Title: Materials Requirement Planning
1Materials Requirement Planning
- Selected Slides from Jacobs et al, 9th Edition
- Operations and Supply Management
- Chapter 18
- Edited, Annotated and Supplemented by
- Peter Jurkat
2Master Production Scheduling (MPS)
18-2
- Time-phased plan specifying how many and when the
firm plans to build each end item
Aggregate Plan (Product Groups)
3Aggregate Production Plan
Figure 14.2
4Master Production Schedule (MPS)
Can be expressed in any of the following terms
- A customer order in a job shop (make-to-order)
company - Modules in a repetitive (assemble-to-order or
forecast) company - An end item in a continuous (stock-to-forecast)
company
See MPSLotSizing.xls
5Additional MRP Scheduling Terminology
18-5
- Gross Requirements
- Scheduled receipts
- Projected available balance
- Net requirements
- Planned order receipt
- Planned order release
6BOM Example
7Bills of Material
- List of components, ingredients, and materials
needed to make product - Planning Bills (Pseudo Bills) A
- Created to assign an artificial parent to the BOM
- Used to group subassemblies to reduce the number
of items planned and scheduled - Used to create standard kits for production
- Modular Bills B C
- Modules are not final products but components
that can be assembled into multiple end items - Can significantly simplify planning and
scheduling
- Phantom Bills
- Describe subassemblies that exist only
temporarily - Are part of another assembly and never go into
inventory - Low-Level Coding D, E, G
- Item is coded at the lowest level at which it
occurs - BOMs a reprocessed one level at a time
- Provides product structure
- Items above given level are called parents
- Items below given level are called children
8BOM Example
9BOM Example
Required Part A 50 Part B 2 x number of
As (2)(50) 100 Part C 3 x number of As
(3)(50) 150 Part D 2 x number of Bs 2
x number of Fs (2)(100) (2)(300) 800 Part
E 2 x number of Bs 2 x number of Cs
(2)(100) (2)(150) 500 Part F 2 x number of
Cs (2)(150) 300 Part G 1 x number of Fs
(1)(300) 300
10Material Requirements Planning
18-10
- Materials requirements planning (MRP) is a means
for determining the number of parts, components,
and materials needed to produce a product - Number determined by counting
- if 3 widgets are needed for every framit
- then the number of widgets needed is 3 times the
number of framits - this is not rocket science - except when hundreds
of assemblies and thousands of parts are involved - MRP provides time scheduling information
specifying when each of the materials, parts, and
components, all with maybe different lead times,
should be ordered or produced - Dependent demand drives MRP
- MRP implemented by software systems
11Example of MRP Logic and Product Structure Tree
18-11
Given the product structure tree for A and the
lead time and demand information below, provide a
materials requirements plan that defines the
number of units of each component and when they
will be needed
Product Structure Tree for Assembly A
Lead Times A 1 day B 2 days C 1 day D 3
days E 4 days F 1 day
Total Unit Demand Day 10 50 A Day 8 20 B
(Spares) Day 6 15 D (Spares)
Number in parenthesis is number of child parts
needed for every parent part
1218-12
First, the number of units of A are scheduled
backwards to allow for their lead time. So, in
the materials requirement plan below, we have to
place an order for 50 units of A on the 9th day
to receive them on day 10.
1318-13
Next, we need to start scheduling the components
that make up A. In the case of component B
we need 4 Bs for each A. Since we need 50 As,
that means 200 Bs. And again, we back the
schedule up for the necessary 2 days of lead time.
LT 2
Spares
4x50200
1418-14
Finally, repeating the process for all
components, we have the final materials
requirements plan
See MRPScheduleWorksheet.xls and
MRPScheduleWorksheet.doc
15Types of Time Fences
18-15
- Frozen
- No schedule changes allowed within this window
- Moderately Firm
- Specific changes allowed within product groups as
long as parts are available - Flexible
- Significant variation allowed as long as overall
capacity requirements remain at the same levels
16Material Requirements Planning System
18-16
- Based on a master production schedule, a material
requirements planning system - Creates schedules identifying the specific parts
and materials required to produce end items - Determines exact unit numbers needed
- Determines the dates when orders for those
materials should be released, based on lead times
- Generates reports
1718-17
18Additional MRP Scheduling Terminology
18-18
- Gross Requirements
- Scheduled receipts
- Projected available balance
- Net requirements
- Planned order receipt
- Planned order release
19Closed Loop MRP
18-19
Production Planning Master Production
Scheduling Material Requirements
Planning Capacity Requirements Planning
- With addition of
- Purchasing
- other manufacturing functions
- dispatching, and
- scheduling
- MRP became MRP II, also often called
Manufacturing Requirements Planning - Then expansion to ERP came naturally if not easily