Managing Risks in Projects MT 246 Module 13 - PowerPoint PPT Presentation

1 / 55
About This Presentation
Title:

Managing Risks in Projects MT 246 Module 13

Description:

estimates at time of contract signature become budget for remainder of ... Incentivize the Technical Team. Consultants for Critical Reviews and Assessments. T&E ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 56
Provided by: andyd6
Category:

less

Transcript and Presenter's Notes

Title: Managing Risks in Projects MT 246 Module 13


1
Managing Risks in ProjectsMT 246 - Module 13
2
Last Lecture Cost Estimating and Budgeting
  • Estimating Process
  • takes place at proposal time
  • time phasing and bottom line totals
  • direct labor
  • direct material
  • Overhead, G A, and Profit applied to totals
  • final iteration at negotiation of contract
  • Budgeting Process
  • estimates at time of contract signature become
    budget for remainder of program
  • updated and reforecast throughout life of
    contract

3
Risk Concepts
  • The Likelihood that some Problematical Event will
    Occur
  • The Impact of the Event if it does Occur
  • Risk f (likelihood, impact)
  • Project is considered Risky if at least One
    Factor is large

4
Risk Identification
  • Risk Tolerance is a Function of Experience
  • PM
  • Stakeholders
  • Risk of Failure
  • Schedule
  • Budget
  • Technical Goals
  • Risk of Opportunity
  • Rewards
  • Savings
  • Benefits

5
Risk Identification (Continued)
  • Ways to Identify Project Risk
  • Chronology
  • Type of Work
  • High Risks
  • Approach is New/Unusual
  • Technology is New/Unusual
  • Staff needs Training in New Tasks/Skills
  • Process using New Equipment, Systems or Procedures

6
Sources of Risk
  • Any Factor of uncertain Probability which can
    affect the Outcome is of a Project is a
  • Risk Source
  • Risk Hazard

7
Sources of Risk (Continued)
  • Internal Risks
  • Market Risk
  • Ill Defined Market or Customer needs and
    Requirements
  • Failure to Identify Changing Needs and
    Requirements
  • Failure to identify Newly Introduced Products by
    Competitors
  • Technical Risk
  • Maturity
  • Complexity
  • Quality
  • Concurrency, or Dependency

8
Sources of Risk (Continued)
  • External Risks,
  • Market Conditions
  • Competitors Actions
  • Government Regulations
  • Interest Rates
  • Decisions by Sr. Mgmt or Customer
  • Budgets
  • Staffing
  • Priorities

9
Sources of Risk (Continued)
  • External Risks (Continued)
  • Customer Needs and Behavior
  • Supplier Relations
  • Weather
  • Labor Troubles
  • Material or Labor
  • External Control by Customers or Subcontractors

10
Identification Techniques
  • Analogy
  • Records, History and Lesson Learned from Previous
    Projects
  • Checklist
  • Factors which can affect the Project
  • Becomes more Relevant with more accurate and
    Complete Historical Data
  • WBS Analysis
  • Each WP is Assessed for Internal and External
    Risk

11
Identification Techniques (Continued)
  • Process Flowcharts
  • Look at Functional Process Designs
  • Pinpoint Potential Trouble Spots
  • Precedence Relationships in Project Network
  • Brainstorming and Cause and Effect Diagrams
  • Outcome (Effect) can Identify Causes (Hazards)
  • Risk Hazard (cause) can Identify Outcomes
    (Effect)

12
Cause and Effect Diagram
13
Risk Assessment
  • Risk Likelihood
  • Probability a Hazard or Risk Factor will
    Materialize
  • Numerical Value between 1.0 (Certain) and 0
    (Impossible)
  • Qualitative Rating
  • High Greater than 50
  • Medium 20 to 50
  • Low 20 or Less
  • Composite Likelihood Factor (CLF)
  • Sum of Multiple, Independent Risk Sources

14
Sources of Failure and Likelihood
15
Influence Diagram
16
Risk Assessment(Continued)
  • Risk Impact
  • What Happens if a Risk Hazard Materialized
  • Specified in Terms of
  • Time
  • Cost
  • Performance Measures
  • Qualitative
  • High
  • Medium
  • Low

17
Risk Assessment(Continued)
  • Risk Impact (Continued)
  • Numerical Measure Between 0 and 1.0
  • 0 not Serious
  • 1.0 Catastrophic
  • Composite Impact Factor (CIF) is the Impact from
    Multiple Risk Source, Simple Weighted Average
  • CIF (W1)TI (W2)CI (W3)SI

18
Impact Values for Technical, Cost, and Time
19
Risk Assessment(Continued)
  • Risk Consequence
  • Function or Likelihood and Impact
  • Can be Expressed as Numerical rating between 0
    and 1.0
  • Risk Consequence Rating (RCR)
  • RCR CLF CIF - CLF(CIF)
  • Can be Expressed as an Expected Value or the
    Average Outcome for large Tries
  • Risk Consequence (Impact) x (Likelihood)

20
Risk Assessment(Continued)
  • PERT
  • Incorporates Risk through the three Estimates for
    Each Project Activity
  • a, Optimistic
  • m, Most Likely
  • b, Pessimistic
  • Use a larger value of b to account for Greater
    Risk
  • This Produces a larger Variance for Project
    Completion Time (Add buffer Time to Project)
  • PERT Provides a Way for Measuring the
    Consequences of Risk on Project Completion Times

21
Risk Assessment(Continued)
  • Risk Priority
  • PM must Define a Risk Tolerance Level
  • Consider Risks at that Level and Higher
  • Team Members Review all these Tasks and Make
    Recommendations
  • In Complex Systems Joint Failures Can Occur
  • Bhopal India 10,000 Deaths
  • Chernobyl 50,000 Cancer Deaths Forecast

22
Risk Response Planning How to Deal with the
Problem
  • Transfer the Risk
  • Avoid Risk
  • Reduce Risk
  • Contingency Planning
  • Accept Risk (Do Nothing)

23
Risk Likelihood, Risk Impact, and Expected Value
Consequences
24
Transfer the Risk
  • Transfer Partly or Fully from Customer to
    Contractor or Vice Versa
  • Use Contract Incentives
  • Fixed Price Contractor Assumes All the RISK for
    Cost Over-Run
  • FP Incentive Fee Contractor 60, Customer 40
  • Cost Plus Incentive Fee Contractor 40, Customer
    60
  • CPFF Customer Assumes almost All the Risk

25
Avoid Risk
  • Alter the Initial Project Concept
  • Eliminate Risky Activities
  • Minimize System Complexity
  • Reduce End-Item Quality Requirements
  • Change Contractors
  • Incorporate Redundancies
  • Change Safety Procedures
  • Better to Reduce Risk to Acceptable Level Than
    Eliminate Payoff Opportunity

26
Reduce RiskTechnical Performance
  • Best Technical Team
  • Perform Analysis of Key Technical Parameters
  • Models and Simulations
  • Use CASE Tools
  • Parallel Development on High-Risk Tasks
  • Incentivize the Technical Team
  • Consultants for Critical Reviews and Assessments
  • TE

27
Reduce RiskTechnical Performance (Continued)
  • Reduce System Complexity to a Minimum
  • Reorganize Tasks
  • End Item Design
  • Decouple Activities
  • Contains Failure to one Activity
  • Use Design Margins
  • A Management Reserve
  • Design Value is Greater than Design Requirement

28
Reduce RiskMeeting Schedules
  • Create Master Project Schedule
  • Schedule Risky Tasks Early to Allow Time to
    Recover
  • Focus on Critical and Near-Critical Activities
  • Path
  • Risk
  • Best People on Time-Critical Tasks

29
Reduce RiskMeeting Schedules (Continued)
  • Incentives for OT
  • Compensated Salary
  • Compensated Time
  • Do High Risk Activities in the Project Network in
    Parallel
  • Organize Project Early with Adequate Staff

30
Reduce RiskMeeting Project Cost
  • Identify and Monitor Cost Drivers
  • Perform Design Alternative Reviews and
    Assessments
  • Validate System Design and Performance
  • Modeling
  • Assessment
  • Maximum Use of Proven Technology and COTS

31
Reduce RiskMeeting Project Cost (Continued
  • Systems Engineering
  • Build Test Models to Verify Design
  • Early Breadboarding
  • Prototyping,
  • Test Evaluation
  • Focus on Meeting the Minimum Requirements and
    Nothing More

32
Contingency Planning
  • The Get-Well-Plan
  • Identify Risks
  • Anticipate what might Happen
  • Plan of Action to Respond
  • Form
  • Post-Hoc Remedial
  • In Parallel to the Original Plan
  • Preventive Action to Mitigate the Risk Impact

33
Accept Risk (Do Nothing)
  • Not All Risks are Severe or Fatal
  • Cost Benefit Analysis
  • Not for Risks which are Potentially Severe

34
Risk Management is Project Management
  • Another Tool for PM
  • Supplements
  • Requirements Definition
  • Task Definition
  • Scheduling
  • Budgeting
  • Configuration Management
  • Change Control
  • Performance Tracking and Control

35
Risk Management Principles
  • Create Risk Management Plan
  • Create a Risk Profile
  • Likelihood
  • CS Impact
  • Contingencies
  • Trigger Events
  • Risk Officer
  • Not the PM
  • Devils Advocate

36
Risk Management Principles (Continued)
  • Calculate a Risk Reserve
  • Risk Time RT
  • Risk Cost RC
  • Monitor Risk Continuously
  • Establish Communication Channels
  • Document Everything of any Value for Lesson
    Learned

37
Expect the Unexpected
  • Do All You Can
  • Cannot Cover Every Contingency
  • Bonapartes Principle came along before Murphys
    Laws, i.e., Something Surely Will Go Wrong Plan
    for It to Occur

38
Caveats (Bewares)
  • Input to RA is Subjective
  • Not what will but what might
  • Analysis and Planning gives Sense of Power
  • Managing not Eliminating
  • Stifles Imagination
  • Brute Force Approach to Technology
  • Micromanagement is Never Appropriate

39
Risk Analysis Methods
  • Expected Value
  • Decision Trees
  • Uncertainty and Payoff Tables
  • Simulations

40
Expected Value
  • For A Project,Expected Value Represents the
    Average Outcome
  • Weighted Average of all Outcomes
  • Likelihoods are the Weights
  • EV SUM (Outcomes x Likelihood)
  • Risk Project Time and Cost are Determined Using
    Expected Value

41
Expected Value (Continued)
  • Risk Consequence on Project Duration is Risk
    Time, RT
  • RT (Corrective Time) x (Likelihood)
  • Risk Consequence on Project Cost is Risk Cost, RC
  • RC (Corrective Cost) x (Likelihood)
  • BTE Baseline Time Estimate
  • BCE Baseline Cost Estimate

42
Expected Value (Continued)
  • To Account for Risk factors that Affect the
    Project as a Whole
  • Expected Project Completion Time, ET
  • ET BTE RT
  • Expected Project Completion Cost , EC
  • EC BTC RC
  • When ET and EC cannot be Estimated
  • ET BTE (1 Likelihood)
  • EC BTEC (1 Likelihood)

43
Expected Value (Continued)
  • A Better Way to Calculate Expected Values for the
    Entire Project
  • Consider each WBS Element/Work Package Separately
  • Estimate Risk Likelihood and ET and EC
  • Aggregate for the Entire Project

44
Expected Value (Continued)
  • EC BCE ( (Corrective Cost) x (Likelihood))

45
Expected Value (Continued)
  • ET BTE ( (Corrective Time) x (Likelihood))

46
Project Network With Risk Times from Previous
Table
47
Decision Trees
  • Decision Tree a Pictorial Representation of
    different Chance events or Strategies
  • Assess the Risk Response which obtains the
    best-to-be Expected Consequence
  • Application
  • Cost of Potential Project Failure Against Benefit
    of Project Success
  • Expected Outcome BCE x (Failure Likelihood)
    Net Profit x (Probability of Success)
  • Alternative Risk Responses
  • BCE 10M,
  • Risk Factor (Likelihood ) 0.6
  • Risk Impact 5M

48
Decision Tree for Alternative Risk Responses
49
Uncertainty and Payoff Tables
  • Uncertainty When no Prior Experience Exists EV
    Risk Consequence Cannot be Computed
  • Best Strategy under Uncertainty
  • Identify Alternative Routes
  • Routes are Called States of Nature
  • Consider all Strategies and Assign the Likely
    Outcome for Each State of Nature
  • The Likely Outcomes are Represented in a Payoff
    Table

50
Payoff Table for Three Strategies and Three
States of Nature
51
Uncertainty and Payoff (Continued)
  • Regret Any Choice of Strategy other than the
    Best One
  • Minmax Regret A Strategy which minimizes the
    regret of not having made the best(max) choice
  • Regret for a Given State of Nature is the
    difference in the outcomes between the Best
    Strategy and any other Strategy (Regret Table)

52
Regret Table for Three Strategies and Three
States of Nature
53
Uncertainty and Payoff (Continued)
  • Another Approach to Strategy Selection
  • Assume Every State of Nature has the Same
    Likelihood using the Maximum Expected Payoff
    Criteria
  • Outcome is Calculated from the Expected Payoff
    for Each Strategy as the Sum from Each State of
    Nature Value Times the Constant Likelihood Value
  • The Maximum Value (by Strategy) is the Best
  • NB Three of the Four Selection Criteria Yield C
  • Irresistible

54
Simulations
  • This Top was Covered in Chapter 8
  • More in the Tutorial _at_RISK

55
Next Topic
  • Chapter 11 Project Control
  • It will Require Two Lectures
  • Read Chapter 11
  • Work Review Questions and Problems in Chapter 10
    (This is not a HW assignment) 3, 4,9,13,15, 20,
    22, 23, 28
Write a Comment
User Comments (0)
About PowerShow.com