Title: PROJECT MANAGEMENT
1PROJECT MANAGEMENT
- Outline
- What is project mean?
- Examples of projects
- Project Planning and Control
- Project Life Cycle
- Gantt Chart
- PERT/CPM
2What is Project?
- What is the different between normal business
activities and Project? - Project
- Unique, one time operations design to
accomplish a specific set of objectives in a
limited time frame.
3Examples of project
- Building a house
- Building a factory
- Add assembly line in the factory
- Merging to companies
- Managing political campaign
- Designing a new product
- Soft ware development
4Project Management
- Project
- Lengthy network of activities needed to complete
a major output. - Project Management
- Planning, execution, and controlling resources to
needed to complete the project. -
5Project Life Cycle
- Definition
- Why we need to start new project
- Feasibility Analysis (Cost, Benefit , risk of
under taking a project) - Planning
- Details of the work, estimates time, Human
resource and cost - Execution
- During which a project itself is done
- Termination
- During which closer is achieved
6Project Planning, Controlling and Scheduling
- Project Planning
- 1. Setting goals.
- 2. Defining the project.
- 3. Tying needs into timed project activities.
- 4. Organizing the team.
Before Project
7Project Planning, Controlling and Scheduling
- Project Scheduling
- 1. Tying resources to specific activities.
- 2. Relating activities to each other.
- 3. Updating and revising on regular basis.
8Project Planning, Controlling and Scheduling
- Project Controlling
- 1. Monitoring resources, costs, quality and
budgets. - 2. Revising and changing plans.
- 3. Shifting resources to meet demands.
During Project
9Work Breakdown Structure
10Project Control Gantt Chart
- The Gantt chart is a popular tool for planning
and scheduling simple project. - It enables a manager to initially schedule
project activities and then to monitor progress
over time by comparing planned progress to actual
progress
11Project Control Gantt Chart
a
b
a
c
b
d
c
d
d
12PERT and CPM
- PERT (program evaluation and review technique)
- U.S. Navy Special Projects Office (1958)
- Polaris missile project
- CPM (critical path method)
- J. E. Kelly of Remington-Rand and M. R. Walker of
Du Pont (1957) - Scheduling maintenance shutdowns of chemical
processing plants
13Questions answered by PERT/CPM
- When will the entire project be completed?
- What are the critical activities or tasks in the
project, that is, the ones that will delay the
entire project if they are late? - Which are the non-critical activities, that is,
the ones that can run late without delaying the
entire projects completion? - What is the probability that the project will be
completed by a specific date?
14Questions answered by PERT/CPM
- At any particular date, is the project on
schedule, behind schedule, or ahead of schedule? - On any given date, is the money spent equal to,
less than, or greater than the budgeted amount? - Are there enough resources available to finish
the project on time? - If the project is to be finished in a shorter
amount of time, what is the best way to
accomplish this at the least cost?
15To Find Critical Path ???
- To find the critical path, need to determine the
following quantities for each activity in the
network - 1. Earliest start time (ES) the earliest time an
activity can begin without violation of immediate
predecessor requirements. - 2. Earliest finish time (EF) the earliest time
at which an activity can end. - 3. Latest start time (LS) the latest time an
activity can begin without delaying the entire
project. - 4. Latest finish time (LF) the latest time an
activity can end without delaying the entire
project.
16CPM with Single Time Estimate
Consider the following consulting project
Develop a critical path diagram and determine
the duration of the critical path and slack times
for all activities
17When I can start depends on when predecessors
finish.
C, 1
18Dont delay the project
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C, 1
ES4 EF9
LS14 LF15
LS9 LF14
LS4 LF9
19Critical Path Slack
ES4 EF6
D, 2
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C, 1
ES4 EF9
LS14 LF15
LS9 LF14
E, 5
LS4 LF9
Duration 15 weeks
20CPM with Three Activity Time Estimates
21Expected Times
22PERT/ CPM
- CPM uses two sets of time and cost estimates for
activities - A normal time and cost and
- A crash time and cost
- The normal cost is an estimate of cost to
complete an activity in normal time. - The crash time is the shortest possible activity
time. - Crash cost is the cost of completing the activity
on a crash or deadline basis.
23Project Crashing with PERT/CPM Four Steps
- Find the normal critical path and identify the
critical activities. - Compute the crash cost per week (or other time
period) for all activities in the network. - This process uses the following formula
24Project Crashing with PERT/CPM Four Steps
- 3. Select the activity on the critical path with
the smallest crash cost per week. - Crash this activity to the maximum extent
possible or to the point at which your desired
deadline has been reached - 4. Check to be sure that the critical path you
were crashing is still critical. - Often, a reduction in activity time along the
critical path causes a non-critical path or paths
to become critical. - If the critical path is still the longest path
through the network, return to step 3. - If not, find the new critical path and return to
step 2.
25Subproject
- For extremely large projects, an activity may be
made of several smaller sub-activities. - Each activity might be viewed as a smaller
project or a subproject of the original project. - The person in charge of the activity might wish
to create a PERT/CPM chart for managing this
subproject. - Many software packages have the ability to
include several levels of subprojects