Title: Proton Driver Options Cost Comparison
1Proton Driver OptionsCost Comparison
- Rich Stanek
- March 15 , 2005
2Outline
- Goal of the Comparison
- History of the Numbers
- Methodology Cost Estimating Approach
- Results Comparing the Estimates
- Cost Drivers
- Observations Contingency Range of Values
- Conclusions
3Goal of the Comparison
- Provide a fair and consistent cost comparison
between the Linac and Synchrotron PD options - Independent of technical or physics related
issues - Consistent level of estimation and detail for
each option - Use the same labor rates, /sf for buildings and
data format/cost roll up - Assemble a reasonable level of back up
documentation (Basis of Estimate) for both cost
estimates - Understand the Range of Values for the cost of
a PD - Provide the starting point/basis for the final PD
cost estimate - NOTE Costs are shown in FY04 dollars and
without GA charges unless specifically noted - GA and Contingency are added at the highest
level
4History of the Numbers (Synchrotron)
- PD I Study done for a 16 GeV Proton Driver (2000)
- PD II Study reduced the energy to 8 GeV and added
a SC Linac option (2002) - Much of the PD II Sync cost estimate was scaled
from the original PD I numbers but then adjusted
to include a replacement of the existing Front
End Linac (Directors Charge Letter) - Familiarity of FNAL personnel with building
synchrotron machines and how things scale, helped
this estimate maintain its accuracy - The Synchrotron cost estimate has not had the
same level of recent cost peer review nor working
group participation as has the Linac cost
estimate - (Synchrotron technical design has been reviewed)
5History of the Numbers (Linac)
- Linac options initial cost estimate relied
heavily on scaling from TESLA and SNS numbers
with appropriate modification for technical
differences - As a core project team was formed, the Linac
estimate was further refined and developed by
forming Working Groups and performing cost
exercises (ex. Civil Working Group gt meets
weekly and cryomodule cost estimate exercise gt
resulted in RFQ) - Experience based on FNAL/TESLA/SNS actuals was
used where applicable
6Cost Estimating Approach
- Take a conservative approach to estimating the
costs of the PD (defendable numbers) - Cost estimators started out with the knowledge
that an overall contingency was going to be added
to the entire project cost (30 across the
board)gt some subsystems added scope contingency
as part of their input estimates - Cost estimates cover components up to and
including injection into the Main Injector. - Cost of the Main Injector Upgrades (ex. RF
Upgrades) was not included in either cost
estimate - Assumption is that as the PD project moves
forward and detail designs are further developed
it will go through a Value Engineering stage
where technical/cost trade-offs will be evaluated
and a true contingency and risk matrix will be
adopted
7Maintaining the Accuracy
- Each option had a primary contact
- Synchrotron gt Weiren Chou
- Linac gt Bill Foster
- This allowed for a reasonable level of checks
and balances in the comparison effort - Tried to use the same people to make estimates
for both systems (where applicable)
8Methodology
- Evaluate documentation that was compiled for the
PD II Study gt the starting point - Put both estimates into a common form (Excel)
using common costs where possible (labor rates
based on TD actual averages and BTeV values) - Improve the accuracy of the estimates
- Look for holes/missing items
- Look for obvious errors in the estimates
- Look for inconsistencies between the two options
- gt Led to new estimates for several key
components - Compare the two options (escalate old est. to
2004) - Perform reality checks internal review
9Cost Comparison - High Level
Most of the initial installation work will be
Davis Bacon and shows up as MS costs GA rate
will be less on large purchasing actions
10Comparing the Estimates
- Civil Construction
- Both use the same format of estimation (FESS
std.) - Linac is an all new estimate gt based on new
location - Includes more detail in terms of exact
routing/requirements - Synchrotron is a mixture of new/old estimates
- Old estimates (2002) were escalated to 2004
(using DOE Guidelines) - Use the same /sf for new/similar buildings
- Both use construction techniques very familiar to
FNAL - Site choices made to allow ease of accelerator
ops and future growth - Linac option has had external consultant look at
feeder req. - Sync placement is in close proximity to existing
infrastructure - Has both positive and negative implications
- Should make it easier to tap into existing
utilities - May have more of an impact on current operations
11Comparing the Estimates (contd)
- Linac/Front End Improvements
- Both only have high level estimates
- Based on TESLA, SNS, FNAL Linac Upgrade or vendor
communication - Magnets (Main Synchrotron and all transport
lines) - Both Based on FNAL/TD estimates (using std.
methodology which has been accurate in the past)
gt use current steel and conductor prices - Sync gt RD of rapid cycling, large aperture
magnets not included - Both assume existing MTF (conventional) is fully
operational - Utilities
- Linac gt new estimate based on conceptual design
FNAL experience - Sync gt scaled from MI actuals/modified using
FNAL experience - Power Supplies RF Equipment
- Both based on FNAL experience, purchase orders
and vendor quotes - Linac/Klystrons gt uses costs from recent TESLA
purchase orders
12Comparing the Estimates (contd)
- Cryomodules (Linac)
- Based on vendor RFQ (55 of MS est.) and
TESLA/SNS experience - Assembly estimates use TESLA LHC Project
actuals - Assumes CM assembly infrastructure in place
(synergy with SMTF/ILC) - Modulators Pulse Transformers (Linac)
- Based on actuals for equipment supplied by FNAL
to TESLA (TTF) - Modified to take into account quantity/price
reduction - Instrumentation Controls
- Sync estimated down to individual components
- Linac contains estimates at a high level
(beginning to get more detail) - Infrastructure Integration
- Often neglected when estimating individual
subsystems - Both used equal estimates (high level) where
applicable - Most of the initial installation will be
Davis-Bacon work
13Comparing the Estimates (contd)
- RD Costs
- Linac cost estimate assumes that the
infrastructure to test cavities and build
cryomodules will be in place either at FNAL or at
other collaborating Labs (ex. LANL/ANL for spoke
cavities) at the start of the Project gt synergy
with SMTF and ILC RD project - Therefore the cost to set up these facilities is
not included - Linac effort will continue to take advantage of
ongoing work at SNS, TESLA TTF and other SCRF
facilities - Synchrotron assumes the RD to develop rapid
cycling, wide aperture magnets and power supplies
will be completed before the start of the Project - gt Therefore the cost to perform this work is not
included
14PD Option Cost Comparison
15Cost Drivers
- Synchrotron K
- Civil Construction 64,710 (26.5)
- Magnet System 40,841 (16.7)
- Linac Improvements 34,564 (14.2)
- Power Supply Network 30,921 ( 12.7)
- Linac
- Cryomodules 101,608 (31.9)
- Civil Construction 81,168 (25.5)
- Cryogenic System 28,589 ( 9.0)
- RF Klystrons Distribution 25,171 ( 8.2)
16Synchrotron Cost Drivers
17Linac Cost Drivers
18Ratio of SWF/MS
Includes contracted EDIA for Civil Engineering
Design
19Reality Checks
- Main Injector Project vs. Linac PD Estimate
- 230M gt escalated to 2004 273M PD 319M
- Project Management gt 5.8 PD 7.8
- Civil/Total Costs 44.8 PD 25.4
- Technical Sys./Total Costs 49.4 PD 67
- SWF/MS Costs 22.6 PD 38.8
- SNS (estimate)
- SNS Linac cost 550-600M (1.5 MW power)
20Observations
- There is a difference in the level of recent
detail attention given to the two PD options
and the approach taken when estimating. However,
both options were initially given an across the
board 30 contingency (for consistency reasons) - This way of estimating contingency for the
overall project is somewhat arbitrary and does
not reflect either the technical risk of the
individual components nor the conservatism of the
estimates - The actual contingency analysis will do just that
- Look at another methodology which focuses on a
Range of Values for the cost of each option
gt reflects the confidence/uncertainty of
the estimate
21Synchrotron Cost Estimate Analysis
22Linac Cost Estimate Analysis
23Range of Values
Linac
Sync
24Conclusions
- A fair and consistent cost comparison was
performed between the two Proton Driver Options
(Synchrotron SC Linac) - A Basis of Estimate was established for both cost
estimates that draws on relevant experience with
similar equipment both at FNAL and other Labs - This cost estimate will be a solid starting point
for additional cost and schedule work that will
be performed as the PD project moves forward - Range of Values for the cost estimate of a Proton
Driver to be built at FNAL is approximately 400M
to 500M (including contingency and GA)