Title: Stakeholder Meeting
1Stakeholder Meeting 6
March 28, 2002
2Todays Agenda
- Project Status
- Review of Project Alternatives for the Pajaro
River Mainstem - Overview of Army Corps of Engineers Process
- Detailed analysis of project alternatives.
- Continued public and stakeholder involvement.
- Flood Protection Alternatives for Corralitos and
Salsipuedes Creeks - Financial Overview
March 28, 2002
3Project Status
- Since June 2001
- Set out to achieve consensus on a single Flood
Project Concept for Pajaro and tributaries. - Evaluated over 10 concepts to achieve 100-year
flood protection. - Established agreement that final Project will
involve a combination of flood project elements
(Hybrid approach) including - Some floodwalls/levee raising
- Bridge modification/replacements
- Some vegetation management
- Some dredging
- Some set-back onto agricultural land.
-
March 28, 2002
4Project Status-Working Group Design Criteria
- Design Criteria for Maximum Consensus
- Urban Reach
- No Set-back
- Maximum Floodwall/Levee Raise 4 feet.
- Agricultural Reaches
- Maximum 100 set-back on each side
- Levee raise 5 feet.
- Vegetation and Channel Roughness
- Need vegetation for stability, permitting,
riparian habitat and maintainability - Levees need to be reconstructed
- 100-Year Level of Protection-if possible
March 28, 2002
5Alternatives Advanced by Working Group
March 28, 2002
6Alternative 1 Hybrid with 100-year Protection
Reach 1
Reach 2
Reach 3
Reach 4
7Alternative 1a Variation Hybrid with 100-year
Protection
Reach 1
Reach 2
Reach 3
Reach 4
8Alternative 2 Option with Lower Level of
Protection
Option for a Lower Level of Protection
- 30-year protection below urban area is a non
starter - 50-year protection in all reaches has been
modeled (preliminary) - 50-100 ft. setback on both sides in reaches1,2,4.
- 4 ft. levee raise throughout all reaches.
- Provides for 40,000 cfs protection (50 Year) with
Alternative 1 roughness and three feet of
freeboard. - Highest flow since 194030,000 CFS
- FEMA insurance still required, but premiums
reduced. - Other options from Army Corps of Engineers
March 28, 2002
9Project Alternatives
Alternative 1 and 1a
Alternative 2
100-year Protection Hybrid Option
Option with lower level of protection
Floodwalls/Levee Raising
Setbacks
- No Set-backs
- Levee/FW raise for 100-year flows
- Raise heights of 7-10 ft
- Velocities Scour not likely to be permittable
- 225setback each side
- Vegetation roughness to accommodate 300
vegetated corridor - Requires 517 acres agricultural land.
-
March 28, 2002
10Corps of Engineers Process Overview
- 3 alternatives from Stakeholder process will be
carried forward. - Some alternatives will no longer be evaluated in
depth.
- Further hydraulic analysis
- Cost estimating of alternatives
- Benefit/Cost Analysis
- Preliminary environmental analysis
- Coordination Act consultation with USFWS and NMFS
- Counties asked to comment and concur on a
recommended plan. - One recommended plan presented to Army Corps of
Engineers Headquarters.
- Final Draft EIR/EIS.
- Public comment and response.
- Certification under NEPA.
- CEQA certification.
11Corps of Engineers Process Overview
- 3 alternatives from Stakeholder process will be
carried forward. - Some alternatives will no longer be evaluated in
depth.
- Further hydraulic analysis
- Cost estimating of alternatives
- Benefit/Cost Analysis
- Preliminary environmental analysis
- Coordination Act consultation with USFWS and NMFS
- Counties asked to comment and concur on a
recommended plan. - One recommended plan presented to Army Corps of
Engineers Headquarters.
- Final Draft EIR/EIS.
- Public comment and response.
- Certification under NEPA.
- CEQA certification.
12Further Evaluation of Project Alternatives
Alternative 1 and 1a
Alternative 2
Other Alternatives developed by the COE
100-year Protection Hybrid Option
Option with lower level of protection
Army Corps of Engineers is proceeding with
detailed evaluation
Hydraulic Analysis
Cost Estimates
Benefit/Cost Analysis
Preliminary Environmental Analysis
Coordination Act
13Detailed Evaluation of Project Alternatives
Hydraulic Analysis
Cost Estimates
Benefit/Cost Analysis
Preliminary Environmental Analysis
Coordination Act
- Detailed alignments, heights, and effects of
vegetation and roughness scenarios. - Risk and uncertainty.
March 28, 2002
14Detailed Evaluation of Project Alternatives
Hydraulic Analysis
Cost Estimates
Benefit/Cost Analysis
Preliminary Environmental Analysis
Coordination Act
- Each alternative will be analyzed for a detailed
cost estimate.
March 28, 2002
15Detailed Evaluation of Project Alternatives
Hydraulic Analysis
Cost Estimates
Benefit/Cost Analysis
Preliminary Environmental Analysis
Coordination Act
- Determine which alternative provides the optimum
flood damage avoidance, given the project cost.
March 28, 2002
16Detailed Evaluation of Project Alternatives
Preliminary Environmental Analysis
Coordination Act
Hydraulic Analysis
Cost Estimates
Benefit/Cost Analysis
March 28, 2002
17Detailed Evaluation of Project Alternatives
Hydraulic Analysis
Cost Estimates
Benefit/Cost Analysis
Preliminary Environmental Analysis
Coordination Act
March 28, 2002
18Further Evaluation of Project Alternatives
- Fish and Wildlife Coordination Act
- Conducted by USFWS under contract with COE
- Determines impacts of alternatives on fish
wildlife - Recommends types and amounts of mitigation for
losses - Prepares Biological Assessment for NMFS for
Steelhead - This process will start early (April 2002) to
address permitting standards regarding
vegetation. - Stakeholders will be involved through special
subject focus group meetings and the October 2002
Stakeholder Meeting will focus on this subject. - In the absence of a local consensus on this
subject, this process will determine the minimum
requirements.
March 28, 2002
19Further Evaluation of Project Alternatives
- Federal Agency Coordination Requirements
- Project that causes no further degradation of
existing riparian/riverine habitat or - Project that allows natural processes to improve
habitat or ideally, - Project that improves habitat while providing
flood control. - Because the Project will need some vegetation
control as part of future maintenance, the Corps
of Engineers must consult under Section 7. - Source page 82 Status Report-COE Response to
jurisdictional questions
March 28, 2002
20Milestones and Opportunities for Public Input
2002 Milestones
21Corps of Engineers Process Overview
- 3 alternatives from Stakeholder process will be
carried forward. - Some alternatives will no longer be evaluated in
depth.
- Further hydraulic analysis
- Cost estimating of alternatives
- Benefit/Cost Analysis
- Preliminary environmental analysis
- Coordination Act consultation with USFWS and NMFS
- Counties asked to comment and concur on a
recommended plan. - One recommended plan presented to Army Corps of
Engineers Headquarters.
- Final Draft EIR/EIS.
- Public comment and response.
- Certification under NEPA.
- CEQA certification.
22Milestones and Opportunities for Public Input
2003 Milestones
23Flood Protection for Corralitos and Salsipuedes
Creeks
24Level of Flood Protection on Creeks
Capacity on Salsipuedes and Corralitos Creeks
With 0 Feet of Freeboard
25Level of Flood Protection on Creeks
26Flood Protection Concepts for the Creeks
Concepts evaluated for hydraulic proficiency
- Levee raise and floodwall
- Setback levee/floodwall
- Increased/improved storage in College Lake
- Flow bypass (Floodplain and Tunnel)
27Flood Protection Concepts-Existing Conditions
28Flood Protection Concepts for the Creeks
Questions from previous Stakeholder Meeting
- Interior Drainage
- Threats of flooding from more than just the
creeks. - Channel Maintenance
- It appeared that Salsipuedes is filling up with
sediment, thus reducing the capacity and causing
more flooding.
29Channel Maintenance
CHANNEL INVERT PROFILES
110
110
100
100
90
90
80
80
HWY 152
HWY 152
GREEN VALLEY RD.
70
70
GREEN VALLEY RD.
Invert Elevation (ft)
60
60
50
50
40
40
HWY 129
HWY 129
55.0' (1968 Bridge Plans)
55.0' (1968 Bridge Plans)
30
30
52.9' (1936 Bridge Plans)
52.9' (1936 Bridge Plans)
51.6' (College Lake Outlet Invert)
51.6' (College Lake Outlet Invert)
20
20
10
10
Pajaro River
Pajaro River
0
0
0
4,000
8,000
12,000
16,000
20,000
24,000
28,000
0
4,000
8,000
12,000
16,000
20,000
24,000
28,000
River Station (ft)
River Station (ft)
1949
1969
1995
March 28, 2002
30Flood Protection Concepts for the Creeks
Key Hydraulic Observations
- Sediment removal from Salsipuedes Creek is not a
stand-alone solution. - Although the existing system still handles design
flow, we are attempting to manage 2-2 ½ times
that amount. - College Lake storage must be part of the
solution. - Corralitos Creek has the least capacity spills
out first. - Interior drainage problems exist resolution must
be a part of the solution. - Bridges at Highway 129 and 152 are constrictions
and will likely need replacing.
31Flood Protection Concepts for the Creeks
Hydraulic Constraints
32Flood Protection Concepts for the Creeks
Illustration of Basic Dynamics
- Creek Width vs. Creek Water Surface
- Creek Width vs. College Lake Water Surface
- College Lake Outfall Size vs. Salsipuedes Creek
Flow - Increased College Lake Water Surface vs. Nearby
Homes and Businesses
33Flood Protection Concepts for the Creeks
Potential Elements of Solution
- Include some setbacks and bench excavation to
lower water surface. - Improve College Lake storage to limit downstream
flows. - Include interior drainage improvements.
- Include permittable maintenance activities.
- Use a combination of levees, floodwalls, and
setbacks on both creeks. - Address the need for bridge replacement.
34Financial Framework
35Financial Analysis of Flood Protection
Alternatives
Financial Analysis Framework will
- Overview of Project Costs
- Local Share vs Federal Share
- Unfunded Local Share
- Tax/Benefit Assessment Options
March 28, 2002
36Total Project Costs (for discussion only)
37Total Project Costs (for discussion only)
38Total Project Costs (for discussion only)
39Total Project Costs (for discussion only)
40Total Project Costs (for discussion only)
41Property in the Floodplain
Land Use Types
Totals
Monterey County
Santa Cruz County
Amount
Amount
Amount
AGRICULTURE
Acres
3401.43
5096.85
8498.28
COMMERCIAL
Acres
48.86
316.73
365.59
Parcels
65
265
330
INDUSTRIAL
Acres
60.33
0
60.33
Parcels
27
27
INSTITUTIONAL
Acres
24.81
549.2
574.01
Parcels
25
206
231
RESIDENTIAL
Parcels
202
2066
2268
Acres
74.68
719.42
794.1
TOTALS
Acres
3610.11
6682.2
10292.31
Parcels
319
2537
2856
Percent of Total
35
65
100
42Stakeholder Meeting 6
March 28, 2002
43Project Alternatives No Longer Being Evaluated
44Project Alternatives No Longer Being Evaluated
Pure Floodwall/ Levee Raise
- Pure floodwall/levee raise with 100-year
protection in all reaches - Pure setbacks of 225 with 100-year protection in
all reaches - Loss of more than 500 acres of agricultural land.
Pure setbacks
March 28, 2002
45Project Alternatives No Longer Being Evaluated
Pure Floodwall/ Levee Raise
- Pure floodwall/levee raise with 100-year
protection in all reaches - Pure setbacks of 225 with 100-year protection in
all reaches - Insufficient in fully addressing flood waters.
- -No viable upstream solutions which are cost
effective - -No legal authority
- -Refer to pages 31-Project Status Report
Pure setbacks
Full upstream Retention/ Detention
March 28, 2002
46Project Alternatives No Longer Being Evaluated
Pure Floodwall/ Levee Raise
- Pure floodwall/levee raise with 100-year
protection in all reaches - Pure setbacks of 225 with 100-year protection in
all reaches - Insufficient in fully addressing flood waters.
- Unrealistic maintenance costs and lack of
permittability. - -Refer to Page 30-Project Status Report
Pure setbacks
Full upstream Retention/ Detention
Major Dredging
March 28, 2002
47Project Alternatives No Longer Being Evaluated
Pure Floodwall/ Levee Raise
- Pure floodwall/levee raise with 100-year
protection in all reaches - Pure setbacks of 225 with 100-year protection in
all reaches - Insufficient in fully addressing flood waters.
- Unrealistic maintenance costs and lack of
permittability. - Not geographically feasible.
- -Requires 450 acres ag land
- -Refer to Page 29-Project Status Report
Pure setbacks
Full upstream Retention/ Detention
Major Dredging
Full Bypass channels
March 28, 2002
48Alternatives Advanced by Working Group
March 28, 2002
49Project Alternatives
- No Set-backs
- Levee/FW raise for 100-year flows
- Raise heights of 7-10 ft
- Velocities Scour not permittable
- 225setback each side
- Vegetation roughness to accommodate 300
vegetated corridor - Requires 517 acres agricultural land.
-
March 28, 2002
50Further Evaluation of Project Alternatives
Alternative 1
Alternative 2
Alternative 3
Variation 100-year Protection Hybrid Option
Other Alternatives developed by the COE
100-year Protection Hybrid Option
Option with lower level of protection
Army Corps of Engineers is proceeding with
detailed evaluation
Hydraulic Analysis
Cost Estimates
Benefit/Cost Analysis
Preliminary Environmental Analysis
Coordination Act