CHAPTER 16 MATERIAL MANAGEMENT

1 / 22
About This Presentation
Title:

CHAPTER 16 MATERIAL MANAGEMENT

Description:

... that are available to the purchaser if payment is made in a timely fashion ... Product data are illustrations, standard schedules, performance charts, ... – PowerPoint PPT presentation

Number of Views:34
Avg rating:3.0/5.0
Slides: 23
Provided by: gsa63

less

Transcript and Presenter's Notes

Title: CHAPTER 16 MATERIAL MANAGEMENT


1
CHAPTER 16MATERIAL MANAGEMENT
2
FIBER REINFORCED POLYMER REBAR
  • The Need Reinforced concrete is a very common
    building material for the construction of
    facilities and structures
  • Insufficient concrete cover, poor design or
    workmanship and the presence of large amounts
    admixtures and as well as environmental factors
    all can lead to cracking of the concrete and
    corrosion of steel bars
  • The Technology composite materials made of
    fibers embedded in a polymeric resin, also known
    as fiber-reinforced polymers (FRPs) have become
    an alternate to steel reinforcement for concrete
    structures

3
Dry Dock 4 Pearl Harbor, Hawaii
Caissons and port facilities
4
MATERIAL MANAGEMENT PROCESS
  • In the traditional contractual relationship, the
    owner contracts with a GC or CM to build his
    facilities and with an architect to perform the
    design
  • The GC, through this contract with the owner, is
    obliged to perform the work in accordance with
    the architects instructions, specifications and
    drawings. Thus the architect is the owners agent
    during the design and construction of a project
  • The lines of communication between the three
    parties are established as shown in fig. 16-1
  • The materials that comprise facilities in
    building construction are subject to review by
    the architect or design professional.
  • The contractor delegates responsibility for some
    of the categories of work involved in the project
    to subs and suppliers
  • As result of this delegation, a distinct life
    cycle evolves for the materials that makes up the
    project.
  • The four main phases of this cycle are shown in
    fig. 16-2

5
Fig. 16-1 The Owner-Architect-Construction
Relationship
Fig. 16-2 Material Life Cycle
6
THE ORDER
  • When the contract for construction is awarded,
    the GC immediately begins awarding subcontracts
    and purchase orders for the various parts of the
    work. How much of the work is subcontracted
    depends on the individual contractor
  • Some GCs subcontract all of the work in an
    effort to reduce the risk of cost overruns and to
    have every cost item assured through stipulated
    sum subcontract quotations. Others perform almost
    all the work with their own field forces
  • The subcontractor, through the agreement, must
    provide all materials and perform all work
    described in the agreement
  • AGC of America publish the standard subcontract
    agreement for use by their members. See appendix
    G for the sample of this agreement
  • All provisions of the agreement between the owner
    and contractor are made part of the subcontract
    agreement by reference
  • The most important referenced document in the
    subcontract agreement is the General Conditions.
    Procedures for the submittal of shop drawings and
    samples of certain materials are established in
    the General Conditions
  • The General Conditions provide that where a shop
    drawings or sample is required by the Contract
    Documents.any related work performed prior to
    Engineers review and approval of the pertinent
    submittal will be at the sole expense and
    responsibility of the Contractor.
  • sales location, factory or the purchasers yard
    or job site
  • The Bill of Lading is a contractual agreement
    between a common carrier and a shipper to move a
    specified item or group of goods from point A to
    point B at a contracted price

7
THE ORDER CONTD
  • The purchase order is a purchase contract between
    the contractor and the supplier. This document
    describes the materials to be supplied, their
    quantities and the amount of the purchase order
  • Purchase orders vary in complexity and can be as
    simple as a mail order house (e.g., Sears) order
    form, or as complex as the construction contract
    itself
  • When complex and specially fabricated items are
    to be included in the construction, very detailed
    specifications and drawings become part of the
    purchase order
  • Some typical purchase order forms are shown in
    figures 16-3 and 16-4
  • One item of importance in the order is the basis
    of the price quotation and responsibility for
    shipment
  • Price quotations normally establish an FOB
    location at which point the vendor will make the
    goods available to the purchaser
  • FOB means Free On Board and defines the fact that
    the vendor will be responsible for presenting the
    goods free on board at some mutually agreed upon
    point such as the vendors
  • This is important because if the FOB location is
    other than the vendors location, the vendor is
    indicating that the price includes shipment
  • The vendor may quote the price as cost, insurance
    and freight (CIF). This indicates that the quoted
    price includes item cost plus the shipment cost
    to include freight and insurance expenses to the
    FOB location
  • In the event the vendor ships the goods, it is of
    interest to establish at what point in time title
    of ownership passes from vendor to the purchaser.
    This is established by the Bill of Lading
  • If ownership passes to the purchaser at the
    vendors location, the contract for shipment is
    made out between the purchaser and the common
    carrier

8
THE ORDER CONTD
  • In cases in which the vendor has quoted a CIF
    price, he acts as the agent of the purchaser in
    retaining a carrier and establishing the
    agreement on behalf of the purchaser
  • The bill of lading is written to pass title of
    ownership at the time of pickup of the goods by
    the common carrier at the vendors location
  • If goods are to be paid on delivery (i.e., COD),
    the title of ownership passes at the time of
    payment. In such cases the bill of lading is
    between the vendor and common carrier
  • The sequence of events in CIF and COD
    transactions are shown in figures 16-6 and 16-7
  • The invoices normally states the payment
    procedure and establishes trade discounts that
    are available to the purchaser if payment is made
    in a timely fashion
  • Terminology relating to trade discounts is as
    follows
  • ROG/AOG the discount period begins upon receipt
    of goods (ROG) or arrival of goods (AOG)
  • 2/10 Net 30ROG this expression appearing on the
    invoice means 2 can be deducted from the
    invoiced amount if the carrier pays within 10
    days of AOG/ROG. Full payment due within 30 days
    of AOG/ROG
  • 2/10 PROX Net 30 payment is due in full by the
    end of the following month
  • 2/10 EOM the discount (2) is available to the
    11th of the month following ROG. Payment is due
    in full there after
  • Trade discounts received are treated as earned
    income in financial statements
  • The special conditions of the purchase order may
    include a hold harmless clause. Such clause
    protects one of the parties to the purchase order
    from liability arising out of damages resulting
    from the conditions of the purchase order

9
Figure 16-3 Field Purchase Order
10
Figure. 16-4 Formal Purchase Order
11
Figure 16-5 Procurement Documents and Title
Transfer Sequence
12
Fig. 16-6a Typical Bill of Lading
13
Figure 16-6b Continued
14
Figure 16-7 Typical Invoice
15
APPROVAL PROCESS
  • The contract drawings prepared by the architect
    are generally not specific enough to facilitate
    accurate fabrication of the materials involved
  • Therefore to produce the necessary materials for
    a project, subcontractors and suppliers must
    provide details that further amplify the contract
    drawings
  • These details can be classified into three
    groups
  • Shop drawings
  • Product data
  • Samples
  • Shop drawings are defined in the general
    conditions as All drawings, diagrams,
    illustrations, schedules and other data or
    information which are specifically prepared or
    assembled by or for the contractor and submitted
    by contractor to illustrate some portion of the
    work.
  • Design professional are responsible for
    verification that the supplied shop drawings
    correctly interpret the contract documents
  • Dimensions, quantities and coordination with
    other trades are the responsibility of the
    contractor
  • Approved shop drawings become the critical
    working drawings of a project and are considered
    a part of the contract documents
  • Product data may be submitted to illustrate the
    performance characteristics of the material items
    described by the shop drawings or may be
    submitted as verification that a standard product
    meets the contract specifications
  • Product data are illustrations, standard
    schedules, performance charts, instructions,
    brochures, diagrams and other information
    furnished by the contractor to illustrate a
    material, product or system for some portion of
    the work

16
APPROVAL PROCESS CONTD
  • Mill test reports, concrete mix designs, masonry
    fire rating tests, curtain wall wind test reports
    and mechanical equipment performance tests are
    examples of product data
  • Product data are particularly important when a
    subcontractor or supplier submits data on a
    product that is variance from the contract
    specifications
  • Samples usually involve the finishes of a project
    and are physical examples of materials to be
    supplied. The architect may require samples of
    plastic laminate finishes for doors and counters,
    flooring, wall coverings, paint, stucco, pre-cast
    concrete, ceilings and other items
  • The approval process involving shop drawings,
    product data, and samples have several sub stages
    that are critical to the material life cycle.
    These are
  • Submission by the sub or supplier
  • Review of the submittal by the contractor
  • Review by the architect or design professional
  • Return of submittal to the sub or the supplier
  • Usually six copies of shop drawings are submitted
    for approval
  • Timing of submittals are submitted immediately or
    15 days after the contract award
  • Once the submittals are reviewed by the
    contractor, the process of checking for
    conformance with the intent of the contract
    documents is performed
  • A submittal, whether it is a shop drawing,
    product data or sample is governed by the
    contract drawings and specifications

17
APPROVAL PROCESS CONTD
  • The contractor is required by the general
    conditions to clearly note to the architect or
    design professional any variation from the
    contract documents
  • The amount of time involved in the contractors
    review of submittals may vary from 1-5 days
  • It must be remembered that time spent in
    reviewing, checking and coordinating submittals
    is one of the most effective methods of ensuring
    a highly coordinated and smooth running project
  • Once the contractor has completed the review of a
    submittal, the document is transmitted to the
    architect for approval
  • As a general rule 2-3 weeks is a good estimate
    for the time required by the architect to
    complete the review and return the submittal
  • The final stage of the approval process for a
    material item is the return of the submittal to
    the supplier or subcontractor. The submittal may
    be in one of the following four states when
    returned to the contractor
  • 1) approved, 2) approved with noted corrections
    no return submittal needed, 3) approved with
    noted corrections however, a final submittal is
    required, 4) not approved resubmit
  • The first through third designations would
    release the vendor and subcontractor to commence
    fabrication and delivery. The fourth stage would
    require that the approval process be repeated
  • The material is now ready for fabrication and
    delivery

18
FABRICATION and DELIVERY PROCESS
  • Of the four phases of materials life cycle the
    fabrication and delivery process is the most
    critical
  • Generally, the largest amount of time is lost/or
    gained in this phase
  • The duration of the fabrication and delivery
    process depends on directly on the nature of the
    material and the amount of physical
    transformation involved
  • Contractors generally devote the largest amount
    of time and effort to controlling and monitoring
    the fabrication and delivery phase
  • Unfortunately, the fabrication and the delivery
    usually only become activities on the job
    schedule when the delivery becomes a problem
  • At the completion of fabrication, the delivery of
    the material is made and the final phase of the
    life cycle is begun

19
INSTALLATION PROCESS (CONSTRUCTABILITY)
  • The installation process involves the physical
    incorporation into the project of a material item
  • Depending on how effectively materials are
    scheduled and expedited, materials arriving at
    the job site may be installed immediately,
    partially installed or stored or completely
    stored for installation
  • One of the most important aspects of the
    effective storage of materials is the physical
    protection of material items.
  • The magnitude of the amount of materials involved
    warrants meticulous layout of materials
  • Reinforcing steel, for instance, may be organized
    in a lay-down area and then directly hoisted as
    needed. Adequate lay-down areas must be provided
    within each of the vertical hoisting equipment

20
MATERIAL TYPES
  • Building construction materials can be logically
    grouped into three major categories
  • Bulk materials that require little or no
    fabrication (table 16-1)
  • Manufacturers standard items that require
    fabrication (table 16-2)
  • Items that are fabricated or customized for a
    particular project (table 16-3)
  • Grouping materials into categories can be of
    value in determining which materials warrant
    major contractor control efforts
  • Obviously, material items that require
    fabrication have longer life cycles because of
    submittal requirements and fabrication. These
    materials require a great deal of control by the
    contractor
  • Bulk material category includes those materials
    that require very little vendor modification and
    can be delivered from vendor storage locations to
    the job site with very little fabrication delay
  • Manufacturers standard material items include
    materials that are usually stocked in limited
    quantities and are manufactured for the project
    after the order is executed and submittals are
    approved
  • The fabricated category of construction materials
    must conform to a particular projects unique
    requirements
  • The fabricated item, is composed of or results
    from modifications of standard components

21
Table 16-1 Typical Bulk Materials
Table 16-2 Typical Standard Material Items
22
(No Transcript)
Write a Comment
User Comments (0)