PROJECT MANAGEMENT - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

PROJECT MANAGEMENT

Description:

PROJECT MANAGEMENT Outline What is project mean? Examples of projects Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM 23 24 25 What is Project? – PowerPoint PPT presentation

Number of Views:83
Avg rating:3.0/5.0
Slides: 26
Provided by: amaiuPbw
Category:

less

Transcript and Presenter's Notes

Title: PROJECT MANAGEMENT


1
PROJECT MANAGEMENT
  • Outline
  • What is project mean?
  • Examples of projects
  • Project Planning and Control
  • Project Life Cycle
  • Gantt Chart
  • PERT/CPM

2
What is Project?
  • What is the different between normal business
    activities and Project?
  • Project
  • Unique, one time operations design to
    accomplish a specific set of objectives in a
    limited time frame.

3
Examples of project
  • Building a house
  • Building a factory
  • Add assembly line in the factory
  • Merging to companies
  • Managing political campaign
  • Designing a new product
  • Soft ware development

4
Project Management
  • Project
  • Lengthy network of activities needed to complete
    a major output.
  • Project Management
  • Planning, execution, and controlling resources to
    needed to complete the project.

5
Project Life Cycle
  • Definition
  • Why we need to start new project
  • Feasibility Analysis (Cost, Benefit , risk of
    under taking a project)
  • Planning
  • Details of the work, estimates time, Human
    resource and cost
  • Execution
  • During which a project itself is done
  • Termination
  • During which closer is achieved

6
Project Planning, Controlling and Scheduling
  • Project Planning
  • 1. Setting goals.
  • 2. Defining the project.
  • 3. Tying needs into timed project activities.
  • 4. Organizing the team.

Before Project
7
Project Planning, Controlling and Scheduling
  • Project Scheduling
  • 1. Tying resources to specific activities.
  • 2. Relating activities to each other.
  • 3. Updating and revising on regular basis.

8
Project Planning, Controlling and Scheduling
  • Project Controlling
  • 1. Monitoring resources, costs, quality and
    budgets.
  • 2. Revising and changing plans.
  • 3. Shifting resources to meet demands.

During Project
9
Work Breakdown Structure
10
Project Control Gantt Chart
  • The Gantt chart is a popular tool for planning
    and scheduling simple project.
  • It enables a manager to initially schedule
    project activities and then to monitor progress
    over time by comparing planned progress to actual
    progress

11
Project Control Gantt Chart
a
b
a
c
b
d
c
d
d
12
PERT and CPM
  • PERT (program evaluation and review technique)
  • U.S. Navy Special Projects Office (1958)
  • Polaris missile project
  • CPM (critical path method)
  • J. E. Kelly of Remington-Rand and M. R. Walker of
    Du Pont (1957)
  • Scheduling maintenance shutdowns of chemical
    processing plants

13
Questions answered by PERT/CPM
  • When will the entire project be completed?
  • What are the critical activities or tasks in the
    project, that is, the ones that will delay the
    entire project if they are late?
  • Which are the non-critical activities, that is,
    the ones that can run late without delaying the
    entire projects completion?
  • What is the probability that the project will be
    completed by a specific date?

14
Questions answered by PERT/CPM
  • At any particular date, is the project on
    schedule, behind schedule, or ahead of schedule?
  • On any given date, is the money spent equal to,
    less than, or greater than the budgeted amount?
  • Are there enough resources available to finish
    the project on time?
  • If the project is to be finished in a shorter
    amount of time, what is the best way to
    accomplish this at the least cost?

15
To Find Critical Path ???
  • To find the critical path, need to determine the
    following quantities for each activity in the
    network
  • 1. Earliest start time (ES) the earliest time an
    activity can begin without violation of immediate
    predecessor requirements.
  • 2. Earliest finish time (EF) the earliest time
    at which an activity can end.
  • 3. Latest start time (LS) the latest time an
    activity can begin without delaying the entire
    project.
  • 4. Latest finish time (LF) the latest time an
    activity can end without delaying the entire
    project.

16
CPM with Single Time Estimate
Consider the following consulting project
Develop a critical path diagram and determine
the duration of the critical path and slack times
for all activities
17
When I can start depends on when predecessors
finish.
C, 1
18
Dont delay the project
ES4 EF6
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C, 1
ES4 EF9
LS14 LF15
LS9 LF14
LS4 LF9
19
Critical Path Slack
ES4 EF6
D, 2
ES0 EF2
ES2 EF3
ES3 EF4
LS7 LF9
C, 1
ES4 EF9
LS14 LF15
LS9 LF14
E, 5
LS4 LF9
Duration 15 weeks
20
CPM with Three Activity Time Estimates
21
Expected Times
22
PERT/ CPM
  • CPM uses two sets of time and cost estimates for
    activities
  • A normal time and cost and
  • A crash time and cost
  • The normal cost is an estimate of cost to
    complete an activity in normal time.
  • The crash time is the shortest possible activity
    time.
  • Crash cost is the cost of completing the activity
    on a crash or deadline basis.

23
Project Crashing with PERT/CPM Four Steps
  • Find the normal critical path and identify the
    critical activities.
  • Compute the crash cost per week (or other time
    period) for all activities in the network.
  • This process uses the following formula

24
Project Crashing with PERT/CPM Four Steps
  • 3. Select the activity on the critical path with
    the smallest crash cost per week.
  • Crash this activity to the maximum extent
    possible or to the point at which your desired
    deadline has been reached
  • 4. Check to be sure that the critical path you
    were crashing is still critical.
  • Often, a reduction in activity time along the
    critical path causes a non-critical path or paths
    to become critical.
  • If the critical path is still the longest path
    through the network, return to step 3.
  • If not, find the new critical path and return to
    step 2.

25
Subproject
  • For extremely large projects, an activity may be
    made of several smaller sub-activities.
  • Each activity might be viewed as a smaller
    project or a subproject of the original project.
  • The person in charge of the activity might wish
    to create a PERT/CPM chart for managing this
    subproject.
  • Many software packages have the ability to
    include several levels of subprojects
Write a Comment
User Comments (0)
About PowerShow.com