Project Management Part 5 Project Risk Management - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

Project Management Part 5 Project Risk Management

Description:

e b 6 k h,i 1. f b 4. Draw AOA and AON networks. Activity-on-Arrow ... Lead and lag times are also possible. Other Precedence Relationships. Finish-to-Start ... – PowerPoint PPT presentation

Number of Views:197
Avg rating:3.0/5.0
Slides: 25
Provided by: gregfr3
Category:

less

Transcript and Presenter's Notes

Title: Project Management Part 5 Project Risk Management


1
Project ManagementPart 5Project Risk
Management
2
Topic Outline Risk Management
  • Project risks and risk management
  • Identification of risks
  • Risk assessment and risk analysis
  • Contingency planning
  • Time and cost padding
  • Expected values
  • Risk management exercise
  • PERT analysis
  • Computer simulation analysis

3
Project Risks
  • Uncertainty? a random chance that something will
    happen, with no way to control whether it happens
  • Risk? an uncertain event or condition that could
    negatively impact project performance
  • Each risk has a likelihood, or probability, of
    occurring and possible outcomes if it does occur

4
Managing Risks
  • Since the project manager is responsible for
    project success, he or she can increase the
    likelihood of success by better managing risks
  • Risk management is a proactive approach to
    dealing with uncertainties rather than a reactive
    approach
  • Some risks can be disregarded and some can be
    avoided, but others should be planned for

5
Project Risk Management
  • Risk management in projects involves
  • Identifying risks
  • Assessing and analyzing the likelihood and
    impacts of risks
  • Trying to reduce the uncertainties (by gathering
    more information or making different decisions)
  • Trying to lessen the impacts of risks
  • Developing contingency plans for critical risks
  • Monitoring risks as the project progresses

6
PMIs View of Risk Management
  • Risk management consists of 6 subprocesses
  • Risk Management Planning
  • How to approach and conduct risk mgmt. activities
  • Risk Identification
  • Qualitative Risk Analysis
  • Assessing likelihoods and possible outcomes
  • Quantitative Risk Analysis
  • Computer simulations decision tree analysis
    etc.
  • Risk Response Planning
  • Risk Monitoring and Control

7
Identification of Risks
  • Identifying all of the possible events or
    conditions that might occur and may negatively
    impact project performance
  • A brainstorming session with the project team can
    be a helpful way to ensure that all important
    risks are identified
  • Determining symptoms or warning signs that
    indicate when the risk is about to occur
  • Determining root causes of the risk

8
Risk Assessment
  • This info. should be developed for each risk
  • Description of risk
  • All the possible outcomes of the risk
  • The magnitude or severity of the outcomes
  • Likelihood (probability) of the risk occurring,
    and likelihood of each possible outcome
  • When the risk might occur during the project
  • Interaction of the risk outcomes with other parts
    of this project or other projects

9
Risk Assessment Matrix
10
Risk Analysis Tools
  • Probability analysis
  • Decision tree analysis
  • Monte Carlo simulation analysis
  • Life-cycle cost analysis
  • Delphi techniques for consensus
  • Technology forecasting
  • Game theory analysis
  • PERT analysis
  • Sensitivity analysis
  • Expected value analysis

11
Reducing Risks
  • Try to reduce uncertainties (collect more
    information, use more reliable vendors, design
    for easy production, dont use leading edge
    technologies, etc.)
  • Try to reduce the severity of potential outcomes
    (purchase insurance, convince customer to share
    the risk impacts, train employees how to respond
    quickly, etc.)

12
Contingency Planning
  • A contingency plan is an alternative plan used if
    a risk event or condition occurs.
  • Examples
  • Having a backup supplier for a key material
  • Carrying a safety stock for a key part
  • Having an alternate distribution channel to send
    products to China (air instead of boat)
  • Having hurricane evacuation plans

13
Time and Cost Padding
  • Padding is a commonly used approach to address
    risks, since it is very easy to implement and
    since it protects against most minor risks
  • Padding refers to inflating the original time or
    cost estimates for activities or for the project
  • Unfortunately, this leads to longer project
    durations and higher costs

14
Time and Cost Padding
  • People will generally use up as much time and
    money as they are allowed (if you dont use it
    you lose it!)
  • Student syndrome? if extra padding is built into
    activity time estimates, some people are likely
    to procrastinate getting started, and then the
    protection against risk is lost
  • Although padding can be useful in reducing the
    severity of risk, it can also lead to
    inefficiencies and waste

15
Expected Values
  • A construction manager is trying to decide what
    size crew to schedule for tomorrow based on
    weather
  • Weather
  • Probability 10 20 30 40
    Expected
  • Alternative Nice Cold Rain Snow
    Value
  • Large crew 860 710 160 -350
    136
  • Med. crew 520 430 190 -120
    147
  • Small crew 280 240 170 130
    179
  • sample calculation
  • Large ? .10(860).20(710).30(160).40(-350)
    136

16
Risk Management Exercise
  • Nelson Mandela Bridge case (25 minutes)
  • Divide into small groups
  • Read case
  • Discuss the issues and answer these questions
  • How would you have identified the risks?
  • Using the table provided, discuss how the risks
    were addressed and/or how risks could have been
    addressed. Also, indicate any additional risks
    you can think of.
  • Indicate whether the risks listed are internal or
    external.
  • Describe how you would determine the expected
    values of the risks listed.
  • Do you think that risk was adequately managed in
    this project? Why?

17
Uncertain Task Durations
  • Probability distributions
  • Discrete, uniform, triangular, normal, beta, etc.
  • Most common way to consider task uncertainty is
    to estimate the most likely, pessimistic, and
    optimistic durations.
  • PERT analysis assumes a Beta distribution for
    each task

18
Estimating Task Times (with PERT)
  • Activity duration estimates
  • aoptimistic, mmost likely, bpessimistic time
  • Expected task duration
  • Te (a 4m b)/6
  • Variance of task duration
  • Var (b a)/62

19
PERT Example
  • Task Pred. Opt. Most Likely Pess.
    Te Var
  • a -- 3 4 6 4.167 0.250
  • b -- 2 3 4 3.000 0.111
  • c a 3 3 5 3.333 0.111
  • d a 2 2 2 2.000 0.000
  • e b 4 6 11 6.500 1.361
  • f b 3 4 4 3.833 0.028
  • g c,d 1 1 2 1.167 0.028
  • h e 4 4 4 4.000 0.000
  • i f 3 5 8 5.167 0.694
  • j e,g 3 6 10 6.167 1.361
  • k h,i 1 1 2 1.167 0.028
  • Te (a 4m b)/6 Var (b a)/62

20
PERT Example
  • Use Te values for task durations on project
    network to compute slack values.
  • The results of the new computations still shows
    path b-e-j as the critical path, with an expected
    project duration of
  • Tcp 3.000 6.500 6.167
  • Varcp 0.111 1.361 1.361
  • StdDevcp sqrt(2.833)
  • MS Project with 3 task durations

21
Goldratts Critical Chain
  • Assuming that an activity duration is known leads
    to underestimating project durations
  • Because of this, people tend to pad their time
    estimates
  • This may result in the student syndrome
  • What is that?
  • This in turn leads to procrastination, which can
    then result in missing the finish date

22
Goldratts Critical Chain
  • Add safety time buffers at strategic points in
    the project network
  • Safety time buffer at end of critical path is
    called a project buffer
  • Safety time buffer just before where noncritical
    paths feed into the critical path is called a
    feeding buffer.

23
Computer Simulation Analysis
  • General purpose simulation software can model how
    many products flow through all the machines in a
    factory and on to the warehouse. This capability
    is much more than what is needed to simulate
    projects.
  • Monte Carlo simulation is much simpler type of
    simulation analysis that we can use to model the
    uncertainty of task durations and costs.
  • Crystal Ball and _at_RISK are two such packages.

24
Crystal Ball and Project Analysis
  • Crystal Ball allows you to specify any type of
    probability distribution for each task.
  • You specify all precedence relationships.
  • It then shoots random numbers into your
    probability distributions to simulate thousands
    of completions of the project.
  • The result is a probability distribution of the
    total duration of the project, from which you can
    answer the what-if questions about how long the
    project might actually take.
Write a Comment
User Comments (0)
About PowerShow.com