with the project team to present
preliminary Cx plan discuss Cx contract scope
of work and Cx related responsibilities of the
entire project team - The CA conducts a control systems integration
meeting
42Additional (Highly) Recommended Commissioning
Scope
- The CA conducts a pre-construction commissioning
coordination meeting with the contractors - The CA makes periodic site visits during
construction to review installation and witness
contractor start-up routines - The CA conducts a Lessons Learned meeting after
all Cx is complete
43Often Misunderstood LEED Commissioning
Requirements
- Owners Project Requirement (OPR)
- Basis of Design (BOD)
- BOD based on OPR
- Prior to submittals for Fundamental Commissioning
- Prior to design submittal for Enhanced
Commissioning - Developing project onset maximizes value
44Often Misunderstood LEED Commissioning
Requirements
- Design review intent and timing
- Review as early as possible after the design is
fully developed and documented, such that issues
may be resolved as early as possible before the
construction documents are finalized.
45Often Misunderstood LEED Commissioning
Requirements
- Enhanced Commissioning Credit Independent 3rd
party requirement - 2, Design Review
- 3, Contractor submittal review
- 6, Post Cx review
- All other Enhanced Prerequisite requirements
may be provided by an individual employed by
design or CM firm, but not otherwise working on
the project.
46Commissioning and the Washington Sustainable
Schools Protocol
- E4.0 Fundamental Commissioning Required
- The design team and the school district shall
comply with completion requirements outlined in
Section 1416 of Washingtons NREC and WAC
180-27-080 regarding - Drawings
- Manuals
- System balancing
- Systems commissioning
- And in conformance with ESSB 5509, commissioning
shall be performed for projects over 5,000 s.f.
47Commissioning and the Washington Sustainable
Schools Protocol
- E4.1 Additional Commissioning
- Conduct a commissioning design review of the
Owners Project Requirements (OPR), Basis of
Design (BOD), and design documents prior to
mid-construction documents phase and back-check
the review comments in the subsequent design
submission. - Review contractor submittals applicable to
systems being commissioned for compliance with
OPR and BOD. This review shall be concurrent with
A/E reviews and submitted to the design team and
the owner. - Prepare a final commissioning report following
the WSEC 2004 Building Commissioning Final
Report Guidelines available from NEEC and review
with the school district, verifying that systems
are operational to the OPR and BOD and work is
completed.
48Commissioning and the Washington Sustainable
Schools Protocol
- Verify functional and maintenance training of OM
Staff, and verify that such training is completed
in the Final Commissioning Report. - Verify that training of building occupants
regarding optimal operation of commissioned
systems they interface with has been completed. - Assure through contractual arrangements
involvement by the CxA in reviewing building
operation after one academic year of building use
with OM staff and occupants. Include a plan for
resolving outstanding commissioning-related
issues.
49A properly commissioned facility can result in
-
- Fewer change orders during the construction
process - Fewer call-backs for warranty work
- Long-term tenant satisfaction
- Lower energy bills
- Avoided equipment replacement costs
- Improved profit margin for building owners
- Properly trained operational staff
- Operations and Maintenance manuals are compiled
correctly
50Building commissioning resources
- GAs Building Commissioning Program
www.ga.wa.gov/eas/bcx -
- Building Commissioning Association
- www.bcxa.org
51Thank You
- Ron Major
- Department of General Administration
- (360) 902-7197
- rmajor_at_ga.wa.gov