Title: CHAPTER 16 MATERIAL MANAGEMENT
1CHAPTER 16MATERIAL MANAGEMENT
2FIBER REINFORCED POLYMER REBAR
- The Need Reinforced concrete is a very common
building material for the construction of
facilities and structures - Insufficient concrete cover, poor design or
workmanship and the presence of large amounts
admixtures and as well as environmental factors
all can lead to cracking of the concrete and
corrosion of steel bars - The Technology composite materials made of
fibers embedded in a polymeric resin, also known
as fiber-reinforced polymers (FRPs) have become
an alternate to steel reinforcement for concrete
structures
3Dry Dock 4 Pearl Harbor, Hawaii
Caissons and port facilities
4MATERIAL MANAGEMENT PROCESS
- In the traditional contractual relationship, the
owner contracts with a GC or CM to build his
facilities and with an architect to perform the
design - The GC, through this contract with the owner, is
obliged to perform the work in accordance with
the architects instructions, specifications and
drawings. Thus the architect is the owners agent
during the design and construction of a project - The lines of communication between the three
parties are established as shown in fig. 16-1 - The materials that comprise facilities in
building construction are subject to review by
the architect or design professional. - The contractor delegates responsibility for some
of the categories of work involved in the project
to subs and suppliers - As result of this delegation, a distinct life
cycle evolves for the materials that makes up the
project. - The four main phases of this cycle are shown in
fig. 16-2
5Fig. 16-1 The Owner-Architect-Construction
Relationship
Fig. 16-2 Material Life Cycle
6THE ORDER
- When the contract for construction is awarded,
the GC immediately begins awarding subcontracts
and purchase orders for the various parts of the
work. How much of the work is subcontracted
depends on the individual contractor - Some GCs subcontract all of the work in an
effort to reduce the risk of cost overruns and to
have every cost item assured through stipulated
sum subcontract quotations. Others perform almost
all the work with their own field forces - The subcontractor, through the agreement, must
provide all materials and perform all work
described in the agreement - AGC of America publish the standard subcontract
agreement for use by their members. See appendix
G for the sample of this agreement - All provisions of the agreement between the owner
and contractor are made part of the subcontract
agreement by reference - The most important referenced document in the
subcontract agreement is the General Conditions.
Procedures for the submittal of shop drawings and
samples of certain materials are established in
the General Conditions - The General Conditions provide that where a shop
drawings or sample is required by the Contract
Documents.any related work performed prior to
Engineers review and approval of the pertinent
submittal will be at the sole expense and
responsibility of the Contractor. - sales location, factory or the purchasers yard
or job site - The Bill of Lading is a contractual agreement
between a common carrier and a shipper to move a
specified item or group of goods from point A to
point B at a contracted price
7THE ORDER CONTD
- The purchase order is a purchase contract between
the contractor and the supplier. This document
describes the materials to be supplied, their
quantities and the amount of the purchase order - Purchase orders vary in complexity and can be as
simple as a mail order house (e.g., Sears) order
form, or as complex as the construction contract
itself - When complex and specially fabricated items are
to be included in the construction, very detailed
specifications and drawings become part of the
purchase order - Some typical purchase order forms are shown in
figures 16-3 and 16-4 - One item of importance in the order is the basis
of the price quotation and responsibility for
shipment - Price quotations normally establish an FOB
location at which point the vendor will make the
goods available to the purchaser - FOB means Free On Board and defines the fact that
the vendor will be responsible for presenting the
goods free on board at some mutually agreed upon
point such as the vendors - This is important because if the FOB location is
other than the vendors location, the vendor is
indicating that the price includes shipment - The vendor may quote the price as cost, insurance
and freight (CIF). This indicates that the quoted
price includes item cost plus the shipment cost
to include freight and insurance expenses to the
FOB location - In the event the vendor ships the goods, it is of
interest to establish at what point in time title
of ownership passes from vendor to the purchaser.
This is established by the Bill of Lading - If ownership passes to the purchaser at the
vendors location, the contract for shipment is
made out between the purchaser and the common
carrier
8THE ORDER CONTD
- In cases in which the vendor has quoted a CIF
price, he acts as the agent of the purchaser in
retaining a carrier and establishing the
agreement on behalf of the purchaser - The bill of lading is written to pass title of
ownership at the time of pickup of the goods by
the common carrier at the vendors location - If goods are to be paid on delivery (i.e., COD),
the title of ownership passes at the time of
payment. In such cases the bill of lading is
between the vendor and common carrier - The sequence of events in CIF and COD
transactions are shown in figures 16-6 and 16-7 - The invoices normally states the payment
procedure and establishes trade discounts that
are available to the purchaser if payment is made
in a timely fashion - Terminology relating to trade discounts is as
follows - ROG/AOG the discount period begins upon receipt
of goods (ROG) or arrival of goods (AOG) - 2/10 Net 30ROG this expression appearing on the
invoice means 2 can be deducted from the
invoiced amount if the carrier pays within 10
days of AOG/ROG. Full payment due within 30 days
of AOG/ROG - 2/10 PROX Net 30 payment is due in full by the
end of the following month - 2/10 EOM the discount (2) is available to the
11th of the month following ROG. Payment is due
in full there after - Trade discounts received are treated as earned
income in financial statements - The special conditions of the purchase order may
include a hold harmless clause. Such clause
protects one of the parties to the purchase order
from liability arising out of damages resulting
from the conditions of the purchase order
9Figure 16-3 Field Purchase Order
10Figure. 16-4 Formal Purchase Order
11Figure 16-5 Procurement Documents and Title
Transfer Sequence
12Fig. 16-6a Typical Bill of Lading
13Figure 16-6b Continued
14Figure 16-7 Typical Invoice
15APPROVAL PROCESS
- The contract drawings prepared by the architect
are generally not specific enough to facilitate
accurate fabrication of the materials involved - Therefore to produce the necessary materials for
a project, subcontractors and suppliers must
provide details that further amplify the contract
drawings - These details can be classified into three
groups - Shop drawings
- Product data
- Samples
- Shop drawings are defined in the general
conditions as All drawings, diagrams,
illustrations, schedules and other data or
information which are specifically prepared or
assembled by or for the contractor and submitted
by contractor to illustrate some portion of the
work. - Design professional are responsible for
verification that the supplied shop drawings
correctly interpret the contract documents - Dimensions, quantities and coordination with
other trades are the responsibility of the
contractor - Approved shop drawings become the critical
working drawings of a project and are considered
a part of the contract documents - Product data may be submitted to illustrate the
performance characteristics of the material items
described by the shop drawings or may be
submitted as verification that a standard product
meets the contract specifications - Product data are illustrations, standard
schedules, performance charts, instructions,
brochures, diagrams and other information
furnished by the contractor to illustrate a
material, product or system for some portion of
the work
16APPROVAL PROCESS CONTD
- Mill test reports, concrete mix designs, masonry
fire rating tests, curtain wall wind test reports
and mechanical equipment performance tests are
examples of product data - Product data are particularly important when a
subcontractor or supplier submits data on a
product that is variance from the contract
specifications - Samples usually involve the finishes of a project
and are physical examples of materials to be
supplied. The architect may require samples of
plastic laminate finishes for doors and counters,
flooring, wall coverings, paint, stucco, pre-cast
concrete, ceilings and other items - The approval process involving shop drawings,
product data, and samples have several sub stages
that are critical to the material life cycle.
These are - Submission by the sub or supplier
- Review of the submittal by the contractor
- Review by the architect or design professional
- Return of submittal to the sub or the supplier
- Usually six copies of shop drawings are submitted
for approval - Timing of submittals are submitted immediately or
15 days after the contract award - Once the submittals are reviewed by the
contractor, the process of checking for
conformance with the intent of the contract
documents is performed - A submittal, whether it is a shop drawing,
product data or sample is governed by the
contract drawings and specifications
17APPROVAL PROCESS CONTD
- The contractor is required by the general
conditions to clearly note to the architect or
design professional any variation from the
contract documents - The amount of time involved in the contractors
review of submittals may vary from 1-5 days - It must be remembered that time spent in
reviewing, checking and coordinating submittals
is one of the most effective methods of ensuring
a highly coordinated and smooth running project - Once the contractor has completed the review of a
submittal, the document is transmitted to the
architect for approval - As a general rule 2-3 weeks is a good estimate
for the time required by the architect to
complete the review and return the submittal - The final stage of the approval process for a
material item is the return of the submittal to
the supplier or subcontractor. The submittal may
be in one of the following four states when
returned to the contractor - 1) approved, 2) approved with noted corrections
no return submittal needed, 3) approved with
noted corrections however, a final submittal is
required, 4) not approved resubmit - The first through third designations would
release the vendor and subcontractor to commence
fabrication and delivery. The fourth stage would
require that the approval process be repeated - The material is now ready for fabrication and
delivery
18FABRICATION and DELIVERY PROCESS
- Of the four phases of materials life cycle the
fabrication and delivery process is the most
critical - Generally, the largest amount of time is lost/or
gained in this phase - The duration of the fabrication and delivery
process depends on directly on the nature of the
material and the amount of physical
transformation involved - Contractors generally devote the largest amount
of time and effort to controlling and monitoring
the fabrication and delivery phase - Unfortunately, the fabrication and the delivery
usually only become activities on the job
schedule when the delivery becomes a problem - At the completion of fabrication, the delivery of
the material is made and the final phase of the
life cycle is begun
19INSTALLATION PROCESS (CONSTRUCTABILITY)
- The installation process involves the physical
incorporation into the project of a material item - Depending on how effectively materials are
scheduled and expedited, materials arriving at
the job site may be installed immediately,
partially installed or stored or completely
stored for installation - One of the most important aspects of the
effective storage of materials is the physical
protection of material items. - The magnitude of the amount of materials involved
warrants meticulous layout of materials - Reinforcing steel, for instance, may be organized
in a lay-down area and then directly hoisted as
needed. Adequate lay-down areas must be provided
within each of the vertical hoisting equipment
20MATERIAL TYPES
- Building construction materials can be logically
grouped into three major categories - Bulk materials that require little or no
fabrication (table 16-1) - Manufacturers standard items that require
fabrication (table 16-2) - Items that are fabricated or customized for a
particular project (table 16-3) - Grouping materials into categories can be of
value in determining which materials warrant
major contractor control efforts - Obviously, material items that require
fabrication have longer life cycles because of
submittal requirements and fabrication. These
materials require a great deal of control by the
contractor - Bulk material category includes those materials
that require very little vendor modification and
can be delivered from vendor storage locations to
the job site with very little fabrication delay - Manufacturers standard material items include
materials that are usually stocked in limited
quantities and are manufactured for the project
after the order is executed and submittals are
approved - The fabricated category of construction materials
must conform to a particular projects unique
requirements - The fabricated item, is composed of or results
from modifications of standard components
21Table 16-1 Typical Bulk Materials
Table 16-2 Typical Standard Material Items
22(No Transcript)