3Renovation
- 85 CD phase
- Acock submittal February 27
- Architectural, Engineering, FFE drawings
- 3 week review period
- Reviewers
- OSU Architects office, Physical Facilities,
UNITS, OIT, TP, others - Library Wes, Ryan, Exec, Renovation Committee
members
4Renovation (contd)
- Construction bidding in May
- Move out summer 2006
5Swing Space
- Sullivant Ackerman construction to begin soon
- Construction mostly complete in June
- Temp arrangements for EHS personnel
- Other Ackerman tenants
- MC café is open
- ME move out after August 2006
6Swing Space (contd)
- Sullivant Learning Commons near completion
- April 5 grand opening
7Move Planning
- Move Summer of 2006
- Two Moves
- Collections
- Bids being reviewed
- Offices
- Accelerated Moving
- Detailed schedule to be developed
8One of our move planning meetings!
9Instead, were really trying to focus in on the
schedule.
10General Schedule Collections
- June 2006
- Completion of Rare Books move to STX
- General Collection to Ackerman
- August
- Reference, Current Periodicals, Bound Journals
Videos to Sullivant - Reference, Govt Docs, MIC, MAP to Ackerman
11General Schedule Collections (continued)
- August
- Hilandar Research Library to Ackerman
- Area Studies to Ackerman
12General Schedule - Offices
- Late February/March
- EHS temporary moves for construction
- June
- Circulation, Bookstacks, Mail Services
- (phase 1) to Ackerman
- Rare Books (phase 1) to STX
13General Schedule Offices (continued)
- August
- Administrative Services to Ackerman, Sullivant
- Administration to Ackerman
- Area Studies to Ackerman
- Circulation Bookstacks (phase 2) to Ackerman,
Sullivant - EHS to Ackerman, Sullivant
- Hilandar Research Library to Ackerman
14General Schedule Offices (continued)
- August
- ILL to Ackerman, Sullivant
- Instruction to BUS
- IT to Ackerman, Sullivant, SEL
- Preservation to Ackerman
- Rare Books (phase 2) to Ackerman
- Reference, Govt Docs, MIC, MAPS to Ackerman
15General Schedule Offices (continued)
- August
- Reference, Periodicals to Sullivant
- Technical Services to Ackerman
16Office Move Preparations
- Planning meetings with Mover SP06
- Responsibilities of Mover
- Move all office and public area equipment and
furnishings - Provide boxes
- Tag items for relocation
- Responsibilities of Library Personnel
- Pack up office contents
- Contents in file cabinets, desks, etc
- Contents on bookshelves, shelving
- Move personal belongings
- Records Retention Guidelines
17Bus Service
18Monday-Friday Alt 1(bus circumnavigates
Buckeye Village)
19Monday-Friday Alt 2(bus stops at but does not
circumnavigate Buckeye Village)
20(No Transcript)
21Cost variables
- Variables quarter break service and summer
service. - Two extremes with cost estimates
- continuous service all year except official
University holidays - service only during the three main quarters -
fall, winter, and spring
22Costs, 2006-07
- Estimated cost up to 357,600 per year.
- Weekday 2 buses to run every 15 minutes.
- Weekend, break and summer weekday service
provided with 1 bus (30 minute service) for 51
weeks per year (50 weekends due to holidays) - Estimated cost up to 290,000 per year.
- Weekdays 2 buses to run every 15 minutes as noted
above. - Weekends 30 minute service.
- No summer service. No service during the four
"break" weeks between quarters
23Questions