Title: Tailings Facilities An Introduction from an Insurance Perspective
1Tailings Facilities - An Introduction from an
InsurancePerspective
- Some Operational and Closure Considerations
2Tailings Dam Operation Issues
- Deposit tailings
- Reclaim water
- Plan, engineer and construct rising retention
dams - Document all aspects of operation
- Monitor surface and groundwater quality
- Prepare as-built drawings
- Monitor performance of tailings facility
- React to emergencies and incidents
- Prepare and update closure plans
- Prepare tailings dam operation manual
3Tailings Operational Responsibilities
- General Planning and Budgeting
- Siting Overall Design
- Detailed Design - Tailings Retention Dam
- Construction Tender
- Deposit Tailings
- Operate Reclaim
- Monitoring Performance
- Mine Personnel
- Consultant
- Consultant
- Mine and Consultant
- Mine Personnel
- Mine Personnel
- Mine Personnel and Consultant
4Mine Tailings Personnel Requirements
- Need a trained engineer/technician responsible
for tailings operations at every mine site - Need commitment from corporate office and mine
manager to operate tailings impoundment to
recognized standards - Need continuity in tailings experience both at
mine site and with consultants - Need competent consultants to advise mine and
corporate office
5Operational Issues
- Largely trial-and-error methods used for design
and construction of tailings dams prior to the
1950s - Great strides over past 4 decades through
introduction of soil mechanics in 1960s, lessons
learnt from experience and continual
technological advancements - It is clear that we now have the technology and
know-how for designing SAFE tailings facilities - HOWEVER..
6Operational Issues - Contd
- Deficiencies in tailings management practices not
uncommon - Deficiencies can severely negate strives for
technical design excellence - In most cases, operating personnel lack
understanding of design background OR - Lack appreciation of the significance that
operational deviations from design assumptions
could impose of safety
7Operating Issues - Contd
- DME of Western Australia (1998) observed
- It is now clear that while the required degree
of professionalism is evident in the design and
construction of tailings structures, many of them
are not operated in line with all design
parameters, resulting in particular problems at
several mine sites. The majority of tailings
incidents reported to the Department could have
been avoided if the tailings storage facility had
been operated within design parameters or had
been diligently managed.
8Operating Risks - Contd
- Stated commitment and sincere intent needs to be
backed up by diligent application - Need to recognize close integration between
design, construction and operations. all phases
are inter-related - Unlike water dams, tailings dams are constructed
and operated simultaneously
9Operating Risks - Contd
Impacts
Design
Criteria
Criteria and Rules
Construction
Operations
Effects
Effects
Actual
10Operating Risks - Contd
- Recognition and understanding of the interplay
between design, construction and operations are
important for mine personnel who manages/operates
facility - Staff begins to appreciate potential magnitude of
effects that actions, or lack of actions, can
have on performance
11Inspection and Maintenance
- Regular Inspection Very Important Visual
inspection limited to surficial conditions - Need conscious effort to question cause and/or
meaning of any observed deviations from expected
norms - Always be aware of design and operating criteria
during inspection - Next Figure shows typical visually identifiable
issues that should be kept in mind - Table 1 (overhead) provides minimum checklist of
items
12Inspection and Maintenance Contd
13Inspection and Maintenance Contd
- Inspections should be done regularly by mine
personnel, and also especially - During spring freshet
- Mid-summer
- Prior to first snow fall
- Mid-winter (as much as possible)
- Immediately after relatively large natural events
(e.g. flood)
14Inspection and Maintenance Contd
- Outline routine maintenance measures that can be
done for example - Backfill local erosion gullies
- Infill local differential settlement cracks to
prevent infiltration - Remove ice formation and/or other debris from
water conveyance structures (spillways, ditches,
etc.) - Grading dam crest surface towards pond
- Upgrade erosion protection as required
15Inspection and Maintenance Contd
- Document inspection results including any
maintenance completed, with photographs - Manual should include organizational chart
showing a line of communications for reporting of
incidents or if there is a concern from the
inspections
16Performance Monitoring for Dam Safety
- Program designed so that development of failure
modes are identified with lead time for action - Requires thorough understanding of failure modes,
and most suitable method of observations/instrumen
ts to identify them - Illustration of intricate link between failure
mode type and monitoring devices on next slide
(Anderson et al 1999)
17(No Transcript)
18Some Comments on Performance Monitoring...Contd
- It is prudent that every monitoring device have a
clearly defined function and/or benefit relative
to safety issues - Commonly, focus on where additional devices are
needed.However, where function of existing
device is not clear, then its maintenance should
be questioned - In general, most programs designed for
construction, then often maintained for long-term
monitoring, without questioning their
appropriateness for dam safety needsis it really
appropriate?
19Some Comments on Performance Monitoring...Contd
- Some failure modes cannot be monitored to provide
warning as easily as other failure modes (e.g.
cannot forewarn a seismic event) - Monitoring is best suited for ductile behavior
where shear failure normally takes time to
develop - Failure by brittle behavior provides little
warning (be careful if changes to operations
result in increased loading) - Only defense where monitoring not suitable, is
good design against reasonably worse conditions
20Some Common Problems
- Instruments not read or available readings not
validated - Abnormal readings often viewed as error but
apparently normal readings could also be
error - Misinterpretation or ignored - cause and effect
not appreciated, deviations from historical
trends not appreciated - Trigger levels for action not established or, if
established, no clear action plan - Without diligent execution, monitoring program
simply provides a false sense of security
21Illustrative Case Histories
- Uncertainties due to dynamics of mining
development - Hydrological conditions differ from assumed
often in remote areas with no or little data - Change in mill water balance (more or less water
to pond) - Changes in pit geology and/or mill grind
- Change in ore body - greater storage or faster
dam raises - Unexpected shutdown - continued rising pond level
- Unexpected high clay in tailings - beach slopes,
settled densities, sedimentation rates, storage
capacity, water balance
22Case History 1
- Dam on permafrost
- Key requirement to develop long tailings beach
against dam - Actual operations created large free water pond
against dam, leading to eventual thawing and
degradation of permafrost. - Design background unknown or lack of appreciation
of design deviation
23Case History 2
- Cycloned sand tailings dam at Gibraltar Mine,
British Columbia - Extensive under-drain system, cyclone underflow
discharged directly onto downstream slope - Design done in late 1960s, assumed average 4H1V
slopes - Construction began 1972, performance excellent
- See Figure on Next Slide
24Case History 2 Figure
Gibraltar Tailings Dam
25Case History 2 Contd
- 1991, downstream slope much steeper at 2H1V to
3H1V, compared to original designexcellent sand
quality (clean) and increasing dam height reduces
runout. Prompted a re-evaluation of long-term
seismic stability of tailings dam, completed
1992/93. - KEY POINT
- Review of as-built surveys from mid-1980s onward
already showed propensity for slope to
progressively steepen, but significance not
appreciated. - Original design done decades ago becomes distant
memory need effort to maintain continual
awareness
26Case History 3
- Mineral Kings tailings facility, southeastern
British Columbia - Overtopping occurred sometime in March 1986 when
ice was allowed to form and block spillway - Even though spillway design was likely adequate,
lack of attention to operational details was main
culprit
27Case History 4
- Tailings dam in central interior of Queensland,
Australia - Typical practice in Australia is
upstream-method-of-construction dam raises
constructed on spigotted beach - Key requirement is to ensure thin lifts to
promote drying of tailings, by rotating
spigotting around dam perimeter - Drying is required for strength gain to support
next raise - INCIDENT
- Recent change in ore type and mill grind
tailings much finer and cohesive compared to
previous - Precluded adequate drying of tailings
difficulties in meeting design dam raising
schedule
28Case History 5
- Tailings dam in Indonesia designed on Australian
practices - Australia arid (negative water balance) and low
seismic Indonesia high rainfall (positive water
balance) with areas of high seismic activity - Assumption of drying not appropriate
- Water balance management difficulties resulted in
most of tailings being deposited subaqueously.
Lower densities was key factor in requiring
another unplanned dam raise - Upstream construction led to concerns of long
term seismic stability due to liquefaction of
tailings issue currently being addressed
29Case History 6
- Mine in British Columbia
- Piping developed in sand beach of large tailings
dam discharging some 10,000,000 gallons of water - Large downstream damage, but fortunately no loss
of life - Dam well-designed, rockfill section with graded
filter - FINDINGS
- Filter zones not built as specified rather,
constructed by end-dumping from heights of 6 to
10 m, causing much segregation - Also, free water was allowed to pond too close to
the dam
30Case History 6 Contd
- Poor construction negated effects of design
features that were specifically incorporated to
prevent this failure mode - Remedial measures included filling the pipe with
gravel and fine rockfill, and spigotting tailings
from a new dyke constructed over soft tailings
and located well upstream of main dam - See Figure on Next Slide
31Case History 6 Figure
32Case History 7
- Acid rock drainage precipitates plug drains along
toe of tailings dam- reduce stability
33Case History 7 Contd
- Solution place drains below groundwater level
with a pipe to surface for collection/treatment
34TAILINGS SLURRY TRANSPORT
RAINFALL
RUNOFF
EVAPORATION
WATER RECLAIM
MILL
MILL
SEEPAGE RECOVERY
FREE WATER POND
FLOOD FREEBOARD
RECLAIM PUMP
DAM
TAILINGS
GROUNDWATER SEEPAGE
SCHEMATIC OF TAILINGS DISPOSAL SYSTEM
35What is the purpose of a Closure Plan?
- Public protection for
- safety, e.g. dams and water
- health, e.g. drinking water quality, vegetation
- environment, e.g. fish, dust
- effective use or rehabilitation of land
- Shareholder protection for
- environmental liability
36The Rules are Changing!
- Regulatory requirements are changing.
- Corporate Accounting is changing to recognize
Closure Liability. - International banking rules are changing.
- Social expectations are changing.
37Regulatory Requirements - Closure Plans
- Most plan requirements are similar.
- Differences are more in level of detail, level
of scrutiny and level of enforcement. - Examples Peru (PAMA), British Columbia
(general ), Australia (general), Ontario
(specific), U.S. (specific varies by state)
38Closure to What Standard?
- .. On closure, returning mine sites and
affected areas to viable and, wherever
practicable, self-sustaining ecosystems that are
compatible with a healthy environment and with
human activities - The risk cost (or factor of safety) for
unknowns has to be reasonable.
39Cover Up Plan versus Closure Plan
- Range of requirements from Cover Up to Closure
- decommission buildings
- reclamation
- physical stability, e.g. dams for seismic and
erosion - water management stability, e.g. spillways,
diversions, etc. - chemical stability surface , eg. ARD from rock
dumps and tailings - chemical stability groundwater, e.g. contaminant
plumes - reclamation to productive use, e.g. grazing,
agriculture, wetland, etc. - reclamation to acceptable use
- Long term Care and Maintenance or Transfer of
Liability
40Examples of Financial Assurance
- B.C. Equity silver 30 mil. bond which was
negotiated on closure for ARD. Bonds required
on closure to fund long term care and
maintenance. During operations bonds required
for cover up plans and financial assurance of
company for actual closure requirements. - Ontario Currently being negotiated with the
mining industry - Government wants Bonds for
Closure Plans - Mining Industry wants Financial
Assurance based on Company. Expect to have a
combination of the two. Smaller operations have
put up bonds. - Nevada, Montana Surety company for Closure
Implementation
41Preparing a Closure Plan
- Steps in a closure plan
- Acceptable land use
- Exit ticket
42Closure Plan Table of ContentsOntario
Legislation
- Legal status, environmental policies and
regulatory policies - land ownership, ISO requirements, etc.
- Site characterization baseline and existing
conditions - geology, mineralogy, geochemistry
- hydrology, surface water and groundwater
- aquatic and terrestrial biology
- Operations infrastructure
- inventories and as-builts of mill, dams, roads,
contaminated soils, etc. - document impacts on groundwater, surface water,
dust, soils, aquatic/terrestrial - document environmental management systems, eg..
Handling hazardous waste, fuel, etc.
43Mine Closure Plan Table of Contents contd
- Develop closure alternatives for both temporary
and permanent closure - meet criteria of minimize environment impact
maximize post closure land use - comparative cost assessments and risk/impact
assessments of alternatives - identify technical issues to be resolved to
confirm feasibility of closure plan - identify management issues that could assist
closure - identify monitoring requirements
- Selection of preferred alternative(s)
- alternative to meet Owner specific ,
liability-risk-cost criteria - cost estimate of preferred alternative(s)
- assessment of liability and legal issues of
alternative(s) - develop monitoring program
44Closure Plan Table of Contents
- Identify progressive decommissioning options
- reclaim inactive areas, modify hazardous waste
and hydrocarbon handling - modify operations to reduce closure impacts, eg.
Dust, erosion, seepage, etc. - Post Closure Land Use
- consider transfer or continued use of
infrastructure, eg. Power, roads, water supply - consider future land use that could assist
socio-economic impact of closure, e.g. resort
use, agricultural, industrial, etc. - Closure Plan Review and Update
- annual reviews to reflect changing conditions and
additional information - continually work towards reducing risk and cost
of closure
45Acceptable Land Use?
- No significant human health issues
- safety of structures to standards of other civil
engineering structures - healthy sustainable environment
46EXIT STRATEGIES
- Transfer to government
- Transfer to private developer
- Care Maintenance - operated by the mine
- Care Maintenance - Contractor (e.g MWM Inc.)
- Liability transfer to third party