Beyond regulation - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

Beyond regulation

Description:

Alleged difficulties involved. Needs property rights on transmission lines ... None of alleged problems materialised here. Public contest method worked well in ... – PowerPoint PPT presentation

Number of Views:70
Avg rating:3.0/5.0
Slides: 49
Provided by: Little6
Category:

less

Transcript and Presenter's Notes

Title: Beyond regulation


1
Beyond regulation
  • Stephen Littlechild
  • ESNIE Cargese, Corsica
  • 16 May 2006

2
Outline
  • The regulation literature some elements
  • Other possible arrangements what are they and
    how do they work in practice?
  • Transmission regulation in Australia
  • And in Argentina
  • Settlements in Florida
  • And in Canada
  • Conclusions and further research

3
Regulation literature
4
The early regulation literature
  • Early discussions C18, C19
  • Smith, Mill, Pareto, Marshall, many others
  • Institutional economists C19 early C20
  • Commons et al in US, others in Germany
  • Economic theory (welfare economics)
  • Pigou, Lerner UK 1930s, 1940s, Hotelling US 1938
  • Engineering
  • Dupuit mid C19, Boiteux at EdF in France 1950s

5
Later regulation literature
  • The traditional regulatory process 1950s 1960s
  • Bonbright, Phillips, Trebing
  • The economics of regulation marginal cost
    pricing second-best 1950s, 1960s
  • Baumol, Graaff, Little, Lipsey Lancaster
  • Kahn 1970 economic theory regulatory practice
  • Mathematical optimisation models 1960s, 1970s
  • Peakload pricing Steiner, Hirshleifer,
    Williamson, Littlechild
  • Optimal prices emerge as dual variables in
    optimisation models extend to depreciation and
    uncertainty
  • Cooperative game theory models to share common
    costs
  • Aim to characterise optimal pricing and
    investment policies

6
Modern regulation literature 1
  • Extension of optimisation models
  • Constrained optimisation
  • Alternative objective functions
  • Extensions to uncertainty
  • Non-cooperative game theory
  • Partial and general equilibrium models
  • Extensive theoretical literature
  • Generally from a normative perspective
  • What ought the regulator to do?

7
Alternative paradigms
  • Economic sceptics re marginal cost pricing
  • Coase 1946, 1970 blackboard economics v
    institutions
  • Wiseman 1957 empty box
  • How does regulation actually work?
  • Averch Johnson 1962 distortions in practice
  • Stigler Friedland 1962 what effect of
    regulation?
  • Public choice economics regulatory objectives
    and political pressures, what kinds of regulation
    actually adopted
  • J of Law and Economics (ed. Coase)
  • Austrian economics
  • Imperfect knowledge, uncertainty, change,
    information, discovery, incentives, competitive
    market process
  • How should regulation reflect these ideas?

8
Modern regulatory literature 2
  • Modern institutional economics
  • Coase on regulation (as above), theory of firm,
    social cost, transactions cost etc
  • Williamson on satisficing, transactions costs,
    governance of contractual relations, markets
    hierarchies, vertical integration
  • Demsetz on property rights economic
    organisation
  • Joskow on regulation in practice, vertical
    integration contracts

9
Modern regulatory literature 3
  • US UK theory practice re incentives
  • UK utility privatisations 1980s
  • Competition can replace some regulation
  • What kind of regulation until competition?
  • Littlechild report 1983 RPI-X incentive
    regulation instead of US rate of return
  • Widely adopted internationally
  • Emphasis from allocative to productive efficiency
  • Economic literature on incentive regulation
  • Laffont and Tirole combines with earlier
    theoretical work

10
Summary of regulation literature
  • A long history of economic analysis
  • One theme formal optimisation models
  • Another theme how regulation actually works
  • A third theme incentive regulation
  • All these analyses assume that regulation is
    necessary where there is monopoly
  • Aim to replicate outcome if competition possible?
  • The regulator makes/influences the decisions
  • Perhaps considering views of other parties
  • But they do not have a central or decisive role

11
Regulatory decision-making
  • Alternative arrangements?

12
Regulatory decision-making
  • If regulation replicates a competitive market,
    how to decide for market participants?
  • E.g. how much investment in security of supply
    would customers be willing to pay for?
  • How does the regulator know this?
  • Has to make judgements on their behalf
  • In practice, one size has to fit all
  • UK electricity sector a dozen similar companies
  • All had to have same kind of price control
  • Too difficult to justify variations by company
  • Consequent lack of variety and experimentation
  • No learning process from different experiences
  • This is different from the competitive market
    process

13
Alternative regulatory models
  • Must the regulator take all the decisions?
  • Is there scope to allow market participants to
    make more decisions?
  • Deregulated markets now allow competition
  • But what if there is still monopoly?
  • How do such alternative systems work?
  • What difference do they make?
  • What are their pros and cons?

14
Some cases studied
  • Transmission expansion in Australia Argentina
  • Australia Merchant transmission companies are
    allowed to compete with incumbent transmission
    monopolies
  • Argentina Transmission expansion decisions have
    to be proposed, approved and paid for by market
    participants, not by regulator or transco
  • Settlements in US especially Florida
  • Instead of traditional litigated process,
    settlements are often reached between utilities
    and Public Counsel and/or users, and are
    typically approved by regulator
  • To understand how do these alternatives work?

15
Transmission expansion
  • Alternative regulatory arrangements

16
Transmission expansion
  • Traditional regulated approach
  • TransCo decides what to build and when
  • Some regulatory input before or after
  • Remunerated via return on rate base
  • Merchant transmission now proposed
  • Independent investor decides what when to build
  • No need for regulatory input?
  • Remunerated by charging users
  • Is merchant possible? Which is better?

17
Concerns about merchant
  • Alleged difficulties involved
  • Needs property rights on transmission lines
  • Needs nodal prices these do not always exist
  • Externalities and economies of scale
  • Market power and incentive to undersize
  • Problems of integrating with existing network
  • Allegations
  • Merchant transmission may not be possible
  • Would be too little too late
  • And likely to be other problems

18
Counterarguments
  • Arguments for merchant transmission
  • Quicker to respond to market signals
  • Better incentive to more efficient capex and opex
  • Potential problems with regulated transmission
  • Regulation does not ensure optimality
  • Utilities have incentive to gold plate
  • Regulators concerned to avoid capacity shortages
  • So regulation could mean too much too soon
  • Hence need to establish how the two systems
    operate in practice

19
Evidence?
  • Any evidence of how regulated and merchant
    investment works in practice?
  • Yes - interconnectors in Australia
  • Both regulated and merchant lines exist
  • Special case of transmission 2 nodes
  • fewer problems market prices already available
  • little problem to integrate with rest of network
  • How have they worked in practice?

20
Australia
  • Evidence on alternative regulatory arrangements
    for transmission expansion

21
Australian background
  • Until 1990s, each Australian state government
    owned its electricity system
  • little interconnection between them
  • decision-making from political perspective
  • 1996 National Electricity Market NEM
  • Australian Competition and Consumer Commission
    ACCC now regulates transmission
  • Potential culture clash?

22
Two interconnectors
  • 1994 proposed interconnector between South
    Australia and NSW called SANI later SNI
  • 1997 Independent study found it economic
  • 1998 did not pass customer benefits test
  • 1999 Murraylink merchant line announced
  • Similar capacity and route to regulated SNI
  • 2001 revised SNI passed regulatory test
  • Murraylink appealed to Appeals Tribunal
  • 2002 Aug Tribunal hearings, M-link onstream
  • 2002 Oct Tribunal decision

23
Is SNI economic?
  • SNI interconnector network reinforcement
  • TransGrid consultants IES quantified costs and
    benefits
  • NPV Benefits and costs (Am NPV) of SNI projects
  • SNI Network Interconnector

  • (extra)
  • Benefits 264.5 351.4 -86.9
  • Costs -98.4 -41.2 -57.2
  • Net Benefit 166.1 310.2 -144.1
  • My testimony Network reinforcement is economic
  • But duplicate interconnector is not economic

24
Arguments at Tribunal
  • Transgrid
  • Murraylink would have market power
  • So could and would restrict output
  • Hence risk that network reinforcement underused
  • So cannot do network reinforcement alone
  • Murraylink
  • Murraylink would not have significant market
    power
  • Negligible restriction of network use (0.013)
  • Tribunal majority decision Dec 2002
  • Real risk of stranding so upheld regulatory
    decision
  • Murraylink took to Judicial review
  • Jul 2003 0.013 not a real risk appeal upheld

25
Conversion to regulated status
  • Meanwhile price differentials narrowed
  • Murraylink less profitable than expected?
  • Oct 2002 Murraylink applied for conversion to
    regulated status
  • ACCC allowed at half Murraylinks proposed figure
  • Nov 2003 Murraylink accepted

26
Conclusions on Australia
  • Merchant investment may have flaws
  • Misjudged market built too much too soon
  • But losses borne by investors not customers
  • And company learned from experience
  • Australian regulatory process flawed too
  • Delay, cost and political influence
  • poor economic analysis (including Tribunal)
  • legal errors (c.f. Court view of Tribunal)
  • unjustified stance by transmission company
  • regulated investment too much too soon at
    customer expense, any learning from experience?

27
Argentina
  • Evidence on alternative regulatory arrangements
    for transmission expansion

28
Argentina background
  • Argentina electricity reform 1992
  • restructuring, privatisation, competition,
    incentive regulation of existing T and D networks
  • Mistrust of regulation
  • Decided that transco regulator should not be
    responsible for transmission expansions
  • Public Contest method
  • Users to propose, vote pay for major expansions
  • Construction OM (COM) out to competitive tender

29
Received view of experience
  • Argentine electricity reform worked well
  • lower costs prices, better service, more
    investment
  • But major caveat method of regulating
    transmission expansion did not work well
  • Claimed externalities, free riders, transactions
    costs
  • But only one illustration of this
  • Several years delay to much needed Fourth Line
    from Comahue (major generation source) to Buenos
    Aires (major demand centre)

30
(No Transcript)
31
Fourth Line
  • Congestion increasing on this corridor
  • Sept 1994 3 generators proposed 4th Line
  • COM fee about 58m p.a. over 15 years
  • Public hearing Feb 1995 50 vote against
  • Surprise and concern, including by regulator
  • May 1996 revised proposal - accepted
  • Max fee 44m pa 11m Salex 55m
  • Nov 1997 winning bid 24.5m 11m 35.5m

32
Benefits costs of 4th line
  • Ave congestion revenue 30m p.a.
  • Capacity increase 1/3
  • Benefit 1/3 x 30m 10m p.a.
  • Cost
  • First proposal 58m p.a.
  • Second proposal 24.5 11 35.5m p.a
  • Conclusion 4th Line was not economic
  • Delay was socially beneficial, not costly
  • Cheaper to locate generation near demand instead
  • None of alleged problems materialised here
  • Public contest method worked well in other cases

33
Competition in construction
  • Bidding competitive 2-3 bids in 5 cases
  • All these won by new independent cos
  • 4th Line 4 bidders 13 bids (alternatives)
  • innovative technologies introduced
  • Cost reductions over time
  • pre-reform at least 230k/km
  • 1st 2nd tenders (Govt) 267k/km, 170k/km
  • 4th Line 130k/km - so cost/km about halved
  • Bidding to construct was very successful

34
Assessment of Argentine policy
  • Public Contest method in fact worked well
  • Made better use of existing lines
  • Competitive tendering lowered costs
  • 4th line delay not a failure of PC method
  • Regulation would have yielded to political
    pressures to build many uneconomic lines
  • PC method resisted political pressure
  • Led to more economic outcomes than regulation
  • Preferable if aim is efficient allocation of
    resources

35
Negotiated settlements
  • US origins and early perceptions

36
Origin of negotiated settlements
  • Large backlog of rate cases at Federal Power
    Commission (FPC) in 1960s
  • 1960 over 2900 applications, 10 dealt with
  • 1960 3200 requests, triple staff would take 82
    yrs
  • FPC encouraged settlement
  • 1960-70 some or all of 56 cases
  • saved time and money, reduced uncertainty
  • some concerns about non-consenting parties (slow
    down process?) non-participants (overlooked?)
  • Assumed settlement easier way to same end

37
Settlements at FERC
  • Successor FERC continued FPC policy
  • Federal Energy Regulatory Commission
  • 1980 70 of gas pipeline rate cases settled
  • Wang (2004) 41 cases 1994-2000
  • 34 settled in full, 5 settled in part, 2
    litigated
  • savings in cost reductions in uncertainty
    minimal
  • Settlement different process outcomes
  • looked at situation as whole, not item by item
  • more innovative outcomes not available to FERC
  • especially rate moratoria 21 of 39 settlements

38
Florida
  • Evidence on nature of stipulations and settlements

39
Regulation in Florida
  • Public Service Commission FPSC 1897
  • 386 staff, budget 27m
  • Office of Public Counsel OPC 1974
  • single incumbent Public Counsel 25 years
  • duty to represent the general public of Florida
  • staff 15, budget 2.5m plus consultants
  • Scepticism about US consumer advocates
  • limited effect? tend to favour larger users?

40
FPSC rate cases
41
Stipulated settlements in Florida
  • Public Counsel represents customers
  • by challenging utility in regulatory hearings
  • also by negotiating stipulated settlements with
    utility, then inviting FPSC to approve
  • FPSC staff not now involved in talks
  • All stipulations were accepted in total, no
    cherry-picking (unlike California)

42
Types of case where OPC signed stipulations,
1976-2002
43
Florida PSC earnings review cases 1976-2002
44
FPSC rate cases and OPC stipulations
45
Who benefits?
  • Cost savings relatively small (lt1 value)
  • Customers bigger and earlier rate reductions
  • note staff/FPSC views lack of reduction before
  • Confirm larger users benefit more in some ways
  • Utilities less uncertainty embarrassment?
  • Utilities get what FPSC could/would not give
  • e.g. Removal of objection by others to merger
  • Flexibility on accounting provisions
    (depreciation)
  • Revenue sharing (not profit caps or earnings
    sharing)
  • often despite objections of regulatory staff

46
Conclusions on Florida
  • OPC stipulations are significant in Florida
  • 77 of rate reductions since 1976
  • They benefit customers
  • OPC got greater earlier rate reductions
  • especially for industrial electricity customers
  • but residential customers still benefit overall
  • And lead to changes in regulatory policy
  • More flexibility on depreciation etc than
    staff/FPSC
  • More innovative forms of incentive regulation

47
Conclusions
48
Conclusions
  • Many economic analyses assume that monopoly
    necessitates regulation
  • And that regulator will replicate competitive
    market
  • But there are examples where market participants
    play a major role
  • Australia, Argentina, FERC, Florida (also Canada)
  • These systems actually work well
  • better than widely believed
  • The outcomes are different from regulation
  • And often more economic, better for most parties
  • Scope to encourage elsewhere and research
Write a Comment
User Comments (0)
About PowerShow.com