Title: THE DETERMINATION OF APPROPRIATE PROJECT DELIVERY METHOD


1
THE DETERMINATION OF APPROPRIATE PROJECT DELIVERY
METHOD
2
AUTHORIZED PROJECT DELIVERY METHODS
  • Section 11-35-3005(1)   
  • design-bid-build
  • construction management at-risk
  • design-build
  • design-build-operate-maintain and
  • design-build-finance-operate-maintain.
  • any combination of the above methods approved by
    the State Engineer

3
Project Delivery Options Translator Defining
Characteristics of Each Option
? ? ? ? ? ?
? ? ? ? ? ?
4
Agency Must Determine Which Project Delivery
Method is Most Advantageous to State for the
Project at Hand SC Reg
19-445.2145(B)(1)
  • Will the selected method result in the most
    timely, economical, and otherwise successful
    completion of the project

5
Agency Must Carefully Assess
  • Requirements the project must satisfy
  • Other characteristics that would be in the best
    interest of the State

6
Facts Considerations (what, when, why)
  • Facility
  • type of infrastructure facility or service to be
    acquired
  • size, scope, complexity, and technological
    difficulty
  • extent to which the design requirements for the
    Infrastructure Facility are known, stable, and
    established in writing
  • Location
  • Time Deadlines

7
  • Financing to support design, construction,
    operations, maintenance, repairs, and demolition
    over the facility life cycle
  • Sources of funding
  • Projected cash flow
  • Available Project Delivery Methods
  • comparative advantages and disadvantages of each
  • how these methods may be appropriately configured
    and applied to fulfill State requirements
  • the methods used on similar projects in the past
    and results achieved

8
  • Decision-Making and Administrative Services
  • State personnel available to the governmental
    body
  • Extent to which functions may be appropriately
    assigned to designers, builders,
    construction-managers at-risk, design-builders,
    DBO producers, DBFO producers, peer reviewers, or
    operators
  • Extent to which outside consultants, including
    construction manager agent, may be able to assist
    the governmental body

9
The Written Determination
  • Must describe
  • Project delivery method (Section 11-35-3005),
  • Source selection method (Section 11-35-3015 and
    11-35-1510),
  • Any additional procurement procedures (11-35-3023
    and 11-35-3024(2)(c), and
  • Types of performance security selected (Sections
    11-35-3030 and 11-35-3037)
  • Must set forth the facts and considerations
    leading to these selections (see previous slides)

10
The Determination Sloan v. Greenville County
  • Must effectively inform your governing Board why
    selected delivery method works to the states
    best advantage for the project at issue
  • Must provide the citizens of the state a window
    into the agencys decision-making process
    safeguarding the quality and integrity of the
    contract awards through public accountability

11
Design-Bid-Build Using Competitive Sealed
Bidding SC Reg 19-445.2145(B)(3)
  • Is an appropriate project delivery method for
    any infrastructure facility and may be used by
    any governmental body without further project
    specific justification
  • Excepting guaranteed energy, water, and waste
    water savings projects

12
Determination to Use Design-Bid-Build
  • Project Name ______________________Project No
    ________________________Regarding the above
    referenced project, I have determined as follows
    1 Design-bid-build is the appropriate project
    delivery method, as provided by Regulation
    19-445.2145(B)(3). 2 Competitive sealed bidding
    is the appropriate source selection method, as
    provided by Section 11-35-3015(2)(b). 3 No
    additional procurement procedures, as addressed
    in Sections 11-35-3023 and 11-35-1024(2)(c), will
    be utilized. 4 Bonds or a certified cashier's
    check, as provided in Section 11-35-3030 and
    Regulation 19-445.2145(C), will be required based
    on the project delivery method.

13
Determination to use a Project Delivery Method
Other Than Design-Bid-Build Must Explain Why the
use of Design-Bid-Build is not Practical or
Advantageous to the State
14
State Engineer Approval Required
  • Submit Agency Determination with Request for
    Approval to OSE

15
Special Considerations for Alternative Project
Delivery
  • Request for Proposal Process must be conducted
    under the supervision of OSE
  • RFP process described in Chpt. 6.2 of the Manual
    for Planning and Execution of State Permanent
    Improvement Projects, Pat II
  • RFP Handbook
  • Everyone involved in the selection process,
    including approvals must execute a conflict of
    interest and confidentiallity statement

16
Special Requirements of Design-Build
  • Design Requirements
  • Proposal Development Documents
  • Independent Peer Review

17
Design Requirements
  • written description of the infrastructure
    facility including
  • required features, functions, characteristics,
    qualities, and properties
  • anticipated schedule, including start, duration,
    and completion and
  • estimated budgets for design, construction,
    operation, and maintenance.
  • may, but need not, include drawings and other
    documents illustrating the scale and relationship
    of the features, functions, and characteristics
    of the project.

18
Proposal Development Documents
  • Drawings Other Related Data Sufficient to Fix
    and Describe
  • Size
  • Character
  • Price

19
Independent Peer Review
  • to confirm that the key elements of the
    professional engineering and architectural design
    provided by the contractor are in conformance
    with the applicable standard of care

20
Special Considerations for CM at
Risk19-445.2145(N)
  • Prior to contracting for a GMP, CM services paid
    as a fee based on fixed rate, fixed amount, or
    fixed formula
  • construction may not commence until after Agency
    and CM contract for a fixed price or a GMP
    regarding that portion of the construction

21
QUESTIONS?