Financial Transmission Rights In an LMP System - PowerPoint PPT Presentation

1 / 44
About This Presentation
Title:

Financial Transmission Rights In an LMP System

Description:

East Coal $30.00. 80 MW Thermal. 100 MW Thermal. 90 MW Thermal. 50 MW ... East Coal $30.00. 90 Thermal MW. 90 Thermal MW. 50 Thermal MW. 80 Thermal ... East ... – PowerPoint PPT presentation

Number of Views:271
Avg rating:3.0/5.0
Slides: 45
Provided by: LECG9
Category:

less

Transcript and Presenter's Notes

Title: Financial Transmission Rights In an LMP System


1
Financial Transmission RightsIn an LMP System
  • Presentation to ERCOT Texas Nodal Team
  • By
  • John D. Chandley, LECGOctober 22, 2003
  • Austin, Texas

2
FINANCIAL RIGHTS Overview
  • In an LMP system, Transmission Rights are not
    needed to assure physical delivery or to get
    access to the grid. Physical delivery is assured
    through an ISOs bid-based security-constrained
    redispatch. Rights are needed to hedge the
    financial risks of congestion
  • Congestion effects are reflected in the nodal
    spot prices.
  • Transmission usage charges are defined by nodal
    price differences between the points of receipt
    and delivery.
  • Congestion effects on energy and transmission
    prices are not known until the dispatch and the
    RTO defines prices.
  • A system of price hedges -- financial
    transmission rights -- is needed to provide
    advance price certainty and to provide tradable
    property rights for the value of a congested grid.

3
FINANCIAL RIGHTS Terms
  • A common model of financial transmission rights
    has been implemented in PJM, New York and New
    England. The concept is the same, but the
    terminology varies by region
  • PJM -- FTRs fixed transmission rights.
  • New York -- TCCs transmission congestion
    contracts.
  • New England -- FTRs financial transmission
    rights.
  • These are all point-to-point rights, not flowgate
    rights (FGRs).
  • In PJM, there are both option and obligation
    FTRs.
  • In NY and NE, only obligation FTRs/TCCs are
    offered.
  • MISO has proposed both FTRs and FGRs, and both in
    options and obligations. MISO will probably
    start with just FTRs, but this is not certain.

4
FINANCIAL RIGHTS Why FTRs?
  • Financial transmission rights (or FTRs) serve
    multiple functions
  • FTRs enable market participants to obtain
    long-term transmission price certainty, analogous
    to physical transmission rights.
  • FTRs allow a party access to the price at other
    locations.
  • FTRs allow hedging and trading of rights without
    controlling physical operations.
  • So they dont restrict or undermine economic
    energy trading or an efficient dispatch.
  • FTRs provide a means to value grid upgrade
    investments, because they price the market value
    of avoiding congestion.

5
FINANCIAL RIGHTS Financial Instruments
  • FTRs are financial hedges, not physical rights.
  • Parties do not have to hold FTRs in order to
    schedule use of the system.
  • Hoarding FTRs cant preclude others from using
    the grid.
  • FTR holders are not required to trade their
    unused FTRs to obtain their value.
  • There is no use-it-or-lose-it rule.
  • FTR holders receive the market value of their
    rights even if they do not undertake a matching
    energy transaction.

6
FINANCIAL RIGHTS Efficient Dispatch
  • As financial rights, FTRs function without
    restricting physical operations.
  • FTR holders receive the market value of their
    rights even if they do not undertake a matching
    energy transaction.
  • FTRs support efficient dispatch, because FTR
    owners receive the economic value of their
    transmission rights regardless of how their
    generation is dispatched.
  • FTRs make trading of both transmission rights and
    energy easier and less costly than with exclusive
    physical rights because transmission usage is not
    tied to FTR ownership.

7
FINANCIAL RIGHTS Price Certainty
  • FTRs enable market participants to lock-in a
    price for transmission prior to the trading day.
  • The owner of a FTR is paid the hourly cost of
    congestion (/MWh) between two locations on the
    transmission system. This is the difference in
    nodal prices.
  • If the FTR owners net injections and withdrawals
    match the FTR quantities, then the FTR provides a
    financial hedge for the transmission
    congestion/usage charges -- the equivalent of a
    physical transmission right.
  • FTRs provide the financial equivalent of firm
    transmission for market participants that use
    their FTRs to support bilateral transactions.

8
(No Transcript)
9
FINANCIAL RIGHTS Full Hedging
  • FTR owners scheduling transactions between the
    delivery and receipt points designated by their
    FTR will be fully hedged against congestion
    costs.
  • Suppose Southeast LSE holds 25 FTRs from Bus L to
    Bus V.
  • If the LSE scheduled 25 MW of bilateral
    transmission from Bus L to Bus V, it would pay
    12.50/MWh (the difference in locational prices
    between Bus V and Bus L) in transmission
    congestion charges.
  • Southeast LSE would then receive 12.50/MWh of
    congestion rents for this hour (the difference in
    locational prices between the points specified in
    its FTR). The net usage charge for its schedule
    would be zero.

10
(No Transcript)
11
FINANCIAL RIGHTS Not Use-It-or-Lose-It
  • FTR holders will realize the value of their
    financial transmission rights regardless of their
    grid use.
  • Suppose Southeast LSE holds 50 FTRs from Bus L to
    Bus V, rather than 25 FTRs.
  • If Southeast LSE continued to schedule 25 MW of
    transmission from Bus L to Bus V, it would pay
    transmission congestion charges for this
    transaction.
  • Southeast LSE would still be paid congestion
    rents for its 50 FTRs. On a net basis, Southeast
    LSE would be paid 12.50/MW for the FTRs not used
    to hedge its actual use of the transmission
    system.

12
(No Transcript)
13
FINANCIAL RIGHTS Partial Hedging
  • FTR owners scheduling transactions between
    delivery and receipt points that differ from
    those designated in the FTR may still be
    partially hedged against congestion costs.
  • Suppose that Southeast LSE continued to own 25
    FTRs from Bus L to Bus V, but that it schedules
    25 MW of transmission from Bus A to Bus V to meet
    its load.
  • The LSE would pay 15/MWh (the difference in
    locational prices between Bus V and Bus A) in
    transmission congestion charges.
  • The LSE would then receive 12.50/MWh of
    transmission congestion rents for this hour (the
    difference in locational prices between the
    points specified in its FTR).
  • The net cost of congestion for its transmission
    schedule would be 2.50/MWh.

14
(No Transcript)
15
FINANCIAL RIGHTS Unpredictable Constraints
  • Importantly, FTRs can hedge grid users against
    transmission congestion even when the
    transmission congestion differs from the normal
    pattern.
  • In the example above, cheap energy at L and
    higher load at O have dramatically changed the
    pattern of congestion and increased the
    usage/congestion charges between L and V.
  • An LSE owning 25 FTR from Bus L to Bus V would
    still incur no net cost for its bilateral
    transmission schedule from Bus L to Bus V.
  • Transmission Charge L to V -62.50
  • FTR L to V 62.50
  • Net 0.00

16
FINANCIAL RIGHTS Revenue Adequacy
  • An important property of FTRs is revenue
    adequacy. When there is congestion under
    locational pricing, the differences in locational
    prices will cause the ISO to collect congestion
    rents.
  • Congestion rents fund payments to FTR holders.
  • Revenue adequacy means that the congestion rents
    the ISO collects will be sufficient for it to
    meet its financial obligations to FTR holders,
    regardless of the actual usage of the grid.

17
FINANCIAL RIGHTS FTR Obligations
  • The revenue adequacy test for FTRs is relatively
    straightforward to implement if FTRs are defined
    as obligations.
  • FTR obligations entitle the holder to payments if
    the price differential is positive, but require
    payments to the ISO if the price difference is
    negative.
  • A set of FTR obligations is revenue adequate if
    the set of injections and withdrawals
    corresponding to all of the FTRs is
    simultaneously feasible in a contingency
    constrained dispatch.

18
FINANCIAL RIGHTS Revenue Adequacy
Any simultaneously feasible set of net injections
and loads can describe a set of revenue-adequate
FTRs. That set of FTRs will remain
revenue-adequate even if actual grid use differs
from the set of injections and loads matching the
FTRs.
19
LOAD FLOW UPON WHICH FTR ALLOCATION IS BASED
(bilateral)
0
K
L
5 MW
25 MW
W
C
M
55 MW
87.5 MW
170 MW
A
Y
7.5 MW
22.5 MW
OUT OF SERVICE
IN CONTINGENCY
Z
75 MW
D
X
42.5 MW
100 MW
25 MW
12.5 MW
B
V
N
70 MW
P
O
SYSTEM LOAD 200 MW
20
FINANCIAL RIGHTS Revenue Adequacy
  • The diagram above illustrates the power flow that
    results if injections and withdrawals
    corresponding to the FTRs shown below are made.
  • Since this flow does not violate any of the
    transmission constraints in any contingency, the
    set of FTRs is revenue-adequate.
  • As long as the grids transfer capability when
    determining the day-ahead schedule is not
    reduced, the ISO will be able to meet its
    obligations to FTR holders in full.

21
(No Transcript)
22
FINANCIAL RIGHTS Revenue Adequacy
If the grid use exactly matches the FTRs, the
amount paid for congestion by each grid user will
exactly match the payments to its FTRs. In this
case, the ISO will collect exactly enough
congestion rents to compensate FTR owners.
23
(No Transcript)
24
FINANCIAL RIGHTS Revenue Adequacy
Even if the system dispatch does not match the
FTRs, the ISO will still collect enough revenues
to compensate FTR owners. In the dispatch
illustrated above, the ISO will collect 15,725
in payments by loads and 312.50 in payments by
transmission-only customers and will disburse
13,087.50 to generators. The ISO retains 2,950
in congestion rents.
25
(No Transcript)
26
FINANCIAL RIGHTS Revenue Adequacy
The ISOs obligations under the FTRs that have
been sold are computed below.
27
FINANCIAL RIGHTS Revenue Adequacy
  • The 2,950 in congestion rents collected by the
    ISO are more than the 2,937.50 in congestion
    rents it owes to the holders of FTRs.
  • If the dispatch of the system results in net
    injections and withdrawals matching FTR holdings,
    the congestion rents collected by the system
    operator will exactly offset the payments the ISO
    must make to FTRs holders.
  • The crux of the revenue adequacy theorem is that,
    even if the dispatch results in net injections
    and withdrawals that do not correspond to the
    outstanding FTRs, the congestion rents collected
    by the ISO will cover and may exceed its
    financial obligations to FTR holders.

28
FINANCIAL RIGHTS FTR Obligations
  • FTRs defined as obligations can be partitioned
    and reconfigured for trading, with the
    partitioned FTRs perfectly hedged by the original
    FTR.
  • A FTR from A to B entitles the holder to the same
    payments as FTRs from A to C and C to B.
  • Any FTR from A to B can be partitioned into two
    FTRs A to Hub and Hub to B.
  • Any FTR from A to C can be reconfigured into an A
    to B FTR by purchasing a C to B FTR.
  • This property does not extend to FTRs defined as
    options.

29
FINANCIAL RIGHTS FTR Options
  • In principle, it is possible to define both FTR
    obligations and FTR options. FTR options would
    entitle the holder to the difference in
    locational prices if this difference is positive,
    but would not require payment when it is
    negative.
  • The principal difficulty in implementing FTR
    options is the complexity of implementing the
    revenue adequacy test.
  • Until recently, this difficulty persuaded NY and
    PJM to offer only FTR obligations.
  • However, PJM has developed a method to determine
    the simultaneous feasibility of options.
  • PJM now offers both options and obligations in
    its FTR auctions.

30
FINANCIAL RIGHTS SFT for FTR Options
A set of FTR options is revenue adequate if the
set of injections and withdrawals corresponding
to the FTR options is simultaneously feasible in
a contingency constrained dispatch -- for all
possible levels of every FTR defined as an
option.1 Instead of verifying that a power flow
correspoinding to the set of all outstanding FTRs
is simultaneously feasible (the SFT for
obligations) the ISO must also verify that power
flows corresponding to all possible subsets of
the set of FTRs are simultaneously
feasible. ________________________________ 1Scott
M. Harvey, William W. Hogan, Susan L. Pope,
Transmission Capacity Reservations and
Transmission Congestion Contracts, August 7,
1996, pp. 45-46.
31
FINANCIAL RIGHTS Obligations vs Options
  • In general, more FTR obligations can be awarded
    than FTR options.
  • This is because the obligations may represent
    counterflow that makes other FTRs simultaneously
    feasible, and . . .
  • ISO would collect payments from these FTR
    obligation holders, to help maintain revenue
    adequacy.
  • But parties may prefer options in some
    situations.
  • So options will tend to be more valuable to the
    market
  • And with fewer of them, the prices will tend to
    be higher.

32
FINANCIAL RIGHTS Obligations vs Options
  • Parties may want either obligations or options,
    depending on their expected hedging needs. For
    example
  • An obligation might be preferred to hedge fairly
    constant transactions (e.g., from base-load
    plants to loads).
  • The congestion charges and FTR credits would
    always offset each other, even if the congestion
    flow/LMP differences were reversed.
  • But an option might be preferred for more
    sporadic transactions.
  • Because an obligation might result in payments
    when the transaction wasnt scheduled to offset
    them.
  • MISO proposes this split to deal with existing
    contracts.

33
FINANCIAL RIGHTS Obligations vs Options
  • The ISO might also use obligations and options
    differently when awarding FTRs to those who fund
    transmission upgrades.
  • Parties funding the upgrade might prefer the
    options . . .
  • But if the upgrade had the potential to make
    pre-existing FTRs infeasible, the ISO would also
    need to allocate offsetting obligations to ensure
    simultaneous feasibility and revenue adequacy for
    all outstanding FTRs.
  • Some parties might also want to sell counterflow
    forward through the ISO auction, by accepting FTR
    obligations with likely negative prices for a
    price. We see examples of this in PJM.
  • Theyre betting that the price they receive now
    for these obligations will be greater than the
    cost of providing counter-flow later.

34
FINANCIAL RIGHTS Revenue Adequacy
  • The revenue adequacy theorem assures that the ISO
    will collect sufficient congestion charges to pay
    financial rights holders if the full transfer
    capability of the grid assumed in the FTR
    allocation process is available.
  • In practice, the transfer capability of the grid
    may be less than that assumed in the FTR
    allocation, due to
  • Unplanned transmission outages or
  • Unexpected loop flow (higher than assumed).
  • In this situation, the ISO may not collect enough
    revenues in congestion charges to fully
    compensate financial rights holders.

35
FINANCIAL RIGHTS Revenue Adequacy
  • ISOs have adopted different mechanisms to address
    revenue inadequacy due to outages and loop flow.
  • PJM -- make up deficit from other hours in the
    month or year if possible, then prorate all FTRs
    in affected hours for residual inadequacy.
  • New York -- make up deficit from other hours in
    month if possible. Add any remaining deficit to
    the transmission owners revenue requirements and
    recover in rates.
  • NE-ISO -- make up deficit from other hours in
    month, then from accumulated surplus, then
    prorate all FTRs in affected hours.
  • NY ISO is also developing a FTR-based rate
    incentives for transmission owners to minimize
    outage costs. The TO would guarantee revenue
    adequacy during line outages over which it had
    control.

36
Flowgate Rights
37
FLOWGATE RIGHTS
  • It would be possible to use a system of financial
    flowgate rights in conjunction with an LMP
    system.
  • LMP transmission charges are determined by
    constraint shadow prices.
  • So, LMP transmission charges can, in principle,
    be hedged by holding an appropriate mix of
    flowgate rights for those constraints.
  • However, issues surrounding how to pick an
    appropriate mix and what happens if you cant,
    provoked a debate among market designers.

38
FLOWGATE RIGHTS WITH POINT-TO-POINT FTRS
  • Flowgate rights could be used to complement the
    system of point-to-point FTRs.
  • For example, MISO has considered a system that
    would offer both FTR obligations and options and
    FGR obligations and options.
  • The MISO proposal would have made FGR options and
    obligations available in periodic (monthly)
    auctions.
  • In theory, participants could choose the mix of
    FTRs vs FGRs they wanted through a single
    auction.

39
FLOWGATE RIGHTS AS OPTIONS OR OBLIGATIONS
  • In principle, financial flowgate rights can be
    defined as both options and obligations, just
    like point-to-point FTRs.
  • An FGR option entitles the holder to the payment
    of the constraint shadow price for that flowgate,
    if the constraint shadow price is positive.
  • An FGR obligation would entitle the holder to the
    payment of the constraint shadow price if the
    shadow price is positive, but would obligate the
    holder to pay the constraint shadow price if it
    is negative.

40
THE EARLY ATTRACTION OF FLOWGATE RIGHTS
  • The arguments in favor of flowgate rights have
    paralleled the arguments in favor of zonal versus
    nodal pricing.
  • A genuine desire to simplify the market to
    enhance trading.
  • A concern that point-to-point trading may not be
    easy.
  • A belief (or hope) that congestion will be
    limited to a few predictable commercially
    significant flowgates (CSFs) .
  • Parties would only need to get FGRs for a few
    CSFs.
  • And parties would know which flowgates to
    acquire.
  • Congestion costs on non-CSFs would be rare or
    unimportant (so an uplift would be okay).
  • A belief/hope that the flows across the small
    number of constraints are predictable stable
    distribution factors.
  • So parties could predict how many flowgates to
    acquire for each constraint/CSF, given their
    schedules expected flows and distribution
    factors.

41
ARE THE FLOWGATE ASSUMPTIONS VALID?
  • The ERCOT experience with zonal pricing mirrors
    findings in other large regions, such as
    California, PJM and New England, and applies to
    flowgates.
  • Congestion generally was much greater than
    expected.
  • Intra-zonal congestion was greater than expected.
  • So a few zones (and CSFs) were not enough.
  • For flowgates, this means there can be many
    constraints (and different types) that can have
    commercially significant consequences, and they
    change often.
  • Parties may need many FGRs to hedge each
    transaction, and the binding contingency can
    change quickly, changing the needed FGR mix.
  • Failure by participants to fully cover congestion
    on CSFs and non-CSFs with FGRs would result in
    incomplete hedges, unless their costs were
    socialized.
  • And failing to price any non-CSF constraints
    could lead to
  • Significant uplifts from the ISO managing these
    constraints
  • Possible gaming opportunities for market
    participants
  • I.e., just like zonal pricing.

42
EVOLUTION OF FLOWGATE PROPOSALS
  • Flowgate rights proposals have evolved over the
    last 2-3 years of debate, as seen in the MISO
    proposals
  • Physical FGRs were abandoned early on in favor of
    financial FGRs no use-it-or-lose-it rule.
  • Assumptions that there will only be a few CSFs
    were abandoned. Experience and modeling proved
    this wrong.
  • Assumptions that the distribution factors would
    remain stable were abandoned. (Grid
    contingencies change them.)
  • Hybrid proposals to fix the number of CSFs and/or
    the distribution factors (monthly) and force the
    ISO to manage the rest and socialize the costs
    were eventually abandoned.
  • Proposals now accept little/no socialization.
  • Each party has to pay full congestions costs via
    LMP and accept the risks of incomplete (or wrong
    mix of) hedges.

43
STATUS OF FLOWGATE DEBATE IN THE EAST
  • Prevailing current view FGRs may/may not be
    useful, but if FGRs are offered, the risks will
    be borne by the market participants
  • To pick the right flowgates to cover with FGRs
  • To pick the right number of rights for each
    flowgate
  • To bear the congestion costs for uncovered
    flowgates
  • ISO will avoid socializing costs of uncovered
    flowgates
  • Given these risks, MISO stakeholders agreed that
    FGRs offered by MISO will be short-run, based on
    short-run expectations
  • About where congestion is likely
  • About the conditions (e.g., planned grid outages)
    likely to affect distribution factors.
  • And FGRs not likely to be used for awards to
    those who pay for grid upgrades. PTP FTRs will
    be used for this.

44
INFORMATION ON THE FLOWGATE DEBATE
  • For further information on the flowgate vs
    point-to-point FTR debate and the evolution of
    flowgate proposals, an excellent source is
  • Letter and e-mail exchange between Drs. Shmuel
    Oren and Larry Ruff on flowgate rights systems,
    available on the following website
  • http//www.ksg.harvard.edu/hepg/
  • And many other articles/papers on flowgates on
    the same site.
  • Also see
  • W. Hogan, Getting the Prices Right in PJM April
    2, 1999, found at
  • http//ksghome.harvard.edu/.whogan.cbg.Ksg/pjm039
    9.pdf
  • S. Harvey, MISO Congestion Management System,
    CM Workshop, Dallas, March 14, 2002, available on
    MISO website.
Write a Comment
User Comments (0)
About PowerShow.com