Title: Connections Details for Prefabricated Bridge Elements and Systems
1Connections Details for Prefabricated Bridge
Elements and Systems
WASHTO-X Webinar Prefabricated Bridge Elements
and Systems June 17, 2008
Michael P. Culmo, P.E. CME Associates, East
Hartford, CT
2Roadblocks to Accelerated Construction
- The primary concerns that owner agencies have
with respect to adopting accelerated construction
techniques are - Need for Quality Details
- Durability
- Design Methodologies and Training
- Construction Methodologies
3Connections for Prefabricated Bridge Elements
and Systems
- FHWA has initiated a project to develop this
manual - This publication is intended to provide
information that will go a long way to answering
all four of the previous concerns. - Focus on details that have been used in the past.
4Project Goals
Connection Details for Prefabricated Bridge
Elements and Systems
- Gather details of Connections that have been used
on accelerated bridge construction projects - Investigate transfer of technology from other
markets into the bridge market - Parking Garages
- Stadiums
- Buildings
5- All details needs to pass a critical test
before being published in the document - Does the connection result in a rapid
construction process? - Does the connection transmit the forces between
elements effectively? - Is the connection durable?
- Has it performed well under traffic and in an
exposed environment? - Is it cost effective and easy to construct?
- If a process or connection is proprietary, can it
be incorporated into numerous projects without
producing contracting issues?
6Source of Data
- State DOTs
- Questionnaires sent via e-mail
- Federal Agencies
- International Organizations
- Researchers (previous and current)
- Producers
- Questionnaires sent via e-mail
7Manual Organization
8Connection Data Sheets
9Precast Abutments
10Precast Abutments
11Precast Piers
12Precast Piers
13Precast Decks on PS Beams
14Precast Decks on Steel Framing
15Precast Decks
16FRP Decks
17Grid Decks
18Partial Depth Deck Forms
19Total Bridge Prefabrication
20Total Bridge Prefabrication
21Examples Epping NH
22Epping Bridge Prefabrication
construction of 1-07.avi
23Project Schedule
- Gather information
- Fall 2006 through Spring 2007
- Visit states that are leaders in accelerated
bridge construction - Winter 2007
- Develop manual
- Summer/Fall 2007
- Complete Manual
- Fall 2008
24Project Delivery
- The document will be available for all owners and
designers for use in future accelerated bridge
projects - Website will be established on the FHWA Highways
for Life Website - www.fhwa.dot.gov/hfl/
25Questions?culmo_at_cmeengineering.com