Tailings Facilities An Introduction from an Insurance Perspective - PowerPoint PPT Presentation

1 / 46
About This Presentation
Title:

Tailings Facilities An Introduction from an Insurance Perspective

Description:

Need a trained engineer/technician responsible for tailings operations ... FLOOD FREEBOARD. MILL. EVAPORATION. RUNOFF. TAILINGS SLURRY TRANSPORT. WATER RECLAIM ... – PowerPoint PPT presentation

Number of Views:243
Avg rating:3.0/5.0
Slides: 47
Provided by: jonathan185
Category:

less

Transcript and Presenter's Notes

Title: Tailings Facilities An Introduction from an Insurance Perspective


1
Tailings Facilities - An Introduction from an
InsurancePerspective
  • Some Operational and Closure Considerations

2
Tailings Dam Operation Issues
  • Deposit tailings
  • Reclaim water
  • Plan, engineer and construct rising retention
    dams
  • Document all aspects of operation
  • Monitor surface and groundwater quality
  • Prepare as-built drawings
  • Monitor performance of tailings facility
  • React to emergencies and incidents
  • Prepare and update closure plans
  • Prepare tailings dam operation manual

3
Tailings Operational Responsibilities
  • General Planning and Budgeting
  • Siting Overall Design
  • Detailed Design - Tailings Retention Dam
  • Construction Tender
  • Deposit Tailings
  • Operate Reclaim
  • Monitoring Performance
  • Mine Personnel
  • Consultant
  • Consultant
  • Mine and Consultant
  • Mine Personnel
  • Mine Personnel
  • Mine Personnel and Consultant

4
Mine Tailings Personnel Requirements
  • Need a trained engineer/technician responsible
    for tailings operations at every mine site
  • Need commitment from corporate office and mine
    manager to operate tailings impoundment to
    recognized standards
  • Need continuity in tailings experience both at
    mine site and with consultants
  • Need competent consultants to advise mine and
    corporate office

5
Operational Issues
  • Largely trial-and-error methods used for design
    and construction of tailings dams prior to the
    1950s
  • Great strides over past 4 decades through
    introduction of soil mechanics in 1960s, lessons
    learnt from experience and continual
    technological advancements
  • It is clear that we now have the technology and
    know-how for designing SAFE tailings facilities
  • HOWEVER..

6
Operational Issues - Contd
  • Deficiencies in tailings management practices not
    uncommon
  • Deficiencies can severely negate strives for
    technical design excellence
  • In most cases, operating personnel lack
    understanding of design background OR
  • Lack appreciation of the significance that
    operational deviations from design assumptions
    could impose of safety

7
Operating Issues - Contd
  • DME of Western Australia (1998) observed
  • It is now clear that while the required degree
    of professionalism is evident in the design and
    construction of tailings structures, many of them
    are not operated in line with all design
    parameters, resulting in particular problems at
    several mine sites. The majority of tailings
    incidents reported to the Department could have
    been avoided if the tailings storage facility had
    been operated within design parameters or had
    been diligently managed.

8
Operating Risks - Contd
  • Stated commitment and sincere intent needs to be
    backed up by diligent application
  • Need to recognize close integration between
    design, construction and operations. all phases
    are inter-related
  • Unlike water dams, tailings dams are constructed
    and operated simultaneously

9
Operating Risks - Contd
Impacts
Design
Criteria
Criteria and Rules
Construction
Operations
Effects
Effects
Actual
10
Operating Risks - Contd
  • Recognition and understanding of the interplay
    between design, construction and operations are
    important for mine personnel who manages/operates
    facility
  • Staff begins to appreciate potential magnitude of
    effects that actions, or lack of actions, can
    have on performance

11
Inspection and Maintenance
  • Regular Inspection Very Important Visual
    inspection limited to surficial conditions
  • Need conscious effort to question cause and/or
    meaning of any observed deviations from expected
    norms
  • Always be aware of design and operating criteria
    during inspection
  • Next Figure shows typical visually identifiable
    issues that should be kept in mind
  • Table 1 (overhead) provides minimum checklist of
    items

12
Inspection and Maintenance Contd
13
Inspection and Maintenance Contd
  • Inspections should be done regularly by mine
    personnel, and also especially
  • During spring freshet
  • Mid-summer
  • Prior to first snow fall
  • Mid-winter (as much as possible)
  • Immediately after relatively large natural events
    (e.g. flood)

14
Inspection and Maintenance Contd
  • Outline routine maintenance measures that can be
    done for example
  • Backfill local erosion gullies
  • Infill local differential settlement cracks to
    prevent infiltration
  • Remove ice formation and/or other debris from
    water conveyance structures (spillways, ditches,
    etc.)
  • Grading dam crest surface towards pond
  • Upgrade erosion protection as required

15
Inspection and Maintenance Contd
  • Document inspection results including any
    maintenance completed, with photographs
  • Manual should include organizational chart
    showing a line of communications for reporting of
    incidents or if there is a concern from the
    inspections

16
Performance Monitoring for Dam Safety
  • Program designed so that development of failure
    modes are identified with lead time for action
  • Requires thorough understanding of failure modes,
    and most suitable method of observations/instrumen
    ts to identify them
  • Illustration of intricate link between failure
    mode type and monitoring devices on next slide
    (Anderson et al 1999)

17
(No Transcript)
18
Some Comments on Performance Monitoring...Contd
  • It is prudent that every monitoring device have a
    clearly defined function and/or benefit relative
    to safety issues
  • Commonly, focus on where additional devices are
    needed.However, where function of existing
    device is not clear, then its maintenance should
    be questioned
  • In general, most programs designed for
    construction, then often maintained for long-term
    monitoring, without questioning their
    appropriateness for dam safety needsis it really
    appropriate?

19
Some Comments on Performance Monitoring...Contd
  • Some failure modes cannot be monitored to provide
    warning as easily as other failure modes (e.g.
    cannot forewarn a seismic event)
  • Monitoring is best suited for ductile behavior
    where shear failure normally takes time to
    develop
  • Failure by brittle behavior provides little
    warning (be careful if changes to operations
    result in increased loading)
  • Only defense where monitoring not suitable, is
    good design against reasonably worse conditions

20
Some Common Problems
  • Instruments not read or available readings not
    validated
  • Abnormal readings often viewed as error but
    apparently normal readings could also be
    error
  • Misinterpretation or ignored - cause and effect
    not appreciated, deviations from historical
    trends not appreciated
  • Trigger levels for action not established or, if
    established, no clear action plan
  • Without diligent execution, monitoring program
    simply provides a false sense of security

21
Illustrative Case Histories
  • Uncertainties due to dynamics of mining
    development
  • Hydrological conditions differ from assumed
    often in remote areas with no or little data
  • Change in mill water balance (more or less water
    to pond)
  • Changes in pit geology and/or mill grind
  • Change in ore body - greater storage or faster
    dam raises
  • Unexpected shutdown - continued rising pond level
  • Unexpected high clay in tailings - beach slopes,
    settled densities, sedimentation rates, storage
    capacity, water balance

22
Case History 1
  • Dam on permafrost
  • Key requirement to develop long tailings beach
    against dam
  • Actual operations created large free water pond
    against dam, leading to eventual thawing and
    degradation of permafrost.
  • Design background unknown or lack of appreciation
    of design deviation

23
Case History 2
  • Cycloned sand tailings dam at Gibraltar Mine,
    British Columbia
  • Extensive under-drain system, cyclone underflow
    discharged directly onto downstream slope
  • Design done in late 1960s, assumed average 4H1V
    slopes
  • Construction began 1972, performance excellent
  • See Figure on Next Slide

24
Case History 2 Figure
Gibraltar Tailings Dam
25
Case History 2 Contd
  • 1991, downstream slope much steeper at 2H1V to
    3H1V, compared to original designexcellent sand
    quality (clean) and increasing dam height reduces
    runout. Prompted a re-evaluation of long-term
    seismic stability of tailings dam, completed
    1992/93.
  • KEY POINT
  • Review of as-built surveys from mid-1980s onward
    already showed propensity for slope to
    progressively steepen, but significance not
    appreciated.
  • Original design done decades ago becomes distant
    memory need effort to maintain continual
    awareness

26
Case History 3
  • Mineral Kings tailings facility, southeastern
    British Columbia
  • Overtopping occurred sometime in March 1986 when
    ice was allowed to form and block spillway
  • Even though spillway design was likely adequate,
    lack of attention to operational details was main
    culprit

27
Case History 4
  • Tailings dam in central interior of Queensland,
    Australia
  • Typical practice in Australia is
    upstream-method-of-construction dam raises
    constructed on spigotted beach
  • Key requirement is to ensure thin lifts to
    promote drying of tailings, by rotating
    spigotting around dam perimeter
  • Drying is required for strength gain to support
    next raise
  • INCIDENT
  • Recent change in ore type and mill grind
    tailings much finer and cohesive compared to
    previous
  • Precluded adequate drying of tailings
    difficulties in meeting design dam raising
    schedule

28
Case History 5
  • Tailings dam in Indonesia designed on Australian
    practices
  • Australia arid (negative water balance) and low
    seismic Indonesia high rainfall (positive water
    balance) with areas of high seismic activity
  • Assumption of drying not appropriate
  • Water balance management difficulties resulted in
    most of tailings being deposited subaqueously.
    Lower densities was key factor in requiring
    another unplanned dam raise
  • Upstream construction led to concerns of long
    term seismic stability due to liquefaction of
    tailings issue currently being addressed

29
Case History 6
  • Mine in British Columbia
  • Piping developed in sand beach of large tailings
    dam discharging some 10,000,000 gallons of water
  • Large downstream damage, but fortunately no loss
    of life
  • Dam well-designed, rockfill section with graded
    filter
  • FINDINGS
  • Filter zones not built as specified rather,
    constructed by end-dumping from heights of 6 to
    10 m, causing much segregation
  • Also, free water was allowed to pond too close to
    the dam

30
Case History 6 Contd
  • Poor construction negated effects of design
    features that were specifically incorporated to
    prevent this failure mode
  • Remedial measures included filling the pipe with
    gravel and fine rockfill, and spigotting tailings
    from a new dyke constructed over soft tailings
    and located well upstream of main dam
  • See Figure on Next Slide

31
Case History 6 Figure
32
Case History 7
  • Acid rock drainage precipitates plug drains along
    toe of tailings dam- reduce stability

33
Case History 7 Contd
  • Solution place drains below groundwater level
    with a pipe to surface for collection/treatment

34
TAILINGS SLURRY TRANSPORT
RAINFALL
RUNOFF
EVAPORATION
WATER RECLAIM
MILL
MILL
SEEPAGE RECOVERY
FREE WATER POND
FLOOD FREEBOARD
RECLAIM PUMP
DAM
TAILINGS
GROUNDWATER SEEPAGE
SCHEMATIC OF TAILINGS DISPOSAL SYSTEM
35
What is the purpose of a Closure Plan?
  • Public protection for
  • safety, e.g. dams and water
  • health, e.g. drinking water quality, vegetation
  • environment, e.g. fish, dust
  • effective use or rehabilitation of land
  • Shareholder protection for
  • environmental liability

36
The Rules are Changing!
  • Regulatory requirements are changing.
  • Corporate Accounting is changing to recognize
    Closure Liability.
  • International banking rules are changing.
  • Social expectations are changing.

37
Regulatory Requirements - Closure Plans
  • Most plan requirements are similar.
  • Differences are more in level of detail, level
    of scrutiny and level of enforcement.
  • Examples Peru (PAMA), British Columbia
    (general ), Australia (general), Ontario
    (specific), U.S. (specific varies by state)

38
Closure to What Standard?
  • .. On closure, returning mine sites and
    affected areas to viable and, wherever
    practicable, self-sustaining ecosystems that are
    compatible with a healthy environment and with
    human activities
  • The risk cost (or factor of safety) for
    unknowns has to be reasonable.

39
Cover Up Plan versus Closure Plan
  • Range of requirements from Cover Up to Closure
  • decommission buildings
  • reclamation
  • physical stability, e.g. dams for seismic and
    erosion
  • water management stability, e.g. spillways,
    diversions, etc.
  • chemical stability surface , eg. ARD from rock
    dumps and tailings
  • chemical stability groundwater, e.g. contaminant
    plumes
  • reclamation to productive use, e.g. grazing,
    agriculture, wetland, etc.
  • reclamation to acceptable use
  • Long term Care and Maintenance or Transfer of
    Liability

40
Examples of Financial Assurance
  • B.C. Equity silver 30 mil. bond which was
    negotiated on closure for ARD. Bonds required
    on closure to fund long term care and
    maintenance. During operations bonds required
    for cover up plans and financial assurance of
    company for actual closure requirements.
  • Ontario Currently being negotiated with the
    mining industry - Government wants Bonds for
    Closure Plans - Mining Industry wants Financial
    Assurance based on Company. Expect to have a
    combination of the two. Smaller operations have
    put up bonds.
  • Nevada, Montana Surety company for Closure
    Implementation

41
Preparing a Closure Plan
  • Steps in a closure plan
  • Acceptable land use
  • Exit ticket

42
Closure Plan Table of ContentsOntario
Legislation
  • Legal status, environmental policies and
    regulatory policies
  • land ownership, ISO requirements, etc.
  • Site characterization baseline and existing
    conditions
  • geology, mineralogy, geochemistry
  • hydrology, surface water and groundwater
  • aquatic and terrestrial biology
  • Operations infrastructure
  • inventories and as-builts of mill, dams, roads,
    contaminated soils, etc.
  • document impacts on groundwater, surface water,
    dust, soils, aquatic/terrestrial
  • document environmental management systems, eg..
    Handling hazardous waste, fuel, etc.

43
Mine Closure Plan Table of Contents contd
  • Develop closure alternatives for both temporary
    and permanent closure
  • meet criteria of minimize environment impact
    maximize post closure land use
  • comparative cost assessments and risk/impact
    assessments of alternatives
  • identify technical issues to be resolved to
    confirm feasibility of closure plan
  • identify management issues that could assist
    closure
  • identify monitoring requirements
  • Selection of preferred alternative(s)
  • alternative to meet Owner specific ,
    liability-risk-cost criteria
  • cost estimate of preferred alternative(s)
  • assessment of liability and legal issues of
    alternative(s)
  • develop monitoring program

44
Closure Plan Table of Contents
  • Identify progressive decommissioning options
  • reclaim inactive areas, modify hazardous waste
    and hydrocarbon handling
  • modify operations to reduce closure impacts, eg.
    Dust, erosion, seepage, etc.
  • Post Closure Land Use
  • consider transfer or continued use of
    infrastructure, eg. Power, roads, water supply
  • consider future land use that could assist
    socio-economic impact of closure, e.g. resort
    use, agricultural, industrial, etc.
  • Closure Plan Review and Update
  • annual reviews to reflect changing conditions and
    additional information
  • continually work towards reducing risk and cost
    of closure

45
Acceptable Land Use?
  • No significant human health issues
  • safety of structures to standards of other civil
    engineering structures
  • healthy sustainable environment

46
EXIT STRATEGIES
  • Transfer to government
  • Transfer to private developer
  • Care Maintenance - operated by the mine
  • Care Maintenance - Contractor (e.g MWM Inc.)
  • Liability transfer to third party
Write a Comment
User Comments (0)
About PowerShow.com