Title: Individual Program Reviews
1(No Transcript)
2GPS Space and ControlOverview
- Accomplishments/Challenges/Way Ahead
- Block IIR/IIR-M Satellites
- Block IIF Satellites
- Control Segment
3Block IIR/IIR-M Satellite Description
- Post Modernization
- Modernized Signals Similar Power
- L1, L2 C/A, L2C
- L1, L2 P(Y)
- L1, L2 M-Code
- Design Life
- 10 Years
- 3 Rubidium Clocks
- IIR-M Satellites 14-21
- Pre Modernization
- Heritage Signals
- L1, C/A
- L1, L2 P(Y)
- Design Life
- 10 Years
- 3 Rubidium Clocks
- IIR Satellites 1-11
EARLY IMPROVED SECURITY ANTI-JAM
4Constellation Health/Status
- CURRENTLY 28 OPERATIONAL SATELLITES
- 3 Block IIs SVN13 Launched June 1989
- Oldest Operational Satellite
- 17 Block IIAs
- 8 Block IIRs
- Next Mission IIR-10 on 17 Oct 03
- 1st Block IIR with Enhanced Antenna Panel
First IIR-M Still Scheduled For July 04
Launch M-Code/Flex Power
5Constellation Average Peak ERD
As of 22 Aug 03
G
O
O
D
6 IIR/IIR-M Accomplishments
- IIR-M Technical Baseline Negotiated
- Tail-biting Convolutional Encoding
- Flex Power
- Security Requirements Established
- SAASM ICD Updated
- Missions IIR-8 and IIR-9 Launched100
Successful - IIR-9 Set Healthy In Record Time To Support
Operation Iraqi Freedom
7IIR/IIR-M Acquisition Approach
- Best Commercial Practices Vice Full Mil-Spec
- JPO Manpower DownsizedOversight Vice Insight
- No Formal FCA/PCALess DMCA Direct Review
- Concurrent Development and Production Schedule
Success Oriented - Assumed Security Approvals on Schedule
JPO/Contr
8IIR/IIR-M Industry Results
- PMPCB Parts Issues Overwhelming
- Tin Whiskers
- DC-DC Converter Capacitors
- Transmitter Driver Boards
- Schedule Concurrency Driving Decision Making
- Placeholders In Qual Units, Work-arounds
Abound - Pathfinder Vehicle At Cape
- Aurora of a High Risk Development Program
Team Needs to Step Up To The Challenge
9IIR/IIR-M Challenges
- 1st IIR-M Launch (Jul 04) In Jeopardy
- Parts Problems Continuing
- Antenna Panel Passive Inter-Modulation (PIM)
- Three (3) Panels Currently Qualified Others
Experiencing PIM Phenomenon - Root Cause Not Completely Understood Much Work
To Do - Timely Replenishment Of Aging Force
- OPS Tempo High 5 Launches Scheduled In FY04, 4
In FY05 - Fly Out of Block IIR in FY06
- Final IIR-M Satellite Currently Without A
Booster - Working Options To Include EELV
10IIR/IIR-M Way Ahead
- Execute Re-planned Schedule To Protect 1st IIR-M
Flight In Jul 04 - No Margin Remaining Requires Contractor
Dedication - Antenna Panel Passive Inter-Modulation (PIM)
- Panel For 1st IIR-M In Testing PIM Issues Being
Worked - Constellation Sustainment
- IIR-10 On Schedule For 31 Oct Launch IIR-11 On
15 Jan 04 - Three Additional Launches in 2004
11Block IIF Satellite Description
- Post Modernization
- Modernized Signals Similar Power
- L1 C/A, L2C
- L1, L2 P(Y)
- L1, L2 M-Code
- L5 New Civil Signal
- Design Life
- 12 Years
- 2 Rubidium and 1 Cesium Clocks
- 12-16 Satellite Production Run
- Pre Modernization
- Heritage Signals
- L1, L2 C/A
- L1, L2 P(Y)
- Design Life
- 15 Years
- 1 Rubidium and 3 Cesium Clocks
- 33 Satellite Production Run
IMPROVED ACCURACY, SECURITY ANTI-JAM
12IIF Accomplishments
- Production began on first 3 Space Vehicles - Nov
02 - Modernization Changes
- Development Definitized - Nov 02
- Production Negotiations completed - Jun 03
- Flex Power development started - Mar 03
- Basic Contract Settlement - May 03
- Antenna test site selected - May 03
- Launch Site preparations at Cape Canaveral
- 14 of 40 Component FCA/PCA conducted to date
13IIF Challenges
- M-Code
- Facility and Security Clearance Delays
- Protracted Specification Definitization
- Schedule delays for Navigation Data Unit and L
Band Test Set - Growing Costs
- Subcontractor Performance Rate Growth
- Additional costs for Navigation Payload, Assembly
Integration Test (AIT), Program Management,
System Engineering - Parts Obsolescence Issues for Space Vehicles
13-15 - Single Board Computer, Spacecraft Processor,
Combined Earth sensor, Rate Gyro Package, Remote
Multiplexer Unit, Power Regulating Equipment - Diminishing Parts Manufacturing Sources
- Rubidium Clocks
14IIF Way Ahead
- M-Code
- Working closely with JPO program protection
- Modified schedule to maintain first IIF delivery
- Growing Costs
- Government preparing budget unfunded requirements
- Parts Obsolescence Issues for Space Vehicles
13-15 - Identifying potential obsolete parts
- Qualify replacement parts FY05-06
- Diminishing Parts Manufacturing Sources
- Planning to purchase additional Rubidium clocks
to maintain industrial base
15Control Segment Description
- Post Modernization
- Upgrade Schedule
- IIR-M Upgrade for Legacy
- Delivery Oct 03
- Version 5
- 300 KSLOC
- Incremental Deliveries beginning Feb 03/Ops Jan
05 - M-Code Test Only
- 20KSLOC of simulator changes
- Version 6
- 184 KSLOC
- M-MSRE h/w upgrades
- Provide M-Code Capability
- Delivery Sep 05/Ops Mar 07
- Pre Modernization
- AEP Upgrade Schedule
- Version 3/4
- 1402 KSLOC
- Delivery Sep 01
- Version 5
- 269 KSLOC
- Single DeliverySep 03/Ops
- Jan 05
- High Risk
- Version 6
- Size 34 KSLOC
- Delivery Sep 05/Ops Mar 07
- Version 7 (option)
- Size 102 KSLOC
- Delivery Sep 07/Ops Mar 09
16Control Segment Accomplishments
- Launch, Anomaly and Disposal Ops (LADO)
- - Successfully shadowed IIR-8 and IIR-9 launches
using prototype system at CERES (Jan 03 and Mar
03) - - Completed SRR (Feb 03), PDR (Apr 03), and CDR
(Jun 03) - - Finished installing LADO Primary hardware
install in Mod 11 (Aug 03) - Architectural Evolution Plan (AEP)
- - Successfully ran OCS V3/4 Operational User
Evaluation (OUE) at Schriever AFB in the GPS
Support Facility (Feb 03) - - Completed OCS V5.0 Formal Qual Testing exactly
as scheduled with 94.6 of all requirements
passing (Mar 03) - - Finished Control Segment Integrated Baseline
Review (IBR) (Apr 03) - - Held Control Segment In-Process Design
Review (IPDR) and Independent Program Baseline
Review (IPBR) (Jun 03) - - Put Modernized Monitor Station Receive
Element (MMSRE) and IIR SAASM on contract (Jul
03) - - Concluded Level 2 Confidence Test for OCS V5.0
(Aug 03)
17Control SegmentChallenges
- - Launch, Anomaly and Disposal Ops (LADO)
- Finish facilities/fit-up for both LADO Space Ops
Centers - Define need for geographically-separated LADO
backup facility - - Architectural Evolution Plan (AEP)
- Complete OCS V5.2 Code and Unit Test on schedule
- Incorporate last-minute user operational
requirements/tools into V5.2 - Put lower-risk Transition CONOP in place
- Many requests to incorporate new community
requirements - Civil Monitoring, M-code, Flex Power, NIMA
interfaces - Significant resource contention for Development,
Testing, Training, Tech Order Verification,
Interface checkout - General Issues
- Funding for new community requirements
- Security regulations/instructions are changing in
the middle of acquisition - Getting comms and cryptographic equipment
installed by need dates
18Control SegmentWay Ahead
- Launch, Anomaly and Disposal Ops (LADO)
- Finish building out both LADO Space Ops Centers
(Oct 03) - Definitize LADO Cleanup Proposal (Nov 03)
- Complete software development on II/IIA/IIR
Release (Jan 04) - End FQT on II/IIA/IIR Release (May 04)
- Complete II/IIA/IIR System Test (Aug 04)
- Architectural Evolution Plan (AEP)
- Complete OCS V5.2 Code and Unit Test (Oct 03)
- Put Cleanup AEP Proposal, OCS V5.2 Flex Power
requirements, NISPOM Compliance, MMSRE Civil
Monitoring, Enhanced Phased Ops Transition, and
T.O. Verification on contract (on or before Dec
03) - Finish OCS V5.0 Level 1 Confidence Test (Dec 03)
- Conclude OCS V5.2 Integration and Test (Jan 04)
- Complete OCS V5.5 Requirements Analysis (Apr 04)
- Deliver OCS V5.2 software (Aug 04)
19GPS Space and Control Way Ahead
- Continue to sustain existing GPS constellation
- Next IIR launch expected in Oct 03
- Complete IIR-M and IIF development
- Needed for constellation sustainment
- 1st IIR-M Launch now scheduled for Jul 04
- 1st IIF Launch no earlier than Mar 05
- Deliver LADO and OCS V5.2
- Get off of AFSCN Command Control System by Oct
04 - Ready Control Segment for 1st IIF launch
- Continue to Evolve Control Segment
- Deliver SAASM capability in OCS V5.5 and Flex
Power in OCS V6