Temporary Housing Program - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Temporary Housing Program

Description:

The use of recreational travel trailers is no longer considered a viable option ... Elimination of costly and inefficient trailer disposition process ... – PowerPoint PPT presentation

Number of Views:45
Avg rating:3.0/5.0
Slides: 17
Provided by: TVO
Category:

less

Transcript and Presenter's Notes

Title: Temporary Housing Program


1
Federal Emergency Management Agency
  • Temporary Housing Program
  • Turn-Key Services Lease Proposal

2
Agenda
  • Temporary Housing Situation Assessment
  • Current State
  • Financial Assessment
  • Leasehold Program Proposal
  • FEMA Program Benefits
  • Storm House Team Members
  • Sample Ruggedized HUD Code Specs
  • Forest River Floor Plans

3
FEMA Temporary Housing Situation Assessment
  • Since the 2005 Hurricane season and due to
    significant public outcry, FEMA has sought to
    dramatically improve temporary housing
  • The use of recreational travel trailers is no
    longer considered a viable option
  • Disabled citizens in Louisiana filed a
    class-action lawsuit in 2006 and since FEMA has
    modified their guidelines to include as much as
    15 UFAS-compliant temporary housing in reserve
    inventories

4
Temporary Housing Procurement Current State
  • FEMA acquires temporary housing units from
    housing manufacturers and retailers
  • FEMA engages large prime contractors to
    facilitate the installation of these temporary
    housing units in post-natural disaster
    environments
  • Prime contractors in turn hire mid-sized
    contractors who then hire smaller subcontractors
    to perform the work
  • After its intended use, FEMA is responsible for
    repair and/or refurbishment for reuse or sale

5
FEMA Temporary Housing Financial Assessment
  • FEMA spends 75,000 and above for each installed
    temporary manufactured housing unit (mobile home)
  • On a monthly basis, FEMA pays over 4,200 per
    18-month lifecycle
  • In addition, the current program requires
    significant internal human resources to
    facilitate contracts and manage layers of
    independent contractors and subs
  • After 18 months or longer, FEMA either donates or
    auctions the unit through the GSA in order to
    recover residual value, if any
  • FEMA begins the process again after next disaster

6
Leasehold Program Proposal
  • 130 MPH Ruggedized 2BR Park Models and/or
    Ruggedized 2 or 3 BR HUD Code Manufactured Homes
    with UFAS compliance option from Forest River,
    Inc.
  • 130 MPH Temporary Foundation System
  • Complete Program Management Services
  • Finance
  • Design
  • Build
  • Purchase
  • Transportation
  • Staging
  • Installation
  • Maintenance
  • Deactivation
  • Refurbishment
  • Redeployment

7
Leasehold Program Proposal
  • A turn-key finance and operations program by
    Storm House, a collaboration of professional,
    FEMA-experienced emergency housing companies
    with manufactured housing units from Forest
    River, Inc. (a Berkshire Hathaway Company)
  • 1,000 or more ruggedized Forest River Park Models
    and/or HUD Code Manufactured Homes including
    transportation, staging, installation,
    maintenance, deactivation and refurbishment
    services
  • Projected monthly lease fees (1,000 unit order or
    above)
  • 3,000 for 2BR ANSI Code Model
  • 3,350 for 2BR HUD Code Model
  • 3,700 for 3BR HUD Code Model
  • 500 units per month transported and installed at
    FEMA post-disaster locations
  • Lease payments are commenced upon deployment of
    units by Storm House. Reduced fees for second
    lease term creates additional savings

8
FEMA Program Benefits
  • Direct cost reduction of approximately 500 to
    1,200 per unit each month during initial
    18-month lease term.
  • Savings of over twenty million dollars for a
    1,000 unit lease program
  • Approved ruggedized Forest River Park Models
    and/or HUD Code Manufactured Homes with UFAS
    compliant versions
  • Less headcount requirements for program
    implementation
  • Elimination of costly and inefficient trailer
    disposition process
  • Energy-efficient design reduces utility costs
  • Enhanced public perception of Federal Government
  • Reduced governmental liability through lease
    agreement
  • Improved indoor air quality via UV-based air
    filtration system
  • 130 MPH temporary foundation system

9
Storm House Team Members
  • The Gephardt Capital Group
  • Strategic Capital Advisors
  • Forest River, Inc.
  • FEMA Housing Manufacturer
  • SouthCoast Group
  • Emergency Housing Strategies
  • Mobile Disaster Structures
  • Emergency Housing Consultant
  • Telepier Foundations
  • Temporary Foundation Technologies

10
130 MPH Ruggedized HUD Code Specs
  • 14 x 40 (2BR) 14 x 56 HUD Code (3BR) Floor
    Plans
  • 2 x 6 Exterior Framing 2 SPF w/ 16 On Center
    8 Sidewalls
  • 16 On Center 40 lb. Load Roof Truss with 3/8
    Sheathing
  • Double I-Beam Through Axle Center Area with Extra
    Axle
  • High-Wind Metal Roofs with 5/12 Roof Pitch
  • Flame Retardant R19 Exterior Wall Insulation
  • Foam-backed Impact Resistant, Energy Efficient
    Siding
  • 200 Amp Electrical Service
  • Smoke Alarms with Battery Backup
  • Dual Pane Single Hung Tilt Windows w/ Removable
    Screens
  • Complete Furnishings Package
  • HVAC UV-based Air Filtration System
  • Exceeds New Formaldehyde Testing Requirements

11
Forest River 2 BR Park Model 12 x 36 400
Square Feet
12
Park Model Elevation
13
Forest River 2 BR HUD Code 14 x 40 560 Square
Feet
14
2BR HUD Code Elevation
15
Forest River 3 BR HUD Code14 x 56 784 Square
Feet
16
3BR HUD Code Elevation