Title: Ethanol Summit
1Ethanol Summit
- Clark Smith
- Nebraska Department of Environmental Quality
- Air Quality Permitting Section
- clark.smith_at_ndeq.state.ne.us
2Discussion Topics
- Construction Permit Triggers
- Commence Construction
3Construction Permit Triggers
- When is a construction permit required?
- When a source constructs, modifies, or
reconstructs an emissions unit, and - The change in emissions exceeds the thresholds in
Chapter 17 and/or Chapter 19 - OR
- When the existing permit is worded such that the
source cannot make the change they want
4Construction Permit Triggers
- Construction installation of a new emissions
unit or source - Modification any physical change in, or change
in method of operation, of an affected facility
which increase the amount of any air pollutant
(some exclusions) - Reconstruction a situation where the fixed
capital cost of the new components exceed 50 of
the fixed capital cost of a comparable entirely
new facility or source
5Construction Permit Triggers
- Does the project increase potential emissions in
levels that exceed thresholds in Chapter 17
and/or Chapter 19? - Does existing permit allow the change?
- How is permit worded?
- Any conditions that prohibit making the change?
6Construction Permit Triggers
- Source wants to change solvents. New solvent
contains VOCs in amounts that exceed the CP
thresholds CAS for the solvent not on HAP list. - Will this be a physical change or change in the
method of operation?
Answer YES, A Change in Method of Operation
7Construction Permit Triggers
- Source wants to change solvents. New solvent
contains VOCs in amounts that exceed the CP
thresholds CAS for the solvent not on HAP list. - Does this change require a permit?
Answer YES, Based on the information given, a
permit is needed.
WHY The potential emissions due to the change
exceed the construction permit thresholds in
Chapter 17 and/or Chapter 19.
8Construction Permit Triggers
- NOWSource has permit that requires all emissions
from solvent operations be sent to and controlled
by a thermal oxidizer. The controlled emissions
(using the control efficiency of the thermal
oxidizer for VOC) are less than CP thresholds. - Does this change require a permit?
Answer MAYBE, for VOC a permit is not required,
but is CAS for a solvent sufficient in
determining if HAPs are contained in the solvent
NO, if one or more of the components of the
solvent is a HAP, you will have to evaluate the
change in emissions for HAP.
9Construction Permit Triggers
- Ethanol plant wants to install 4th fermentation
tank and connect it to existing scrubber.
Uncontrolled emissions are greater than the CP
thresholds, controlled emissions are less than
the CP thresholds. - Will this be a physical change or change in the
method of operation?
Answer YES, A Physical Change
- Does this change require a permit?
Answer MAYBE,
You need to read your permit.
10Construction Permit Triggers
- Permit has enforceable requirement all emissions
from fermentation must be routed to and
controlled by a scrubber. - If this was the only condition associated with
the fermentation tanks, a permit would not be
required because the controlled emission rate
could be used in determining the increase in
emissions.
- Another condition states that the source is
permitted to construct three fermentation tanks. - Is a construction permit required?
Answer YES, A permit is needed to construct the
fourth fermentation tank.
11Construction Permit Triggers
- Key items to consider
- Will this change be considered a physical change
or change in method of operation? - Will there be a change in emissions?
- Which regulations am I subject to (Federal or
State)? - How is my permit worded?
- Did I look at all of my permit conditions?
12Commence Construction
- Title 129 and all construction permits require a
source to commence construction within 18
months of permit issuance. - What does it take to commence construction?
- Owner or operator has all necessary
preconstruction approvals (i.e. obtained proper
permits) and either has - Begun, or caused to begin, a continuous program
of physical on-site construction of the source - Entered into binding agreements or contractual
obligations which cannot be cancelled or modified
without substantial loss to the owner or operator
13Commence Construction
- Begun, or caused to begin a continuous program of
physical on-site construction refers to
construction activities that are permanent in
nature - Footings and Foundations
- Underground Utilities to serve an Emissions Unit
14Commence Construction
- Entering into binding agreements with substantial
losses - The agreements and/or contracts must be in
relationship to the physical on-site activities
(contract to build, contract for equipment) - EPA guidance suggests that the loss be in the
range of 10 of the overall cost of the project.
15Commence Construction
- Revised General Condition I.(F) in Construction
Permits - The date construction, reconstruction or
modification commenced as defined in Chapter 1,
Section 031. Notification shall be postmarked no
later than 30 days after such date and include a
summary description of whether the requirement
was met through - (a) Initiating physical on-site construction
activities of a permanent nature that meet the
definition of begin actual construction, or - (b) Entering into binding agreements or
contractual obligations. If this option is
used, the notice shall also include a brief
summary of each binding agreement or contractual
obligation entered into, the date of the
agreement or contract, and why it cannot be
cancelled or modified without substantial loss
to the owner or operator.
16Any Questions?
Thank You! Clark Smith NDEQ Air
Division clark.smith_at_ndeq.state.ne.us