Title: GWATCH TOOL FOR CITIZENS MONITORING OF PUBLIC WORKS PROJECTS
1G-WATCH TOOL FOR CITIZENS MONITORING OF PUBLIC
WORKS PROJECTS
- Prof. Juan Mayo Ragragio
- Ateneo School of Government
- 21 September 2004 Makati City
2Why monitor DPWH?
- Public works are vital public goods
- Big amount of contracts
- Corruption in agency
3What to monitor in DPWH?
- Delays
- Cost increases
- Causes of delays and cost increases
- Readily observable physical defects
- Deviation from normative process
4Framework for Citizens Monitoring
- Tool and method must be simple and can be applied
easily by ordinary citizens - Consultation with agency regarding the monitoring
activity must be part of the method
5Monitoring Tool
6Methods
- Site visit
- Data-gathering
- Documents review and analysis
- Interviews
7Documents to use
- Progress reports and summary reports (Central
Office data and field data) - Contracts
- Supplemental Agreement
- Variation Orders
- Notice to Proceed
- Notice of Award
- Program of Work
8G-Watch Phases
Phase 1 Tool development and testing
9Phase 1
- No MOA with agency
- Coverage
- 4 highway projects
- 1 flood control project
- Ave. delay 415 CDs/project
- Ave. cost increase P176.5M/project
- Problems attributed to
- delayed fund releases from DBM
- bad weather condition
- financial crisis
10Phase 2
- MOA with agency signed
- Coverage
- 6 road projects
- 1 flood control project
- Ave. delay 831 CDs per project
- Ave. cost increase P105.5M per project
- Additional consultancy fee due to delay P522M
- Problems on right-of-way and environment clearance
11Phase 3
- MOA with agency signed
- Coverage
- 15 Locally Funded Projects (LFPs)
- 11 Foreign-Assisted Projects (FAPs)
- Ave. delay 52 CDs/LFP 287 CDs/FAP
- Ave. cost increase P241,290/LFP P59M/FAP
- Delays attributed to bad weather condition, late
GOP payment, peace and order situation, RoW - Cost increases attributed to changes in work plan
and work suspension
12HIGHLIGHTS OF PHASE 3
13Monitoring Objectives
- To check the progress of on-going projects and
performance of completed projects - To identify problems that cause delay in project
implementation - To check on variances in targets (in terms of
time, cost or project specifications) - To identify other issues related to project
implementation
14COVERAGE Criteria
There are a total of 26 projects monitored by
G-WATCH
- Projects identified in consultation with DPWH
- Implementing Office
- (Central Office, Local Offices)
- Project Status
- (Completed, On-going)
- Project Type
- (Road Construction, Flood Control, Airport
Terminal, Road Maintenance) - Funding Source
- (ADB, WB, JBIC, locally-funded)
- Geographical Spread
- (Luzon, Visayas, Mindanao)
1511 FAPs vs. 14 Local Projects
16DELAYS OF MORE THAN 1 YEAR
ON-GOING PROJECTS
? in time
42.6
54.5
123.6
17SUMMARY (Time Variance)
- 18 out of 25 projects incurred delays (72 of
those monitored) - 4 projects incurred delays of more than 1 year
- All are Foreign-assisted
- 1 Completed, 3 On-going
- Change in Time 43 to 123
- Total Time Variance 3,941 CD or an average
delay of 158 CD (5 months)
18CAUSE OF DELAYS
19TOP 2 PROJECT COST INCREASESIN PERCENTAGE
P354,641,354.03 92
20SUMMARY (Cost Variance)
- 14 out of 25 projects increased project cost
(56 of those monitored) - 2 projects increased cost by more than 25
- All are Foreign-assisted
- 1 Completed, 1 On-going
- Total Cost Variance P659,560,596.57 or an
average increase of P26,382,423.86
21CAUSE OF COST INCREASES
22OTHER RELEVANT ISSUES
DPWH Responses (August 11)
- SUB-CONTRACTING
- Macalelon-Mulanay Road, Quezon, ADB
- BID IRREGULARITY
- Babak-Samal-Kaputian National Road
- MULTIPLE CONTRACTS
- Bislig Bridge, Surigao del Sur
- MISCOMPUTATIONS
- Some Local projects
- Allowed sub-contracting to verify
amount/percentage sub-contracted if within limit - To be verified by CO
- Splitting or Multi-release contract to be
verified by CO - Due to manual computations thus subject to
human error -
23A CASE OF SUB-CONTRACTINGMacalelon-Mulanay,
Quezon
- Reported case of sub-contracting
- Subcontracted by E. Ramos Construction to Wee Eng
Construction km 247700 to 265700 - 41 (18 km) of road projects net length, 43.54
km - Amount P170,800,000.00 or 18 of contract price
Subcontract agreement XXX shall be subject to
increase or decrease by the CONTRACTOR depending
on its assessment of actual work done
- D.O. 4 and 70 s.2004
- prior written consent of the approving authority
- not gt 50 of value of project
24A CASE OF BID IRREGULARITY Babak-Samal-Kaputian
National Road
- Actual Start before Notice to Proceed
- Important Dates
- Bid Date March 28, 2003
- Notice of Award April 9, 2003
- Project Start April 25, 2003
- Notice to Proceed June 9, 2003
- Notice of Award closely scheduled with Bid
Opening
25WHEN WILL WE SEE THE BRIDGE ?
99.99 accomplished
1998 P 31,116,039.51
All refer to exactly the same contract information
96.16 accomplished
1999 P 12,158,707.57
92.51 accomplished
2000 P 22,917,091.79
Actual Project Start July 13, 2000
60.32 accomplished
2002 (SA1) P 28,741,362.44
As of Feb 2004, researcher noted local district
officials observation that the project is not
even 25 complete in physical appearance. They
estimated that it may take another 5 years to
complete.
Original Project Cost Increased by P63,817,161.8
P94,933,201.31
26Bislig Bridge (Time Cost Variances)
Time Variance
? in time 159.2
Cost Variance
27CASES OF MISCOMPUTATIONS
Program of Work Babak-Samal-Kaputian
- ? A1 to A4 7,825,454.48
- 3 of ? (A1 to A4)
- 234,763.63
- Variance
- 350,000 - 234,763.63
115,236.37
28Major Questions
- Why do the same findings occur yearly?
- Why are they not addressed and corrected
immediately?
29Learnings
- Non-technical monitoring by citizens can be done
and can pressure both government and constructor
to improve work quality - Non-adversarial engagement with agency bears
results
Thank you!