Title: Productivity Improvement
1Productivity Improvement Session 2
2The Four Phases of the Construction Process
3Interfacing the Supervisor with the Estimate
- Supervisor should meet with the estimator during
the bid preparation and provide construction
productivity information to the estimator. - The supervisor should review the estimate to
identify the vital few and the useful many. - Supervisor reviews contract drawings and
specifications to determine base bid work and
potential change order work. - Supervisor reviews project supplementary
conditions to identify unique project clauses
that may cause the supervisor difficulties if
they are overlooked. - Supervisor should sign off that pre-planning
tasks have been performed.
4Criteria for Identifying the Vital Few
- Cost of the work
- Risk or variation in the production process
- Work tasks that dictate or drive the project
schedule - Work tasks the firm and supervisor have seldom
done previously
5Pre-Planning Production Budgets(1. Calculate
needed production per day)
- Quantity of work to perform 20,000 sfca
- Divided by number of work days 10 days
- Equals 2,000 sfca/day
6Pre-Planning Production Budgets(2. Calculate
production rate performed per crew-hour)
- (5 craft-hours) x (10 sfca) (50 sfca)
- (crew-hour) (craft-hour) (crew-hour)
7Pre-Planning Production Budgets(3. Calculate
production performed by the crew per day)
- (8 crew-hours) x (50 sfca) (400 sfca)
- (day) (crew-hour) (day)
8Pre-Planning Production Budgets(4. Calculate
number of crews required)
- (2,000 sfca) divided by (400 sfca) (5 crews)
- (day) (day/per crew)
9(No Transcript)