Title: Project Description and Needs


1
(No Transcript)
2
Project Description and Needs
  • Lincoln Way Widening
  • Addition of a center-turn lane and safety
    improvements to the grade and
  • horizontal alignment.
  • Needs
  • Increase safety within the existing corridor
  • Reduce traffic congestion
  • Provide access management
  • Provide infrastructure improvement to foster
    economic development
  • along the corridor

3
Project Development to Date
  • Public Meeting reviewed and received input
    regarding
  • initial five alternatives
  • Alternative 3 - determined to be the preferred
    alternative
  • Right-Sizing of Alternative 3 - provided most
    economical

  • option, while meeting the
  • project needs
  • Preliminary Engineering in progress, near
    completion

4
Overview Right-Sized Alternative 3
  • Adding a turn lane using variable width widening
  • Constructing a barrier curb for safety and
    access control
  • Constructing a sidewalk and pedestrian buffer
  • Realigning Henderson and Guice Road for
    increased
  • safety and efficient travel
  • Improvements to State Street
  • Upgrading traffic signal at the intersection of
  • Lincoln Way and Route 48

5
Preferred Alternative Typical Section
6
Visualization of Roadway - Before
7
Visualization of Roadway - After
8
Preliminary Maintenance of Traffic During
Construction
  • Four Phases of Traffic Control places an
    emphasis on
  • minimizing disruption to business owners
  • Widen to the east maintaining two lanes on the
    west
  • Widen to the west maintaining two lanes on the
    east
  • Maintain pedestrian access through work zone
  • during construction
  • PennDOT will coordinate details with
  • municipality during Final Design
  • Maintain access to businesses

9
Traffic Signals Construction Upgrades
  • New signal at Henderson and Guice
  • Upgrade to the existing signal at State Street
  • Timing adjustments at Route 48

10
Driveway Adjustments ADA Compliance
  • Depressed concrete curb to define access
  • to businesses
  • Americans with Disabilities Act (ADA)
  • compliant ramps at all intersections
  • and driveway access points

11
Potential Required Right-of-Way
  • Several potential property, or sliver takes
  • Potential total takes or displacements to
    accommodate
  • safety improvements at Henderson and Guice
  • Right-of-Way acquisition process typically lasts
  • 18 to 24 months

12
Funding
  • Current Transportation Improvement Program (TIP)
  • Discussions currently on-going regarding TIP
    Update
  • Preliminary Engineering Estimate Currently Being
  • Developed

13
Next Steps
  • Complete Preliminary Engineering
  • Begin Final Design
  • Complete Right-of-Way acquisition plan
  • Advertise Project for Construction
  • Notice to proceed to selected contractor
  • Construction Phase / Open to Traffic

14
Milestone Schedule
15
Questions?