Best Practices in Energy Efficiency - PowerPoint PPT Presentation

1 / 87
About This Presentation
Title:

Best Practices in Energy Efficiency

Description:

Best Practices in Energy Efficiency – PowerPoint PPT presentation

Number of Views:86
Avg rating:3.0/5.0
Slides: 88
Provided by: kristinhei
Category:

less

Transcript and Presenter's Notes

Title: Best Practices in Energy Efficiency


1
Best Practices in Energy Efficiency
Retro-Commissioning
2
Agenda
  • Energy, The Big Picture
  • How to Save Energy
  • OM Approaches to Energy Savings
  • What is Commissioning?
  • Retro-Commissioning

3
The American Building Contribution
  • If U.S. uses 25 of global energy
  • and U.S. Buildings require 40 of U.S. energy
  • Then 10 of global energy use is

U.S. Buildings
4
(No Transcript)
5
The Energy Savings Equation
kWhsaved kWhbaseline - kWhpost retrofit
  • Energy savings is not a one-time reading

6
Energy Calculation
Energy Power Runtime kWh kW hrs Annual
Energy (kWh/yr) Input Power (kW)
Runtime(hrs/yr) Notes kW can be taken from
tables, calculated or measured with
meters Runtime can be estimated or measured with
meters
7
Tools for Identifying Energy Opportunities
  • Benchmarking Tools
  • Commercial Building Surveys
  • Energy Audits
  • Monitoring and Trending
  • Commissioning

8
Is Your Building a Poor Performer?
http//poet.lbl.gov/cal-arch/
9
Where Does the Energy Go?
2003 U.S. Commercial Buildings
  • 2005 Building Energy Outlook-USDOE
  • Annual Energy Outlook 2003-USDOE
  • BOMA Datahttp//www.boma.org/
  • PGE Commercial Building Surveyshttp//www.pge.co
    m/biz/energy_tools_resources/building_survey/inde
    x.html

10
PGE Commercial Building Surveys
Grocery
Large office building
http//www.pge.com/biz/energy_tools_resources/buil
ding_survey/index.html
11
Why Measure?
  • Identify energy-saving opportunities
  • Quantify energy savings from upgrade to facility
  • Understand where energy is going
  • Understand building operations
  • Demonstrate improved building operations
  • Understand performance of new strategy or
    equipment
  • Diagnose equipment problems
  • Identify demand response strategies
  • Understand utility costs
  • Other reasons?

12
Measuring Surface Temperature
  • Temperature of difficult to reach locations
  • Temperature of extremely hot or dangerous
    surfaces
  • Determine if simultaneous heating and cooling is
    occurring

13
Examining Illuminance Levels
Retail level
40
20
Theater level
7
50
14
Space Temperature Setbacks
15
Monitoring Air Side Economizers
  • Measurements
  • SA db (shielded)
  • MA db
  • RA db
  • OA db (shielded)
  • Monitor for 1-2 weeks

16
Performance Graph Example 1
17
Performance Graph Example 2
18
Runtime MonitoringkWh kW x Runtime
  • Measures the hours of operation
  • Constant HVAC loads
  • Non-dimmable lighting
  • Pumps (constant speed)
  • Fans (constant speed)
  • Boilers
  • Single-stage compressors

19
Runtime Data
  • Records only ON and OFF conditions
  • Very effective use of memory
  • Not acceptable for variable power loads
  • Sensor types
  • Light level
  • Electro-magnetic field
  • Vibration
  • Can convert other data to runtime
  • Temperature
  • Light
  • Amperage

20
What are Electro-Magnetic Fields (EMF)?
  • Motors generate this when they run
  • Electric current charges windings creating EMF
  • EMF causes magnets (rotors) in motor to rotate
  • Motor loggers pick up this field
  • Sensors read mili-gauss

http//www.electricmotorsales.net/AC2020DC20Mo
tors.html
EMF
http//mapex.com/motor.html
21
Motor Run Time Data
22
Run-Time Data from Status Loggers
Fan continuous on
Compressor over-cycling
Over-cycling zoomed in
Cooling tower fan
23
Data from Timer Controls
Retail Example
24
Verify Lighting Controls
Garage Example
25
Continuous Power and Energy kWh kW x Runtime
  • Measures connected load and runtime
  • Required for varying or multi-staged loads
  • Dimmable lighting
  • Chillers
  • Multi-staged compressors
  • VFDs
  • Plug-loads

26
Baselining Electric Use
27
Kirsch Center, De Anza College
28
Kirsch Center Data
Total power
Site and interior lighting
Miscellaneous transformer
Chiller
Other mechanical
Boiler pump
29
Status Data for Natural Gas Systems
Single-line Diagram
30
Dis-aggregation Preliminary Findings
31
Domestic Hot Water Boiler
  • Used light loggers facing flame
  • Full combustion easily distinguished from pilot
    light
  • Shielded sensor from overhead light

32
Analyzing DHW Data
  • Cycling of boiler visible in data from master gas
    meter and data logger
  • Usage rate is steady
  • Each 5-minute cycle uses 9 cubic feet of gas on
    average

33
Heating Hot Water Boiler
  • The most difficult gas load to measure and
    analyze
  • Experimented with light and temperature loggers
  • Light loggers facing flame and shielded from heat
  • Temperature probe in flue

34
Analyzing HHW Data
  • Run time does correlate to light and temperature,
    but
  • Usage rate is NOT steady
  • Developed a regression to correlate light level
    to CF gas
  • Regression produced multiplier for converting
    light data to CF gas
  • Total is within 3 of actual

35
Gas Data Disaggregated
  • Heating hot water system accounts for 91 of gas
    use at PEC
  • Is 75 in typical CA office
  • Is worth investigating this system further

Typical California office
Pacific Energy Center
36
What Is Commissioning?
  • Commissioning is a systematic process of ensuring
    that all building systems are operating properly.

37
Commissioning is Quality Assurance
  • A coordination process to optimize building
    performance (comfort, reliability, safety,
    energy)
  • Articulating/verifying energy-related design
    intent
  • Construction observation warranty enforcement
  • Controlling first cost
  • Training operators
  • Enhancing safety and risk management
  • Creating more cohesion among team members

38
Types of Commissioning (Cx)
  • New Construction Commissioning
  • Integrated into design/construction process
  • Completed before occupancy
  • Required by LEED-NC
  • vs.
  • Existing Building Commissioning
  • Renovations, additions retrofits
  • Data available on building operation history
  • Required by LEED-EB

39
Beyond New Construction Commissioning
Retro-commissioning
New construction commissioning
On going commissioning
40
Why Commission?
  • Owners do not typically receive fully functional
    building systems
  • Owners face increasing numbers of performance
    problems
  • Buildings have more complex life safety,
    security, communication, and comfort control
    systems
  • Building systems are becoming increasingly
    specialized and integrated
  • Many problems are masked by energy-wasting
    process
  • Multiple trades and contracts are involved
    (fragmentation)
  • Conflicting loyalties and objectives
  • Increasing costs (change orders, call backs)
  • Emphasis on fast track
  • Design fees do not reflect reality
  • Requirements LEED, CHPS, Title 24

41
Building problems (a.k.a. deficiencies) are
pervasive
  • These include Design flaws Construction defects
    Malfunctioning equipment Deferred maintenance

42
Types of Deficiencies Discovered
New (N3300)
Existing (N3500)
43
Cost Outliers
Smaller bldgs tend to have higher Cx costs
Larger bldgs tend to achieve economies of scale
44
First-cost savings alone can pay for cost of Cx!
Evan Mills The Cost-Effectiveness of Commercial
Buildings Commissioning, 2004
45
Pre and Post Commissioning Data
46
Energy Center Commissioning
  • Commissioned existing facility in 2000-2001
  • Square footage 30,000
  • Cost of commissioning 52,000
  • Cost per square foot 1.73
  • Reduced energy use by 26
  • Reduced demand by 32
  • Average annual cost savings of 11,400
  • Improved occupant comfort
  • Demonstration project justified additional cost
  • Effort benefited ongoing coursework on
    commissioning
  • Design Intent identified varied perspectives of
    facility staff
  • Products include problem log and systems manual
  • Major obstacles
  • Time overruns
  • Limited expertise of controls contractor

47
Payback Times New Construction
Payback times not always attractive (if NEBs
excluded)
Median Payback Time 4.8 years
48
Payback Times Existing Buildings
Excluding NEIs
Attractive payback times across a range of Cx
costs
Median Payback Time 0.7 years
49
Other Benefits of Commissioning
  • Smoother turnover
  • Improved comfort
  • Reduced construction and warranty issues
  • More complete documentation
  • Tenant / occupant satisfaction
  • Avoided OM costs / increased reliability
  • Lower utility bills
  • Improved Net Operating Income (NOI)
  • Provides a benchmark

50
A Description of the Cx Process
51
Four Phases of Commissioning
  • Pre-design
  • Design
  • Installation / Construction
  • Post Acceptance / Warranty

52
Pre-Design Phase Objectives
  • Develop the Commissioning Scope of Work
  • Select a commissioning provider
  • Incorporate commissioning requirements into A/E
    Request for Proposals
  • Ideally, prepare the design documentation
    requirements for inclusion into the A/E RFP

53
Design Phase Cx Objectives
  • Provide commissioning-focused design review
  • Ensure that design and operational intent are
    documented
  • Ensure that commissioning is reflected in the bid
    documents (specifications)
  • Tasks
  • Develop Draft Cx plan
  • Gather or Develop written design documentation
    (design intent)
  • Perform a commissioning focused design review
    (50 and 90)
  • Develop Cx specifications for bid documents
  • Facilitate Performance Testing and OM

54
Construction Phase Objectives
  • Ensure systems and equipment work separately and
    together according to design
  • Document findings and resolutions
  • Tasks
  • Lead the Cx Kick-Off Meeting
  • Finalize the Commissioning Plan
  • Perform submittal review
  • Develop checklists and test procedures
  • Perform construction observation
  • Perform verifications / witness start-ups
  • Begin to perform functional performance tests

55
Warranty Phase Objectives
  • Ensure systems and equipment work separately and
    together according to design
  • Establish strategies for persistence
  • Tasks
  • Perform seasonal testing and deferred testing
  • Continue trend logging
  • Ensure OM manuals are complete
  • Complete Systems or Recommissioning Manual (LEED)
  • Oversee building operator training
  • Complete the Final Cx Report

56
Cx Activities
  • Involve
  • Reviewing identifying - resolving
  • Observing identifying resolving
  • Verifying identifying - resolving
  • Testing identifying - resolving
  • Overarching to all of these is
  • Writing
  • Communicating
  • Documenting

57
The Commissioning Team
  • Building owner or property manager
  • Commissioning provider
  • Design professionals
  • General Contractor
  • Installing contractors
  • Facility Manager/Bldg. Operator
  • Testing specialist

58
Documentation Produced
59
Documentation Produced
  • Cx Plan
  • Design intent document
  • MV plan
  • Problem log
  • Functional tests
  • Systems manual
  • Training documents
  • Proposal with cost and savings data

60
Problem Log - Numerous Items Identified Put
Into Their Lane Lines
61
Persistence
62
Existing Building Cx in California (SMUD)
Avg of 8 buildings
Avg of 7 buildings
Avg of 4 buildings
63
Emergence Persistence of Energy Savings
64
PEC Electric Power Data
65
New Construction Persistence Research Results
Red did not persist Blue persisted
66
Examples from Projects
67
Fixed Economizer Actuator Motor
68
Looking at Scheduling
69
Looking at Multiple Trends
Why doesnt the AHU ever shut off ?
Looks like there are not any equipment lockouts
Why is the TES system melting ice at night?
70
Hot Water System Evaluation Trending
  • It takes all of Monday to heat up the HW Loop

71
First Observations Obvious Problems - Sensors
OSA Humidity
72
Resources
73
Resources
  • PECIhttp//www.peci.org
  • CA Commissioning Collaborative online
    libraryhttp//resources.cacx.org/library/
  • LBNL cost-benefit study(and spreadsheet
    download) http//eetd.lbl.gov/emills/PUBS/Cx-Costs
    -Benefits.html
  • Commissioning Functional Test Guidehttp//buildin
    gs.lbl.gov/hpcbs/FTG
  • Design Intent Toolhttp//ateam.lbl.gov/DesignInte
    nt/home.html
  • Energy Design Resourceshttp//energydesignresourc
    es.com
  • Pacific Energy Center Cx workshops!

74
Resources
  • www.cacx.org

75
Resources
  • coming soon
  • www.cacx.org

76
The Functional Testing Guide
  • a tool for design review as well as testing

77
Persistence Study
  • Load up your CD!
  • Download from California Cx Collaboratives
    Online Library
  • www.cacx.org/library

78
Integrated Design Resources
http//www.ctg-net.com/EDR/IntegratedDesign/
www.energydesignresources.com
79
PGE Commissioning Program
  • 40 buildings for investigation over next year
  • Preliminary evaluation of potential facilities
    will happen first
  • 3 consultants contracted to do investigation
    (Free service)
  • Findings with 1 year or less payback customer
    agrees to fund
  • Additional money to buy down other upgrades
    (0.156/kWh or 1.00/therm)
  • To be included talk to PGE account manager

80
PECI Third Party RCx Program
  • The PECI Retrocommissioning Program (currently
    showcased in the SDGE territory) is a unique
    energy efficiency effort aimed to achieve
    cost-effective peak energy and demand savings and
    establish a framework for a long-term,
    comprehensive retrocommissioning program. The
    program is designed to expand retrocommissioning
    capabilities in California by directly addressing
    market barriers, as well as ensure persistence of
    benefits from retrocommissioning. In the program,
    these objectives are met through the development
    of retrocommissioning protocols, building
    operator and commissioning provider trainings,
    and buildings operation tracking systems.
    Furthermore, to effectively market
    retrocommissioning services, the program
    leverages existing relationships among building
    owners, the utilities, and local governments.

81
The Tool Lending Library
82
TLL homepage www.pge.com/pec/tll
83
On-line Tool Request Form
  • Method for all loans
  • Information requested
  • About borrower
  • About project
  • Sends automatic email to TLL staff
  • Typical response is within 24 hours
  • Tools can be shipped across California

84
Sign-out Sheet
  • To borrow tools
  • Business card
  • Signature
  • Agree
  • To return tools
  • That borrower is liable for damages to equipment
    and/or customer facility
  • Use licensed electrician for installing meters on
    equipment over 12v
  • Software cannot be copied for use after loan

85
On-line Catalog
86
Application Notes
87
Thanks!
Write a Comment
User Comments (0)
About PowerShow.com