Title: Impact evaluation for: National Irrigation Rehabilitation Project
1Impact evaluation for National Irrigation
Rehabilitation Project
- Case study 3
- NONIE meeting in Lisbon
- October 1, 2008
2Section A Presentation of National Irrigation
Rehabilitation Project
3Section A Presentation of National Irrigation
Rehabilitation Project
- Background and rationale
- Project concept and strategy
- Project Goal Purpose
- Components
- Selection of Scheme
- Project Implementation
4National Irrigation Rehabilitation Project
- 1.1Background and Rationale
- Agriculture performance specially paddy
production depended heavily on irrigation - Many irrigation schemes were old and deteriorated
facilities resulted in poor water management
practices led to loss of paddy - The irrigation facilities did not function
properly due to poor attention on OM - Need to encourage farmers to assume full
responsibility for OM and thereby reduce the
role of Public Sector Involvement in irrigation
management
5Project Goal
- Stabilize agricultural production and income and
to raise the standard of living of farmers
through rehabilitation and improved OM of
existing irrigation schemes.
6Project purpose
- Stabilized and increase agricultural production
on rehabilitated schemes through sustained and
improved water management with OM of selected
existing of irrigation schemes.
7National Irrigation Rehabilitation Project
- 1.2 The Project Concept and Strategy
- In this backdrop the project strategy was
inline with the Government National Irrigation
subsector strategy to improve the performance of
existing irrigation capacity and promote
increased participation of farmers in the
management and maintenance of schemes. - Rehabilitation
- OM FOs
- Instititional Strengthening
8Project components
- The proposed 7 year project (1991 to 1997)
includes - Rehabilitation and improvement of 1000 minor and
60 medium/major schemes covering about 37 500 ha - (b) Creating viable/healthy Farmer Organizations
(FOs) - for managing the rehabilitated schemes and
introduction of - improved OM practices in all
rehabilitation schemes - (c) Upgrading the skills of farmers and staff of
the implementing - agencies
9 Program Theory and results-chain
Network of Networks on Impact Evaluation
10Project Management
- Executing Agency - Min. Irrigation
- Implementing Agencies - ID, ASD, PC
- PMU PD , Consultants
- National PCC Sec.Min Irrigation, Donor, IAs
- Ptovincial PCC Chief Sec
Network of Networks on Impact Evaluation
11Selection of Schemes
- The schemes for rehabilitation were selected
after reaching prior agreement with the
respective FOs to undertake responsibility for
the full cost of OM of minor schemes and
Distribution and field cannels of major/ medium
schemes after rehabilitation. - Minor Schemes 750 per ha
- Participatory Planning, Management and Post Impl.
12Project Implementation
- Project reached physical rehabilitation targets
civil works of 1048 minor schemes and 34
major/medium schemes (completed in June 1999) - Established scheme levels FOs in all minor
schemes and in all major/medium schemes. - Handed over 64 of completed schemes (ie 2/3) to
registered FOs and 32 of DF cannels (ie 1/3)
major/medium scheme to FOs
13 However the organizational and financial
viability of FOs remain uncertain
- Handing-over process in many schemes is supply
driven - (written agreement signed between IAs and
FOs) and - remains a risk
- Quality Assurance of Civil Works Project
supported 14 Quality Control Labs. Equipments
arrived after 80 work completed.
14 Findings of ICR
- FOs should have been established before
rehabilitation - Organisational and Ginancial Viability of FOs
-Uncertain - Handing-over process in many schemes is supply
driven - Unrealistic Assumtions Major Schemes Headworks
and Main canals - Project Implementation Delays
- Quality Assurance of Civil Works Project
supported 14 Quality Control Labs. Equipments
arrived after 80 work completed. - Cost Criteria Proprities only attended
Partially completed schemes
Network of Networks on Impact Evaluation
15Section B Impact evaluation of National
Irrigation Rehabilitation Project
16Section-B Impact Evaluation of National
Irrigation Rehabilitation Project
- Evaluation Framework and Context
- Evaluation Questionnaires
- Outcome Indicators
- Theory and results framework
- Evaluation Design
- Challengers and Risk
- Methodology
- Implementation
- Management
- Expected Results
- Expected Conclusions
17 Program Theory and results-chain
18Impact Evaluation of National Irrigation
Rehabilitation Project
- Evaluation Questions
- 1.Relevence
- 1.1 Is the project consistent National
Irrigation - subsector strategies and policies of the
government? - 1.2 Has the project included the need and
priorities of - the farmers?
- 1.3 Is the project components and activities are
balanced - and relevant to the Goals and Purpose?
- 1.4 Are the selected schemes, target groups,
target - areas appropriate?
-
-
19Evaluation Questions
- 2.Efficiency
- 2.1 Were the schemes rehabilitated successfully
covering all civil works - specially Headwork and Delivery system
(Cannels)? - 2.2 Is the cost incurred justify the degree of
achievement of outputs and - outcomes? (Comparison with similar
projects) - 2.3 Any alternative strategies that will achieve
the same results? - 2.4 What factors that constrain or contribute to
the efficiency of the project - implementation process?
-
20Evaluation Questions
- 3.Effectiveness
- 3.1 Is the project strategy and sequence of
activities appropriate? - 3.2 Are the schemes functional?.
- State of the maintenance of irrigation
structures - 3.3 Are the FOs are ready to undertake OM?
- 3.4 Do the FOs have ability to generate funds to
meet OM? - 3.5 How is the performance of FOs?.
- 3.6 What are the hindering or contributing
factors for project effectiveness?
21Evaluation Questions
- 4. Impact
- 4.1 Has the overall goal being achieved?
- 4.2 Has the intervention institutionalized
improved water management - practices?
- 4.3 Was there an increase in the Yield, Cropping
intensity and Paddy - production in the scheme?
- 4.4 Did the intervention improve the income and
living standards of farmers in - the scheme?
- 4.5 Any impacts on the institutions?
22Cont Evaluation Questions
- 4. Impact
- 4.6 Any external factors which influenced the
impacts positively or - negatively?
- 4.7 Any unintended effects and impacts of the
project? - 4.8 Did the project had any influence on the
policy?
23Evaluation Questions
- 5.Sustainability
- 5.1 Will the termination of the project affect
the outcomes and impacts? - 5.2 How far the schemes were successfully handed
over to FOs for - maintenance?
- 5.3 Have the FOs taken over OM responsibility
of minor schemes and - selected FD Cannels in major/medium
schemes? - 5.4 Ability of FOs to manage schemes, resolve
water disputes, venture - into the marketing and input suppliers
etc. and whether FOs are - economically and organizationally
empowered through commercial - activities?
-
24 Evaluation framework and context
25Outcome indicators
26Evaluation design
- Impact Evaluation
- Focus - Program outcomes and Impact
- - Program Effectiveness
- Method - Outcome/Impact Measurement
(Results) - - Before/After and with and without
Analysis Framework (Treatment Group
with Comparison Group/Counterfactual
analysis) - - Cost benefit Analysis -
EIRR - DAC/OECD - Relevance, Efficiency,
Effectiveness, Impact, Sustainability - Criteria
- Data - Secondary sources/Administration
Records - - Primary sources
- - Key informant interviews, Focus
group discussions, Community - interviews, Semi
structured survey interviews Direct - Observations.
-
27 Challenges and risks
- Other Services are assured e.g. Extension
Services, Seed Paddy, Fertilizer, Credit - FOs undertake contracts are financially
benefitted - No political interferences in selection of
schemes - Quality assurance system is in operation (civil
works, soil esters etc.) - Stable and improved prices for agricultural
products - No deterioration in catchment hydrology and
rainfall pattern
28 Evaluation Methodology
- Highly successful
- Successful
- Partly Successful
- Unsuccessful
- Judgment of the
- Achievement
- Verification of
- achievement and results
- Question designed to
- addressed to criteria
- Relevance, efficiency, effectiveness,
impact - sustainability
-
-
-
29Implementation
- Evaluability Assessment (Program theory,
availability of data, intended use) - Evaluation Plan
- Appointment of the Management Group and Reference
Group - Defining the TOR
- Contracting the Evaluation and selecting
evaluators - Desk Research
- Scoping Session
- Field Study
- Analysis and drafting the report
- Dissemination
- Management response
30Management
- Reference Group
- Management Group
- National Evaluation Coordinator
- Peer Reviews
31Expected results
- Insert text on expected evaluation results here
32Expected conclusions
- Insert text on expected evaluation conclusions
here