Title: civil work in ppc
1Larsen Toubro Limited ECC Division- DLRO
- WELCOME
- TO
- QUALITY IN CIVIL CONSTRUCTION PROJECT
- PRESENTATION
- By
- N.Nirapandian
2WHAT IS QUALITY?
- The totality of features and Characteristics of a
product or service that on its ability to
satisfy stated or implied need.
3TOPICS
- FORM WORK
- CEMENT
- REINFORCEMENT
- AGGREGATE
- - COARSE AGGREGATE
- - FINE AGGREGATE
- WATER
- ADMIXTURE
- FLY ASH
- BRICK
- CONCRET
- POST CONCRETE CHECK
-
-
4FORMWORK
- MATERIAL
- FORMWORK SCHEME
- DIMENSIONS
- LINE
- LEVEL
- VERTICALITY/PLUMB
- RIGHT ANGLE
- CLEANLINESS
5FORMWORK
- DISTANCE BETWEEN ADJACENT MEMBERS
- COLUMN AND BEAM JUNCTIONS
- LEAK TIGHT JOINTS
- CLEANLINESS OF FORM SURFACE
- APPLICATION OF FORM RELEASE AGENT
6FORMWORK
DO
- Follow the schemes given in Formwork manual
strictly and avoid misuse of components. - Apply form work releasing agent to the form work
surface,to prevent absorption of water from
concrete and adhesion of concrete and damage when
shuttering is removed. The form work releasing
agent should be applied before reinforcement is
fixed in position. - Provide tight joints use foam sheets to
prevent leakage of grouts. - Remove shuttering slowly and avoid sudden
application of load. - Allow specified time before removing
shuttering.Follow the de shuttering time
specified in contract / Indian standards.
7COLUMN FORMWORK SYSTEM
WALER
TIE ROD
PROP
8WALL FORMWORK SYSTEM
9 10CEMENT PHYSICAL PROPERTIES( Testing as per IS
4031)
- Normal Consistency
- Fineness
- Specific Gravity
- Soundness
- Initial and Final setting time
- Compressive strength at various ages-
- 3,7 28-days
11CEMENT CHEMICAL PROPERTIES ( Testing as per IS
4032 )
- Chemical composition
- Heat of Hydration (if applicable)
12CEMENT CHEMICAL COMPOSITION
- SI. NO. OXIDES
PERCENT CONTENT -
- 1 Lime (CaO)
60-70 - 2 Silica (SiO2)
17-25 - 3 Alumina ( Al2O3)
3-8 - 4 Iron oxide ( Fe2O3)
0.5-6 - 5 Magnesia ( MgO )
0.1-4 - 6 Alkalies ( K2O,Na2O )
0.4-1.3 - 7 Sulphuric Anhydride (SO3)
1.3-3
13TYPES OF CEMENT
- 1.Ordinary Portland Cement
- - 33 Grade
-confirm to IS 269 - - 43 Grade
-confirm to IS 8112 - - 53 Grade
-confirm to IS 12269 - 2. Portland Pozzolana Cement
-confirm to IS 1489 - 3. Portland Slag cement
-confirm to IS 455 - 4. Rapid Hardening Cement
-confirm to IS 8041 - 5. Sulphate Resisting Cement
-confirm to IS 12330 - 6. Low Heat Cement
-confirm to IS 12600 - 7. Coloured Cement White Cement -confirm to
IS 8042 - 8. High Alumina Cement
-confirm to IS 6452
14CEMENT SAMPLING TUBE
15STACKING STORAGE OF CEMENT
- Storage of cement bags shall be done by
completely covered dry and moisture proof godawn. - It should not be stacked directly on ground.
- Stacking should be done on wooden blanks at
height of 150 to 200 mm from floor level. - Godawn should not have any permanent opening.
- Stacking should be done week wise(Batch/lot).
- No of cement bag should not be more than 12 in a
single stack. - Gap of 300 mm at least should be maintained
between stack of different weeks/lots/Batch. - Gap of 450 mm should be maintained between stacks
and side wall of godawn. - Gap of 600 mm between two consecutive row of
stacks should be maintained. - Sufficient lighting arrangement should be
provided in cement godawn for handling the
cement bag.
16CODES GOVERNING REINFORCEMENT BARS
- IS 1786 - 1985
- BS 4449 - 1997
- ASTM A 615 1984
- EN 10080
- RUSSIAN (GOST)
17REINFORCEMENT
- MATERIAL
- CHEMICAL PROPERTIES (TC)
- TENSILE STRENGTH
- ELONGATION
- BEND REBEND
- MEAN PROJECTED AREA
- SECTIONAL WEIGHT
- WELDABILITY
18CHEMICAL COMPOSITION OF REBARS AS PER IS 1786 -
1985
19MECHANICAL PROPERTIES OF REBARS AS PER IS 1786 -
1985
20ALLOWABLE TOLERANCE ON NOMINAL MASS OF BARS AS
PER IS 1786 - 1985
- By using bars of negative tolerance effective
savings in cost can be achieved. (The design
construction is based on specific theoretical bar
diameter, but the bars are supplied by weight) - If the bars are with plus weight, it means
reduced geometrical properties of ribs, which in
turn reduces the bond between concrete steel.
And also leads to increase in the project cost.
21TYPES OF REBARS
- Cold Twisted Deformed (CTD) rebars.
- Torsteel Rebars.
- Thermo-Processed (TMT) rebars.
- Corrosion Resistant (CRS) rebars.
- Micro alloyed Steel rebars.
- Coated rebars either galvanized or epoxy coated.
22ADVANTAGES OF TMT BARS
- TMT bars contain lower carbon content thus
exhibit better ductility weld ability (can be
butt welded or lap welded) - TMT bars have better yield strength, tensile
strength, and elongation than CTD bars of same
grade. - TMT bars display easy bend ability and thus
requires less energy for bending rebending
along with superior reverse bending properties. - They possess in built ability to resist loss of
strength when exposed to higher temperatures. - They display better corrosion resistance than CTD
bars due to absence of cold twisting stresses. - TMT bars are also available in higher strength
levels than those listed in the Indian Standard.
Use of Fe 500 grade TMT bars can result in saving
of more than 15 in steel consumption when
compared to CTD bars.
23REINFORCEMENT
- BAR BENDING SCHEDULE
- CUTTING/BENDING TO REQUIRED DIMENSIONS
- SPACING AS PER REQUIREMENT
- LAPS
- TYING
- COVER/CHAIRS
24CUTTING BENDING
- Jigs used for manual bending for correct
dimensions before going for mass production. - Cutting schedule.
- Use of latest revision of drawings bar bending
schedules. - Check bent shape for dimensional accuracy
(against a template), bent radius for signs of
fracture. - Always bend the bars by Cold. Bars larger than
25mm in size may be bent hot at cherry red heat
(not exceeding 8500C) except those bars which
depend for their strength on cold working. Hot
bars shall not be cooled by quenching. ( Clause
6.1.1 of IS 2502 1963) - Bundling labeling bars of identical size, shape
type.
25METHODS OF JOINING REBARS
- WELDING
- SPLICING BY SWAGED COUPLER METHOD
- SPLICING BY USING THREADED COUPLERS
26(No Transcript)
27 REINFORCEMENT COVER COVER BLOCK
- Cover to reinforced concrete member is the
minimum thickness of concrete provided over the
reinforcement steel measured from the exposed
concrete surface to the closest reinforced steel.
The role of concrete in the cover region can be
compared to the role human skin plays in
protecting the flesh other parts of the body. - Concrete in the cover region protects steel
reinforcement in two ways - By providing dense, strong, impermeable barrier
against ingress of moisture, oxygen, chlorides,
sulphates, carbon dioxide, other aggressive
gases chemicals. - By providing passive coating on steel surface.
Due to alkaline nature of concrete, this coating
prevents corrosion of steel.
28REINFORCEMENT COVER AS PER IS 456 - 2000
PERMISSIBLE TOLERANCE FOR COVER
Unless specified, actual concrete cover should
not deviate from the required nominal cover by
10mm there is no negative tolerance.
29PROTECTION OF REBARS
- If the work is suspended for a longer period,
then the dowel bars left in the first phase have
to be protected. The protection can be done by
the following methods - By applying a firm coat of neat cement slurry to
the exposed reinforcement bars leaving no point
untouched. - Apply suitable anti corrosive chemical to guard
against corrosion. - Encase the dowel bars in concrete either fully or
partly.
30Reinforcement
DO
- Conduct applicable tests for the reinforcement
bars for every lot / as stipulated in the
specification - Store reinforcing bars under cover, until
required to use, kept clear of mud, dirt and oil
and preferably stacked by sizes on racks. - Use only bars that are free from mud, dirt, oil,
grease, paint, loose rust, mill scale and pitting
due to corrosion, Slightly oxidized bars are not
good for adhesion with concrete
DONT
- Dont use bars with mud and dirt sticking to
them. Mud and dirt can be easily washed off with
water. - Dont use bars with oil, grease and paint
sticking to them. These should first be dissolved
in suitable solvents. - Dont use bars with loose rust and mill scale.
These can be removed with a wire brush.
31BAR BENDING AND FIXING
DO
- Cut and bend bars according to detail schedules,
paying special attention to bends and hooks. - Join wires securely at crossings with soft iron
wire of 18 or 20 S.W.G. or with galvanized wire
clips specially made for this purpose or by spot
welding. - Carry out bending of bars cold in the normal
course. In certain circumstances, such as bars of
large diameter, heating to cherry red ( 1550 F
) may be permitted and after bending, the bars
allowed to cool naturally , quenching by dipping
in oil should not be allowed. - To maintain adequate cover to the steel
reinforcement, use concrete spacer blocks or
concrete rings of thickness equal to the cover
required preferably wired to bars to prevent
their displacement.
32BAR BENDING AND STEEL FIXING
- Read drawing and bending schedules
- Identifies the types and grades of reinforcement
requirement. - Measure and set out the work
- Calculates from codes and standards the cut
length, the weights of bar the weights involved
in the job. - Computes the quantity of materials used in day to
day work - Estimate the time requirement of a particular
job. - Programmes and maintains progress of material and
labour - Plans necessary work force for the job
- Plans cutting schedule to minimise scrap
- Cuts and bends reinforcement exactly as per the
requirement of the schedule. - Ensure that bent bars of the same type are
bundled together and tagged for identification.
33BAR BENDING AND STEEL FIXING
- Ties and fastens bundled bars to ensure they
remain in position whether horizontal and
vertical - Stacks and stores tidily and safely to ensure
correct utilization based on size and type - Keep accurate and uniform spacing of
bars,staggers laps and maintain correct cover - Recognizes main bars and distributors
- Correlates the sequence of reinforcement placing
with fixing of inserts,sleeves, electrical
conduits anchors. - Prefabricates mesh and cages including additional
bars for lifting safely - Identifies and uses correct ties on structures.
- Protects the steel from corrosion and weathering
action - Prepare reinforcement patterns for special
structures - Work safely at heights using ladders,scaffolds
and safety bolts.
34AGGREGATE
35AGGREGATE
- Coarse Aggregate
- Aggregate most of which retained on 4.75 mm IS
sieve - Fine Aggregate
- Aggregate most of which passed through 4.75mm IS
sieve. - Aggregates must confirm to IS 383 requirement.
36AGGREGATE TESTING
- PETROGRAPHIC examination as per IS 2386 -
- ( part- VIII ).
- COARSE AGGREGATE
- Sl.No. Tests Test standard
Requirement as -
per IS 383 - 1 Deleterious Material IS 2386
(part-II) Ref. Table-1 of IS 383 - 2 Sieve analysis IS
2386 (part-I) ----- - 3 Specific gravity IS
2386 (part-III) 2.6 2.8 - 4 Elongation
- Flakiness Index IS
2386 (part-I) ----- - 5 Soundness test IS
2386 (part-V) 12 tested with Na2SO4 -
18
tesed with MgSO4 -
(Max. ) - 6 Water absorption IS
2386 (part-III) -------- -
-
-
37AGGREGATE TESTING
- Sl.No. Tests Test standard
Requirement - 7 Crushing Value IS 2386
(part-IV) Max. 30 for Road -
Runway 45 for other -
concrete - 8 Impact Value IS
2386 (part-IV) Max. 30 for Road -
Runway 45 for -
other concrete -
9 Abrasion
Value IS 2386 (part-IV)
Max. 30 for Road -
Runway 45 for other -
concrete - 10 Alkali reactivity IS 2386
(part-VII) -------- - 11 Chloride sulphate
- content ASTM
(1411) --------- -
38AGGREGATE TESTING
- Fine Aggregate
- Si.No. Tests Test
standard Requirement - 1 Deleterious Material IS 2386
(part-II) Ref. Table-1 of IS 383 - 2 Sieve analysis IS
2386 (part-I) Ref. Table-1 of IS 383 - 3 Specific gravity IS
2386 (part-III) 2.6 2.8 - 4 Soundness test IS
2386 (part-V) 10 tested with Na2SO4 -
15
tested with MgSO4 -
(Max. ) - 5 Water absorption IS 2386
(part-III) -------- - 6 Chloride sulphate
- content
ASTM (1411) ---------
39PROPERTIES OF AGGREGATE
- S. No. PROPERTIES INFLUENCE ON
CONCRETE -
PROPERTIES - Sp. Gravity/Porosity
Strength / Absorption - Chemical stability
Durability - Surface Texture Bond
grip - Shape
Water demand ( strength ) - Gradation or particle Water
demand (strength), - size distribution
Cohesion, bleeding and segregation - Maximum size
Strength and water demand - Deleterious Materials Water
demand (strength), bond cohesion -
and durability
40Aggregate
DO
- Test aggregates as stipulated in the
specification - Stacking of aggregates of different sizes
separately in the stack yard. - Stack on leveled surface and higher elevations
than the surroundings.
DONT
- Mixing of different sizes of aggregate in stack
yard. - Mixing of aggregates with dirt, mud other
unwanted materials.
41AGGREGATE SAMPLING SCOOP
42WATER
- Water used in Construction shall be tested as
per IS 3025 - and confirm to IS 456
- SI. NO. PROPERTIES TEST
MIN. MAX. -
PROCEDURE LIMIT LIMIT - PH-Value IS 3025
6 --- - Organic solid
--do -- 200mg/lit. - Inorganic solid
--do-- --- 3000mg/lit. - Sulphates ( as SO3)
--do-- --- 4000mg/lit. - Chloride ( as Cl )
--do-- --- 2000mg/lit.for -
PCC 500mg/lit. -
for RCC. - Suspended matter
--do-- --- 200mg/lit. - To neutralise 100 ml sample of water using
phenolphthalein as an indicator, it should not
require more than 5 ml. Of 0.02 normal NaOH. - To neutralise 100 ml sample of water, using mixed
indicator, it should not require more than 25 ml.
Of 0.02 normal H2SO4.
43ADMIXTURE
- It is a material, other than the cement,water
and aggregate in concrete to modify the
properties of ordinary concrete so as to make it
more suitable for any situation.
44TYPE OF ADMIXTURE
- 1. Mineral admixture
- 2. Chemical admixture
- Mineral admixture
- Fly ash
- Silica fumes
- Rice husk ash
- Metakaoline
- Ground Granulated Blast Furnace
45Chemical admixture
- Plasticizers
- Superplasticizers
- Retards and Retarding Plasticizers
- Accelerators and Accelerating Plasticizers
- Air- entraining Admixtures
- Damp proof and Waterproofing admixtures
- Workability Admixtures
- Gas forming Admixtures
- Grouting admixtures
- Bonding Admixtures etc
46FLY ASH
- PHYSICAL PROPERTIES
- Bulk density gm/cm3 1.21
- Specific gravity
2.22 - Resistivity at 500 VDC and 25 0 C
- Surface resistivity
3.79x109 - Volume resistivity
1.1x108 - Lime reactivity
5.8 - Blains surface area, m2/N 35.15
47FLY ASH
- Chemical Properties
- S No. CHEMICAL PERCENT
BY WEIGHT - COMPOSITIONS AS PER IS
38122000PART- I - SiO2
35 ( min.) - Al2O3
----- - Fe2O3
----- - SiO2Al2O3Fe2O3 70
(min.) - MgO
5.0 (min.) - SO3
2.75 (max.) - Loss of Ignition
5.0 (max.) - CaO
-----
48COMPARISION OF PHYSICAL PROPERTIES OF OPC AND FLY
ASH CONCRETE
- S.No. PROPERTIES OF OPC MIX
OPCFLY - CONCRETE
ASH MIX - Workability, slump (mm)
60 70 - Compressive Strength, N/mm 2
- 7-days
20
23.6 - 28-days
30.1
35.1 - 56-days
34.6
42.2 - Water Permeability at
- 28 days m/s x 10-12
8.7
6.6 - Modulus of elasticity at
- 28 days, mpa x 104
2.2
2.71 -
49BRICK ( Common burnt clay brick as per IS 1077 )
- CLASSIFICATION
- Class Designation Avg. Compressive
strength not -
less than (N/MM2) - 35
35 - 30
30 - 25
25 - 20
20 - 17.5
17.5 - 15
15 - 12.5
12.5 - 10
10 - 7.5
7.5 - 5
5 - 3.5
3.5
50QUALITY OF BRICKS
- Free from cracks,flaw and noudles of free lime.
- Smooth rectangular faces with sharp corner.
- Uniform in colour and ringing sound.
- PHYSICAL REQUIREMENTS
- (Brick of size (230x110x70) mm
- Dimensional test
- Test should be conducted on 20 no. sampled bricks
- Dimensions of 20 no. bricks together should be as
below- - Length (4600 /- 80) mm
- Width (2200 /- 40) mm
- Height (1400 /- 40) mm
-
51QUALITY OF BRICKS
- Frog size(Brick mark) should be (60x40x)mm
with depth 10-20 mm and radius 20mm as shown in
IS 1077- clause 6.1.1, fig. 1A. - Water absorption-
- (When tested as per IS 3495- part-2)
- Absorption shall not be more than 20 by weight
up to class - 12.5 and 15 for higher classes.
-
- Compressive strength-
- (When tested as per IS 3495-part I)
- Average Compressive strength of 5 no. sampled
bricks shoild not be less than the minimum
compressive strength specified for the
corresponding class of bricks.
52CONCRETE
- CONSTITUENTS
- CEMENT SUPPLEMENTARY CEMENTITITIOUS
MATERIAL (10 15) - AGGREGATES (60 80)
- WATER (15 20)
- ADMIXTURE
53WATER CEMENT RATIO
In a cement slurry, the ratio of water to cement
expressed as percent, the number of parts of
water used to mix with 100 parts of cement. If
all the water absorbed by the aggregate particles
is neglected just water on the surface is
considered along with the water added to the mix,
then the W/C is called Free water cement
ratio. If water absorbed by the aggregate
particles is also considered in addition to the
water on the surface of the particles as well as
water added to the mix, then the W/C is called
total water cement ratio. In the concrete
mixes, besides cement, if any cementitious
materials like fly ash, silica fume, ground
granulated blast furnace slag, etc is used, and
then the ratio will be known as Water
cementitious ratio.
54SIGNIFICANCE OF WATER CEMENT RATIO
When the concrete is fully compacted, its
strength is taken to be inversely proportional to
water cement ratio. Water cement ratio
determines the porosity of the hardened cement
paste at any stage of hydration hence
influences the durability permeability of
hardened concrete. When concrete is made using
very high water cement ratio, large capillary
pores in cement paste allows high permeability of
water along with other chemicals like chlorides
sulphates, which cause deterioration of concrete.
To have durable concrete structures, it is
desirable to specify low water cement ratios.
55IMPORTANCE OF WATER CONTENT IN THE MIX
- CEMENT W/C
- 400 KG /CUM 0.55
- 300 KG/CUM 0.55
56CHECK FOR CONCRETE
- SLUMP/WORKABILITY
- COHESIVENESS/SEGREGATION
- AIR CONTENT
- COMPACTION
- FINISHING
- CURING
- COMPRESSIVE STRENGTH
- YIELD (SOURCE CONSISTENCY)
- TEMPERATURE CONTROL (Beyond 40 Deg.C)
57CONCRETE SAMPLING SCOOP
58PRODUCTION AND PLACEMENT
- MIXING
- PLACE WITHIN INITIAL SETTING TIME
- VIBRATION
- CURING
- SUPERVISION
- CONSTRUCTION JOINT PREPARATION
59PLACING CONCRETE
DO
- Place concrete in position before initial set
occurs i.e., within 30 minutes of mixing. - Fill all nooks and corners in formwork, surround
all reinforcement with concrete using tamping
rods or vibrators. - Place concrete in horizontal layers ( 6 to 12
deep for R.C. work and 15 to 18 for mass
concrete work) each of which should be compacted
properly, before subsequent layers are placed. - Place each layer before the previous layer has
hardened, except, of course, where concreting of
the previous layer was stopped at the end of the
days work. In fact concrete placing should be
continued without interruptions until the
placement is completed to avoid intermittent cold
joints.
DONT
- Dont place concrete during rains unless proper
cover can be provided. - Dont drop concrete from a height greater than 5
feet to avoid segregation. - Dont use concrete in which initial set of
cement has already started.
60IRONITE FINISH( Patent stone with Metallic
Hardner)
- i) This will consist of a topping
(incorporating iron particles) to bond with
concrete base while the concrete is green. - ii) The metallic hardner finish shall be of
12 mm depth over 28 mm thick concrete base. - iii) Total thickness shall be 40 mm thick.
- The hardening compound shall be uniformely graded
iron particles free from non-ferrous metal
impurities, oil, grease,sand or other injurious
materials - 1 part of metallic hardener shall be mixed dry
with 4 parts of cement, by weight. - To this mixture 6 mm nominal size stone chips
shall be added in proportion of 1 part cement
(mixed with hardener ) to 2 parts of stone chips
by volume and uniformly mixed. - Minimum qty. of water shall be added to make it
workable. - The surface shall be roughened by wire brush as
soon as possible. - This Topping layer shall be pressed firmly and
worked vigorously and quickly to secure full bond
with the concrete base. - The surface shall be finished smoothened with
steel trowel. - The finished floor shall be cured for 7- days by
keeping it wet/ponding.
61PLASTERING WORKS
- SAND
- Sand should consist of natural sand,crushed stone
sand crushed gravel sand. - Sand should confirm to IS 383 and grading should
confirm to IS 1542. - Total of all deleterious substances should not
exceed 5 by weight. - Fineness modulus of sand should be 2.0 to 2.2
- MIXING
- Non observant surface should be used for mixing
the cement sand mortar.
62PLASTERING WORKS
- Cement sand should be mixed in dry state first
and then add water and mixed. - The mortar should be consumed within half an hour
of mixing. - Measuring box should be used to ensure proper
proportion of mix. - If machine mixed, mixing time (Rotation )should
be 1.5 to 2 minutes - APPLICATION OF PLASTER
- For external plaster, the work shall be from the
top floor and downwards. - For internal plaster,ie wall, the work shall be
top and carried downwards. - Plastering shall be carried out to the full
length of the wall or to natural breaking points
like door/windows etc.
63PLASTERING WORKS
- Ceiling plaster shall be completed before
commencing wall plastering. - No single coat, shall exceed 12 mm in thickness.
- Curing shall be 2 days for each coat and for
finished surface at least 7 days.
64CURING
What is Curing? Curing is the process of
preventing loss of moisture from the concrete
while maintaining a satisfactory temperature
regime. Why curing is required? Concrete in its
early life needs to be carefully looked after
like parents looking after their newborn baby. If
the concrete is not nurtured properly by carrying
out the required curing protected against wind
extreme ambient conditions, then the structure
will loose its strength, durability, the
concrete will behave like a child born weak.
65METHODS OF CURING
- Water cure by flooding, ponding, mist spray.
- Water retaining method By using absorptive
coverings such as sand, canvas, burlap or straw
that are kept continuously wet. - By mechanical barriers.
- By using chemical membranes.
66MINIMUM CURING PERIOD AS PER IS 456 - 2000
- For OPC or Super sulphonated cements
Minimum Seven days - For concrete having blended cements like Portland
pozzolana cement, Portland slag cement or mineral
admixtures - - Minimum 10 days. This may be extended to 14
days. - 3. For concrete exposed to dry hot weather
conditions - - Minimum 10 days.
67CURING
DO
Keep all surfaces of newly laid concrete damp for
7 days. Damping can be done in several ways by
hosing or sprinkling of water by wet sacking or
matting by ponding of horizontal surfaces with
raised edges in weak mortar and filling I 2
depth of water or by laying 2 3 thick
layers of sand kept soaked in water.
DONT
Dont neglect curing. It is better to over cure
than to under-cure. Under-curing results in loss
of strength which is irreparable and water is
cheap.
68CONSTRUCTION JOINTS
Construction joints are surfaces where two
successive placements of concrete meet. They are
typically placed at the end of the days work.
But may also be required when the concrete
placement is stopped for longer than the initial
setting time of concrete. The location of
construction joints should be planned. It may be
desirable to achieve bond continue
reinforcement through a construction joint. For
monolithic concrete, a good construction joint
might be a bonded interface that provides a water
tight surface allows for flexural shear
continuity through the interface.
69METHODS OF PREPARATION OF CONSTRUCTION JOINTS
- By using hand chisel hammer
- By using pneumatic bush hammer
- By using water jetting
- By applying surface retarder over the concrete
surface. Cement paste and laitance were brushed
away when the concrete was initial set.
70USE OF SURFACE RETARDER
- Purpose Preparation of Construction Joint (CJ )
- Application
- After compaction and surface finishing of green
concrete, water (if any) should be removed from
surface. - Surface retarder should sprayed or painted with
brush on the surface of green concrete. - Just before starting of final setting time of
concrete, pressurised water jet at an angle of 60
degree from vertical should be applied on the
surface. - Since surface retarder increase the setting time
of concrete on the surface, cement from the top
surface of concrete shall be cleaned off and the
sound aggregate get exposed, which is required
for good CJ surface.
71USE OF SURFACE RETARDER
- Advantages
- It completely avoids chipping of concrete for CJ
preparation - Only air cleaning is required prior to the
concreting - This process is faster than the chipping process.
72CONSTRUCTION JOINTS IN BEAMS SLABS
- Desirable location for construction joints placed
perpendicular to the main reinforcement are at
points of minimum shear or points of contra
flexure. Construction joints are usually located
at mid span or in the middle third of the span,
but locations should be verified by the Engineer
before placement. - Horizontal construction joints in beams and
girders are usually not recommended.Common
practice is to place beams girders
monolithically with the slab. - For the beams where the members are of
considerable depth, it is advisable to place the
concrete in the beam section up to the slab
soffit, then placing the slab in separate
operation. This is to avoid cracking of the
interface because of vertical shrinkage in deep
member if beam slab concrete are placed
monolithically.
73CONSTRUCTION JOINTS IN BEAMS SLABS
- The main concern in joint placement is to provide
adequate shear shear transfer flexural
continuity through the joint. Flexural continuity
is achieved by continuing the reinforcement
through the joint with sufficient length past the
joint to ensure adequate splice length for the
reinforcement. Shear transfer is provided by
shear friction between old new concrete or
dowel action in the reinforcement through the
joint.
74CONSTRUCTION JOINTS IN SLABS
1
2
75Ò
3
Ö
4
76Ö
5
X
( X 1/3rd to 1/4th span )
77CONSTRUCTION JOINTS IN COLUMNS
SMOOTH AND FULL OF LAITANCE
Ò
Ò
ROUGH AND FREE OF LAITANCE
Ò
Ö
78CONSTRUCTION JOINTS IN FOOTINGS
Ò
Ò
KICKER
KICKER
Ö
Ö
79EXPANSION JOINTS
- Expansion joints are used to limit member forces
caused by thermally induced volume changes.
Expansion joint permits separate segments of a
structure to expand or contract without adversely
affecting structural integrity or serviceability. - Expansion joint isolates building segments
provides relief from cracking because of
contraction of the structure. Joint width should
be sufficient to prevent portions of the
structure on either side of the joint from coming
in contact. - Joints may vary in width from 25mm to 15mm. Wider
joint are used to accommodate additional
differential structural movement that may be
caused by settlement or seismic loading. Vertical
expansion joints should pass through the entire
structure above the level of the foundation.
80MATERIALS USED FOR EXPANSION JOINTS
- Flexible boards
- Sealants hot poured, bituminous in origin
- Sealants cold applied, Poly sulphide sealant.
- Pre formed elastomeric
- PVC water stop
- Steel, copper
81SURFACE DEFECTS IN CONCRETE CAUSES AND REMEDIAL
MEASURES
- Any defects in the finished concrete surface
observed after removal of form work -
- Design and construction-related causes
- Difficult placement due to design of a
member - Improper design, construction and
maintenance of forms - Improper selection of concrete mixture
proportions - Failure to adjust concrete mixture
proportions to suit - Placement condition
- Improper placement practices
- Improper vibration and consolidation
practices - Improper steel detailing
82- Equipment-related causes
- Improper equipment
- Improper equipment maintenance
- Equipment failure (crane, pump, concrete plant)
- Interruption of utility service
- Material-related causes
- Improper selection of release agent
- Cement characteristics
- Variation in mixture components
- Inappropriate use of admixtures
- Inappropriate use of release agents
-
- Environmental causes
- Extreme weather conditions
83Types of surface defects
- Surface defects which can result from ineffective
consolidation procedures are discussed below. - 1 Honeycomb
- Honeycomb is a condition of irregular voids due
to failure of the mortar to effectively fill the
spaces between coarse aggregate particles. Where
bridging of the aggregate particles or stiffness
of the mixture is a cause of honeycomb, vibration
may assist in overcoming the bridging by
increasing the flowability of the concrete. - Causes congested reinforcement,
- insufficient paste content,
- improper sand-aggregate ratio,
- improper placing techniques,
- quick setting on hot concrete, and difficult
construction conditions. Changes in mixture
proportions to improve workability may assist in
reducing or preventing honeycombing.
842- -Bugholes (Air surface voids) Bugholes on
vertical faces are normally caused by air
bubbles, but occasionally by water entrapped
between the concrete mass and the form,
especially in sticky or stiff concrete mixtures
of low workability which may have an excessive
sand and/or entrapped air content. Also, the use
of vibrators of too large an amplitude or the
lack of complete insertion of the vibrator head
may result in increased air-void formation.
853--Form-streaking Form-streaking is caused by
mortar leaking through form joints and may be
aggravated by over vibration from vibrators that
are too powerful, or by using forms that vibrate
excessively during consolidation. Placing
excessively wet or high-slump concrete mixtures
will result in more mortar washing out through
tie holes and loose fitting forms. Special care
is sometimes required when super plasticizers are
used, as they tend to increase leakage at form
joints and in pump lines.
4 --Aggregate transparency Aggregate
transparency is a condition characterized by a
mottled coloring on the surface which results
from deficiencies in the mortar. It may result
when concrete mixtures have low sand content, dry
or porous aggregates, or high slump with some
lightweight and normal weight aggregates. Also,
high density or glossy form surfaces may cause
aggregate transparency.
865--Subsidence cracking Subsidence cracking
results from the development of tension when the
concrete settles after or near initial set. The
cracks are caused because the upper concrete
bridges between the forms while the lower
concrete settles. These cracks may occur when
there is an insufficient interval between
placement of concrete in columns and placement of
concrete for slabs or beams. They may also occur
adjacent to block outs or over reinforcing bars
with shallow cover. To prevent subsidence
cracking, the concrete can be revibrated.
Revibration is most effective when done at the
latest time at which the vibrator head will
penetrate the concrete under its own weight.
Subsidence cracking over reinforcing bars can be
controlled by increasing concrete cover during
the design phase and by using well-consolidated,
low-slump concrete.
876--Color variation Color variation may occur
within a placement if the concrete is not uniform
or is incompletely mixed. Vibrators inserted too
close to the form destroy the release agent or
mar the form surface. External vibration used
haphazardly may also cause color variation.
Furthermore, color variations may result from
nonuniform absorption and/or nonuniform
application of the release agent.
7 --Sand streaking Sand streaking is a streak of
exposed fine aggregate in the surface of the
formed concrete caused by heavy bleeding along
the form. It frequently results from the use of
harsh, wet mixtures, particularly those deficient
in 0.30 to 0.15 mm and smaller sizes. Sand
streaking is controlled by the use of tight forms
and proper mixture proportioning, using
well-graded fines to minimize bleeding.
888- -Layer lines Layer lines are dark horizontal
lines on formed surfaces which indicate the
boundary between concrete placements. Layer lines
are caused by stiffening or insufficient
consolidation of the lower level due to lack of
penetration of the vibrator into the lower
level. 9- -Form offsets Form offsets are
usually caused by inadequate stiffness or
anchorage of the forms and can be aggravated by
too high a rate of placement and/or using too
powerful a vibrator. 10--Cold joints Cold
joints frequently occur in concrete for many
reasons. Cold joints can often be avoided by
contingency planning, back-up equipment, working
to keep the concrete surface alive, and working
to vibrate into lower lifts.
89THANKYOU