Title: Beyond regulation
1Beyond regulation
- Stephen Littlechild
- ESNIE Cargese, Corsica
- 16 May 2006
2Outline
- The regulation literature some elements
- Other possible arrangements what are they and
how do they work in practice? - Transmission regulation in Australia
- And in Argentina
- Settlements in Florida
- And in Canada
- Conclusions and further research
3Regulation literature
4The early regulation literature
- Early discussions C18, C19
- Smith, Mill, Pareto, Marshall, many others
- Institutional economists C19 early C20
- Commons et al in US, others in Germany
- Economic theory (welfare economics)
- Pigou, Lerner UK 1930s, 1940s, Hotelling US 1938
- Engineering
- Dupuit mid C19, Boiteux at EdF in France 1950s
5Later regulation literature
- The traditional regulatory process 1950s 1960s
- Bonbright, Phillips, Trebing
- The economics of regulation marginal cost
pricing second-best 1950s, 1960s - Baumol, Graaff, Little, Lipsey Lancaster
- Kahn 1970 economic theory regulatory practice
- Mathematical optimisation models 1960s, 1970s
- Peakload pricing Steiner, Hirshleifer,
Williamson, Littlechild - Optimal prices emerge as dual variables in
optimisation models extend to depreciation and
uncertainty - Cooperative game theory models to share common
costs - Aim to characterise optimal pricing and
investment policies
6Modern regulation literature 1
- Extension of optimisation models
- Constrained optimisation
- Alternative objective functions
- Extensions to uncertainty
- Non-cooperative game theory
- Partial and general equilibrium models
- Extensive theoretical literature
- Generally from a normative perspective
- What ought the regulator to do?
7Alternative paradigms
- Economic sceptics re marginal cost pricing
- Coase 1946, 1970 blackboard economics v
institutions - Wiseman 1957 empty box
- How does regulation actually work?
- Averch Johnson 1962 distortions in practice
- Stigler Friedland 1962 what effect of
regulation? - Public choice economics regulatory objectives
and political pressures, what kinds of regulation
actually adopted - J of Law and Economics (ed. Coase)
- Austrian economics
- Imperfect knowledge, uncertainty, change,
information, discovery, incentives, competitive
market process - How should regulation reflect these ideas?
8Modern regulatory literature 2
- Modern institutional economics
- Coase on regulation (as above), theory of firm,
social cost, transactions cost etc - Williamson on satisficing, transactions costs,
governance of contractual relations, markets
hierarchies, vertical integration - Demsetz on property rights economic
organisation - Joskow on regulation in practice, vertical
integration contracts
9Modern regulatory literature 3
- US UK theory practice re incentives
- UK utility privatisations 1980s
- Competition can replace some regulation
- What kind of regulation until competition?
- Littlechild report 1983 RPI-X incentive
regulation instead of US rate of return - Widely adopted internationally
- Emphasis from allocative to productive efficiency
- Economic literature on incentive regulation
- Laffont and Tirole combines with earlier
theoretical work
10Summary of regulation literature
- A long history of economic analysis
- One theme formal optimisation models
- Another theme how regulation actually works
- A third theme incentive regulation
- All these analyses assume that regulation is
necessary where there is monopoly - Aim to replicate outcome if competition possible?
- The regulator makes/influences the decisions
- Perhaps considering views of other parties
- But they do not have a central or decisive role
11Regulatory decision-making
- Alternative arrangements?
12Regulatory decision-making
- If regulation replicates a competitive market,
how to decide for market participants? - E.g. how much investment in security of supply
would customers be willing to pay for? - How does the regulator know this?
- Has to make judgements on their behalf
- In practice, one size has to fit all
- UK electricity sector a dozen similar companies
- All had to have same kind of price control
- Too difficult to justify variations by company
- Consequent lack of variety and experimentation
- No learning process from different experiences
- This is different from the competitive market
process
13Alternative regulatory models
- Must the regulator take all the decisions?
- Is there scope to allow market participants to
make more decisions? - Deregulated markets now allow competition
- But what if there is still monopoly?
- How do such alternative systems work?
- What difference do they make?
- What are their pros and cons?
14Some cases studied
- Transmission expansion in Australia Argentina
- Australia Merchant transmission companies are
allowed to compete with incumbent transmission
monopolies - Argentina Transmission expansion decisions have
to be proposed, approved and paid for by market
participants, not by regulator or transco - Settlements in US especially Florida
- Instead of traditional litigated process,
settlements are often reached between utilities
and Public Counsel and/or users, and are
typically approved by regulator - To understand how do these alternatives work?
15Transmission expansion
- Alternative regulatory arrangements
16Transmission expansion
- Traditional regulated approach
- TransCo decides what to build and when
- Some regulatory input before or after
- Remunerated via return on rate base
- Merchant transmission now proposed
- Independent investor decides what when to build
- No need for regulatory input?
- Remunerated by charging users
- Is merchant possible? Which is better?
17Concerns about merchant
- Alleged difficulties involved
- Needs property rights on transmission lines
- Needs nodal prices these do not always exist
- Externalities and economies of scale
- Market power and incentive to undersize
- Problems of integrating with existing network
- Allegations
- Merchant transmission may not be possible
- Would be too little too late
- And likely to be other problems
18Counterarguments
- Arguments for merchant transmission
- Quicker to respond to market signals
- Better incentive to more efficient capex and opex
- Potential problems with regulated transmission
- Regulation does not ensure optimality
- Utilities have incentive to gold plate
- Regulators concerned to avoid capacity shortages
- So regulation could mean too much too soon
- Hence need to establish how the two systems
operate in practice
19Evidence?
- Any evidence of how regulated and merchant
investment works in practice? - Yes - interconnectors in Australia
- Both regulated and merchant lines exist
- Special case of transmission 2 nodes
- fewer problems market prices already available
- little problem to integrate with rest of network
- How have they worked in practice?
20Australia
- Evidence on alternative regulatory arrangements
for transmission expansion
21Australian background
- Until 1990s, each Australian state government
owned its electricity system - little interconnection between them
- decision-making from political perspective
- 1996 National Electricity Market NEM
- Australian Competition and Consumer Commission
ACCC now regulates transmission - Potential culture clash?
22Two interconnectors
- 1994 proposed interconnector between South
Australia and NSW called SANI later SNI - 1997 Independent study found it economic
- 1998 did not pass customer benefits test
- 1999 Murraylink merchant line announced
- Similar capacity and route to regulated SNI
- 2001 revised SNI passed regulatory test
- Murraylink appealed to Appeals Tribunal
- 2002 Aug Tribunal hearings, M-link onstream
- 2002 Oct Tribunal decision
23Is SNI economic?
- SNI interconnector network reinforcement
- TransGrid consultants IES quantified costs and
benefits - NPV Benefits and costs (Am NPV) of SNI projects
- SNI Network Interconnector
-
(extra) - Benefits 264.5 351.4 -86.9
- Costs -98.4 -41.2 -57.2
- Net Benefit 166.1 310.2 -144.1
- My testimony Network reinforcement is economic
- But duplicate interconnector is not economic
24Arguments at Tribunal
- Transgrid
- Murraylink would have market power
- So could and would restrict output
- Hence risk that network reinforcement underused
- So cannot do network reinforcement alone
- Murraylink
- Murraylink would not have significant market
power - Negligible restriction of network use (0.013)
- Tribunal majority decision Dec 2002
- Real risk of stranding so upheld regulatory
decision - Murraylink took to Judicial review
- Jul 2003 0.013 not a real risk appeal upheld
25Conversion to regulated status
- Meanwhile price differentials narrowed
- Murraylink less profitable than expected?
- Oct 2002 Murraylink applied for conversion to
regulated status - ACCC allowed at half Murraylinks proposed figure
- Nov 2003 Murraylink accepted
26Conclusions on Australia
- Merchant investment may have flaws
- Misjudged market built too much too soon
- But losses borne by investors not customers
- And company learned from experience
- Australian regulatory process flawed too
- Delay, cost and political influence
- poor economic analysis (including Tribunal)
- legal errors (c.f. Court view of Tribunal)
- unjustified stance by transmission company
- regulated investment too much too soon at
customer expense, any learning from experience?
27Argentina
- Evidence on alternative regulatory arrangements
for transmission expansion
28Argentina background
- Argentina electricity reform 1992
- restructuring, privatisation, competition,
incentive regulation of existing T and D networks - Mistrust of regulation
- Decided that transco regulator should not be
responsible for transmission expansions - Public Contest method
- Users to propose, vote pay for major expansions
- Construction OM (COM) out to competitive tender
29Received view of experience
- Argentine electricity reform worked well
- lower costs prices, better service, more
investment - But major caveat method of regulating
transmission expansion did not work well - Claimed externalities, free riders, transactions
costs - But only one illustration of this
- Several years delay to much needed Fourth Line
from Comahue (major generation source) to Buenos
Aires (major demand centre)
30(No Transcript)
31Fourth Line
- Congestion increasing on this corridor
- Sept 1994 3 generators proposed 4th Line
- COM fee about 58m p.a. over 15 years
- Public hearing Feb 1995 50 vote against
- Surprise and concern, including by regulator
- May 1996 revised proposal - accepted
- Max fee 44m pa 11m Salex 55m
- Nov 1997 winning bid 24.5m 11m 35.5m
32Benefits costs of 4th line
- Ave congestion revenue 30m p.a.
- Capacity increase 1/3
- Benefit 1/3 x 30m 10m p.a.
- Cost
- First proposal 58m p.a.
- Second proposal 24.5 11 35.5m p.a
- Conclusion 4th Line was not economic
- Delay was socially beneficial, not costly
- Cheaper to locate generation near demand instead
- None of alleged problems materialised here
- Public contest method worked well in other cases
33Competition in construction
- Bidding competitive 2-3 bids in 5 cases
- All these won by new independent cos
- 4th Line 4 bidders 13 bids (alternatives)
- innovative technologies introduced
- Cost reductions over time
- pre-reform at least 230k/km
- 1st 2nd tenders (Govt) 267k/km, 170k/km
- 4th Line 130k/km - so cost/km about halved
- Bidding to construct was very successful
34Assessment of Argentine policy
- Public Contest method in fact worked well
- Made better use of existing lines
- Competitive tendering lowered costs
- 4th line delay not a failure of PC method
- Regulation would have yielded to political
pressures to build many uneconomic lines - PC method resisted political pressure
- Led to more economic outcomes than regulation
- Preferable if aim is efficient allocation of
resources
35Negotiated settlements
- US origins and early perceptions
36Origin of negotiated settlements
- Large backlog of rate cases at Federal Power
Commission (FPC) in 1960s - 1960 over 2900 applications, 10 dealt with
- 1960 3200 requests, triple staff would take 82
yrs - FPC encouraged settlement
- 1960-70 some or all of 56 cases
- saved time and money, reduced uncertainty
- some concerns about non-consenting parties (slow
down process?) non-participants (overlooked?) - Assumed settlement easier way to same end
37Settlements at FERC
- Successor FERC continued FPC policy
- Federal Energy Regulatory Commission
- 1980 70 of gas pipeline rate cases settled
- Wang (2004) 41 cases 1994-2000
- 34 settled in full, 5 settled in part, 2
litigated - savings in cost reductions in uncertainty
minimal - Settlement different process outcomes
- looked at situation as whole, not item by item
- more innovative outcomes not available to FERC
- especially rate moratoria 21 of 39 settlements
38Florida
- Evidence on nature of stipulations and settlements
39Regulation in Florida
- Public Service Commission FPSC 1897
- 386 staff, budget 27m
- Office of Public Counsel OPC 1974
- single incumbent Public Counsel 25 years
- duty to represent the general public of Florida
- staff 15, budget 2.5m plus consultants
- Scepticism about US consumer advocates
- limited effect? tend to favour larger users?
40FPSC rate cases
41Stipulated settlements in Florida
- Public Counsel represents customers
- by challenging utility in regulatory hearings
- also by negotiating stipulated settlements with
utility, then inviting FPSC to approve - FPSC staff not now involved in talks
- All stipulations were accepted in total, no
cherry-picking (unlike California)
42Types of case where OPC signed stipulations,
1976-2002
43Florida PSC earnings review cases 1976-2002
44FPSC rate cases and OPC stipulations
45Who benefits?
- Cost savings relatively small (lt1 value)
- Customers bigger and earlier rate reductions
- note staff/FPSC views lack of reduction before
- Confirm larger users benefit more in some ways
- Utilities less uncertainty embarrassment?
- Utilities get what FPSC could/would not give
- e.g. Removal of objection by others to merger
- Flexibility on accounting provisions
(depreciation) - Revenue sharing (not profit caps or earnings
sharing) - often despite objections of regulatory staff
46Conclusions on Florida
- OPC stipulations are significant in Florida
- 77 of rate reductions since 1976
- They benefit customers
- OPC got greater earlier rate reductions
- especially for industrial electricity customers
- but residential customers still benefit overall
- And lead to changes in regulatory policy
- More flexibility on depreciation etc than
staff/FPSC - More innovative forms of incentive regulation
47Conclusions
48Conclusions
- Many economic analyses assume that monopoly
necessitates regulation - And that regulator will replicate competitive
market - But there are examples where market participants
play a major role - Australia, Argentina, FERC, Florida (also Canada)
- These systems actually work well
- better than widely believed
- The outcomes are different from regulation
- And often more economic, better for most parties
- Scope to encourage elsewhere and research