Title: Pixel Electronics slides for UCSC
1Pixel Electronics slides for UCSC
- Cover 0.13 FE chip
- ROD
- Other Activities (except DC-DC)
2Progress in FY07
- Epilogue from 2004 test chip
- Preamp chip submission testing
- Workshop at CERN
- Work-plan for full size chip submission
- Includes non-US manpower
- CPPM
- Bonn
- Genova
- US to focus on unique capabilities
- Analog design
- Architecture
- Full chip integration
32004 test chip epilogue
- CPPM has prepared an SEU measurement setup using
the LBNL 2004 0.13um test chip. - They are irradiating with 20GeV protons at CERN
right now to extend the studies done at the LBNL
88 cyclotron in FY06. - LBNL simply provided test boards, a few chips,
and advice, but we are getting a great deal in
return - More on collaboration with European institutes
later
4Analog test chip submitted Feb. 07
- 130nm bulk CMOS
- 840 pixels complete with threshold and bias
registers. - 2 basic charge-integrating amplifier designs
- resistor continuous reset.
- current source continuous reset.
- nominal current 22mA/pixel
- Goal for final chip is 10mA/pixel
- Simulated ENC 200e- for 400fF input load and
20ns peaking time - Exact value depends on many tunable parameters
3.6mm
2.8mm
5Analog test chip plans
- Expected chip delivery late May
- Test board in fabrication now
- Initial checkout by Abder at LBNL
- Distribution of chips to other test efforts in
June/July - Interest from European collaborators to
participate in testing - Some irradiation possible in FY07, but mainly in
08 - Hope that European colleagues will set up
irradiation tests in FY08- no project fund
request for this. - Note that all transistors are linear (with guard
rings around Nmos) - Critical initial measurements expected
- Threshold dispersion
- Uniformity across array. Operating margin.
- Current consumption, noise and timewalk
6Pixel Upgrade Electronics Workshop
- Held on March 22 at CERN following ATLAS-CMS
Electronics (ACES) workshop. http//indico.cern.ch
/conferenceDisplay.py?confId13957 - 7 electical engineers not presently involved in
pixels attended this meeting - CPPM, Bonn, Nikef, Genova
- Clearly there is interest
- Work Plan drafted in April to foster efficient
collaboration - First global chip designers pone meeting to go
over this plan isnext week
7Plans for FY08
- Work-plan milestones
- Architecture definition September 2007
- Initial Design review January 2008
- Final Design review September 2008
- First full size chip submission December 2008
- LBNL engineering manpower
- 100 Abder Mekkaoui Lead IC designer, analog
front end, integration - 40 Dario Gnani IC designer, High level
description, readout logic - 30 George Chao Pad frame
- 10 Peter Denes Organization, pads. (no cost to
project) - LBNL purchases/fabrications
- Assume a second iteration of front end design (if
nothing else to fine tune lower current
modifications) 65K including test board.
8FY09
- Continue same level of design effort until
submission - For Dec. submission this is 25 of FY08 manpower
cost - Reduced effort still needed after submission in
FY09 for simulation and testing - Take 50 of FY08 cost for remaining 75 of FY09
- Finally need to cover test board design (based on
existing TPLL) and fabrication - EE, drafter, and board fab cost.
- Student-like personnel to operate test setup
- Cost of engineering run to be paid out of BL
replacement ATLAS project, which is MO-B with
the usual sharing. - 20 of 400K
9LBNL FE chip Cost breakdown FY08-09
10Chip Requirements
Very difficult. Critical for power distribution
and material
High luminosity and small radius. Wants new ROD
Low value given by planar sensors and high
value by 3D.
11ROD development
- ROD total bandwidth limited by output s-Link at
1.28Gb/s. - This is only enough for 8 chips at 160Mb/s each.
- This would have to fed into the ROD on 32 40Mb/s
inputs. - To read out a single R4cm layer would need 94
RODs! - It would be much cheaper and reliable to build
fewer new, faster RODs using modern components - Can keep the basic data flow architecture, but
simply implement within new FPGA. - This is NOT yet an urgent need. Could in
principle start in FY09 instead of FY08, but - There is available manpower in FY08
- Early design would feed-back into chip I/O
architecture, leading to a better system - There is synergy with PLL-based test setup needs
12ROD PLL test setup
- Interface definition is common to ROD and PLL
test setup work, and is needed for chip
architecture design. - Expertise at LBNL is common to ROD and PLL test
setup (same people) - FY08 Tasks to be covered in the ROD/PLL area are
- Interface definition
- Schematic layout of revised PLL test card
- Initial look at new generation candidate FPGA for
replacement ROD. - FY08 requested resources (split between chip and
ROD) - 0.2 FTE under 4.1.2.1
- 0.083 FTE under ROD
- 10K MS under ROD (Xilinix evaluation boards)
- FY09 requested resources (split between chip and
ROD) - 0.53 FTE under 4.1.2.1 (includes PLL test card
layout fab) - 0.3 FTE under ROD (prototype BOC and ROD design)
- 30K MS under 4.1.2.1 (PLL test card fab)
13LBNL ROD Cost breakdown FY08-09
14Other LBNL activities
- Progress in FY07 in
- 3D sensor testing and
- Nanowire carpet hybrid pixel development
- 3D sensor testing
- Minor involvement but very positive impact
- Established characterization setup at CERN
enabling test work by U. of Oslo - Provided test boards and debugging help
- Results from this work used to specify load
requirement on new 130nm amplifier. - Will need to increase involvement in FY09 once
first 130nm full chip is available - Note request for tester support in FY09 4.1.2.1.
15Nanowire carpet hybrid pixelsW. Kim (molecular
foundry), C. Tindall (eng.), H. Spieler (phys.),
M. Garcia-Sciveres (phys.), and brand new
addition CERN Medipix group
Concept shown at UCSC upgrade meeting Nov. 2005
2007 Realized implementation
16Nanowire carpet hybrid pixels (cont.)
- Funding sources so far
- LBNL molecular foundry (FY06)
- LBNL LDRD surplus (FY06)
- ATLAS project RD 0.07FTE (FY07)
- No explicit ATLAS RD request for FY08
Diode behavior of NW carpet sample fabricated by
C. Tindall in FY07