Productivity Improvement - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

Productivity Improvement

Description:

Supervisor should meet with the estimator during the bid preparation and provide ... (5 craft-hours) x (10 sfca) = (50 sfca) (crew-hour) (craft-hour) (crew-hour) ... – PowerPoint PPT presentation

Number of Views:236
Avg rating:3.0/5.0
Slides: 10
Provided by: LakishaC
Category:

less

Transcript and Presenter's Notes

Title: Productivity Improvement


1
Productivity Improvement Session 2
2
The Four Phases of the Construction Process
3
Interfacing the Supervisor with the Estimate
  • Supervisor should meet with the estimator during
    the bid preparation and provide construction
    productivity information to the estimator.
  • The supervisor should review the estimate to
    identify the vital few and the useful many.
  • Supervisor reviews contract drawings and
    specifications to determine base bid work and
    potential change order work.
  • Supervisor reviews project supplementary
    conditions to identify unique project clauses
    that may cause the supervisor difficulties if
    they are overlooked.
  • Supervisor should sign off that pre-planning
    tasks have been performed.

4
Criteria for Identifying the Vital Few
  • Cost of the work
  • Risk or variation in the production process
  • Work tasks that dictate or drive the project
    schedule
  • Work tasks the firm and supervisor have seldom
    done previously

5
Pre-Planning Production Budgets(1. Calculate
needed production per day)
  • Quantity of work to perform 20,000 sfca
  • Divided by number of work days 10 days
  • Equals 2,000 sfca/day

6
Pre-Planning Production Budgets(2. Calculate
production rate performed per crew-hour)
  • (5 craft-hours) x (10 sfca) (50 sfca)
  • (crew-hour) (craft-hour) (crew-hour)

7
Pre-Planning Production Budgets(3. Calculate
production performed by the crew per day)
  • (8 crew-hours) x (50 sfca) (400 sfca)
  • (day) (crew-hour) (day)

8
Pre-Planning Production Budgets(4. Calculate
number of crews required)
  • (2,000 sfca) divided by (400 sfca) (5 crews)
  • (day) (day/per crew)

9
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com