RGVSG RENEWABLE ENERGY PROJECT - PowerPoint PPT Presentation

1 / 42
About This Presentation
Title:

RGVSG RENEWABLE ENERGY PROJECT

Description:

RGVSG RENEWABLE ENERGY PROJECT Presentation prepared by INTRODUCTION RGVSG proposes to construct a $23.8 million Clean Energy and Clean Air Project The Project will ... – PowerPoint PPT presentation

Number of Views:148
Avg rating:3.0/5.0
Slides: 43
Provided by: Kiet7
Category:

less

Transcript and Presenter's Notes

Title: RGVSG RENEWABLE ENERGY PROJECT


1
RGVSG RENEWABLE ENERGY PROJECT
  • Presentation prepared by

2
INTRODUCTION
  • RGVSG proposes to construct a 23.8 million Clean
    Energy and Clean Air Project
  • The Project will involve partial funding from the
    North American Development Bank (NADB)
  • Certification by the Border Environment
    Cooperation Commission (BECC) is required

3
PROJECT OBJECTIVES
  • Project needs to result in a net reduction in the
    emission of air pollutants
  • The Upgraded Facility should utilize all of the
    bagasse for on-site energy production with excess
    energy available that can be sold
  • Improve efficiency for existing needs and for
    future expansion of Mill capacity

4
BACKGROUND
  • RGVSG Mill has been in existence since 1973 and
    employs 188 full-time personnel (approximately
    565 personnel during the grinding season)
  • The RGVSG Cooperative has a membership of 127
    sugar growers and is the only sugar mill in the
    State of Texas

5
BACKGROUND
  • Project is located 2 ½ miles west of the City of
    Santa Rosa on Hwy 107
  • The RGVSG members actively farm up to 47,000
    acres of sugar cane (3 of the arable land in
    RGV) yet provides almost 12 of the GDP in the
    RGV (75M/Yr)

6
PROJECT HISTORY
  • RGVSG contracted with Schaffer Associates in
    1998 to conduct planning and design work for a
    two-phase expansion of the Mill
  • Schaffer Associates were the original design
    engineers in 1972 when the Mill was constructed
  • Phase 1 includes Bagasse Boiler Upgrade
  • Phase 2 includes Boiler House Upgrades

7
PROJECT HISTORY
  • C-K Associates were contracted by the RGVSG in
    2000 to complete the air emissions report,
    computer modeling and permit applications for the
    Air Quality Permit
  • In 2002 RGVSG determined that due to market
    conditions and past performance, funding for the
    23.8 million Project would be sought to
    implement the design of the Phase 1 Mill
    Expansion

8
PROJECT HISTORY
  • RGVSG contacted NADB to request partial funding
    under the new mandate program by NADB
  • Turner Collie Braden Inc. (TCB) was contracted
    by the RGVSG to coordinate and prepare the
    required Project Certification Documents for BECC
    approval
  • NADB contracted Pollutech International Limited
    to complete the technical review on behalf of the
    NADB

9
SUGAR MILL PROCESS
  • The proposed Mill Operation is 200 operating days
    based on 100 new boiler capacity and a maximum
    of 70 old boiler capacity
  • Plant was originally designed for 7,500 tcd (tons
    of cane per day) which has been upgraded to
    10,000 tcd and will remain at this capacity for
    the Project
  • Potential to expand to 15,000 tcd with the
    implementation of Phase 2 Improvements in the
    future and change in US Quota (Farm Bill)

10
SUGAR MILL PROCESS
  • General Process of Operation includes
  • - receipt and weighing of cane at the mill
  • - washing of raw cane to remove soil
  • - heavy duty shredding to prepare for milling
  • - milling (7 mills in tandem) to remove 95 of
    sugar juice in cane
  • - sugar juice limed and heated for contaminant
    removal
  • - clarification of heated and limed juice
  • - clarified juice to pre-heaters to produce
    concentrated syrup
  • - concentration of syrup in vacuum pans to form
    crystalline sugar
  • - batch centrifugation to separate sugar from
    liquor (molasses)
  • - storage of crystalline sugar in the sugar
    warehouse

11
Receipt of Cane at Mill
12
Washing/Shredding of raw cane
13
Milling of Cane (7 mills in tandem)
14
Heating/Evaporation
15
Separation of Sugar/Molasses
16
Storage of Raw Sugar
17
Storage of Molasses
18
Bagasse Handling/Storage Area
19
PROCESS FLOW CHART
20
MASS BALANCE SUMMARY
  • NOTE WATER MAKES UP THE REMAINING 48 LOST TO
    EVAPORATION

Component Percent of Cane 5 Year Average () Production Data (tons/year)
Raw Cane 100 1,600,000
Sugar 9.85 157,571
Molasses 3.7 59,283
Bagasse 30 480,296
Filter Mud 6.1 97,642
Cane Wash Sand 1.2 19,192
Ash 1.36 21,823
Air Emissions 0.03 471
21
PROJECT DESCRIPTION
  • The proposed project includes
  • - conversion of all bagasse conveyors to fully
    automated belt conveyors
  • - expansion and upgrade of the bagasse storage
    building
  • - conversion of the boiler building to handle
    the modified bagasse conveyor system
  • - installation of a new high efficiency boiler
  • - new condensate storage tank
  • - rebuilt 6,000 KW turbine generator

22
New Bagasse Handling System
  • Necessary to remove limitations on the delivery
    of the primary fuel source for the boilers
  • Significantly reduce or eliminate the need and
    associated costs of the front end loaders and
    operators

23
New Boiler
  • The addition of a new boiler to increase steam
    capacity by 300,000 lbs/hr for total capacity of
    800,000 lbs/hr (60 increase)
  • A wet scrubber and mechanical dust collector to
    reduce air emissions
  • Since the Plant only needs 540,000 lbs/hr to
    operate, existing boilers are operating at
    reduced capacity (reduced air emissions from both
    existing and new boilers)

24
TURBINE GENERATOR
  • New Boiler will be coupled with a Topping Steam
    Turbine (already purchased) and a new 6000 KW
    Turbine Generator
  • Will bring installed power to 11,000 KW
  • Will enable the Plant to produce energy for
    operation and export (sell) excess energy

25
PROJECT BENEFITS
  • Reduction in use of fossil fuels through the
    implementation of a renewable energy source
    through production of 11 MW leaving 5 MW for sale
  • Eliminates the need for purchase of 1.7 MW of
    outside energy that will be available for use by
    others
  • A 42 reduction in total mass of air pollutants
  • Increased level of service to RGVSG members

26
PROJECT COSTS
  • Source NADB Pollutech Report
  • Note Payback does not show any cost recovery
    from the sale of power

Process Upgrade (10,000 tcd) Capital Cost Annual Cost Savings Payback Period (years)
Bagasse Handling 6,442,532 247,478 26.0
Boiler Upgrades And Turbine Generator 17,384,405 1,853,120 9.4
Total Upgrade 23,826,937 2,100,598 11.3
27
PLANT POWER BALANCE
Year Natural Gas Purchased Electricity Purchased Purchased MW Average Day Total Demand MW Bagasse Power MW Grid Power - Sale Purchase
1998 Mft3 160,332 438,278 KW 6,942,600 423,731 2,042 hrs 3.40 MW 239,211 tby 0.12 MW 3.40 MW
1999 Mft3 228,638 536,114 KW 8,354,400 486,289 2,939 hrs 2.85 MW 346,033 tby 0.12 MW 2.85 MW
2000 Mft3 268,171 701,962 KW 8,841,600 550,183 2,485 hrs 3.56 MW 316,836 tby 0.13 MW 3.56 MW
2001 Mft3 324,482 2,005,955 KW 17,906,400 1,363,775 4,076 hrs 3.80 MW 457,573 tby 0.13 MW 3.80 MW
2002 Mft3 23,210 52,723 KW 10,661,592 697,058 3,936 hrs 2.71 MW 457,573 tby 0.14 MW 2.71 MW
Typical Day 6 MW 4.3 MW 1.7 MW
Future KW 0 0 3,600 hrs 0 MW 6 MW 11 MW - 5 MW
28
PLANT POWER SUMMARY
  • Note based on 24/hr day, 150 days per year
    (3,600 hours/year)
  • Source NADB Pollutech Report, January 2003

Operating Capacity Supply (kw/hr) Demand (kw/hr) Deficit (-) Excess () (kw/hr) Power Purchased (0.051/kw) Power Sold (0.025/kw)
Current production (10,000 tcd) 11,000 6,000 5,000 450,000
Bonus for reduce grid draw 1,700 312,120
29
AIR QUALITY
  • The RGVSG expect to receive the draft permit from
    the TCEQ for the Mill Operations issuance of
    final permit within 60 days after public comment
    period (Consolidated Permit No. 114)
  • The RGVSG is defined as a major stationary
    source under the Federal Clean Air Act
  • The RGVSG also has a Cane Burning Permit

30
AIR QUALITY
  • RGVSG is permitted for
  • - 2,490.4 tpy CO
  • - 0.54 tpy SO2
  • - 233.2 tpy Nox
  • - 222.08 tpy CO
  • - 443.88 tpy VOC
  • As a result, the RGVSG Mill is subject to PSD
    Regulations (Prevention of Significant
    Deterioration) thus must conduct analysis of BACT

31
AIR QUALITY
  • The proposed air quality permit limits the
    operation of the existing boilers at 70 capacity
    and the new boiler at 100 capacity (note power
    required for 10,000 tcd results in 29 capacity
    for old boilers)
  • The reduction in total air emissions for the
    upgraded facility results from the reduced
    operation of the existing boilers and increased
    efficiency of the new boiler

32
PSD EVALUATION
  • Growth Analysis No additional air emissions
    from off-site growth
  • Air Quality Impact Analysis modeling analysis
    adequately evaluates the total ground level
    concentrations of NO2 from improvements
  • Soils/Vegetation Analysis the projected NO2
    concentrations are below the standards and
    significant level thus no adverse impact
  • Visibility Impairment Analysis plant is located
    in sparsely populated area with no scenic vistas
    or airports thus no impairment
  • Area Impacts the plant is located 1,110 km from
    the closest Class 1 Area (Big Bend) thus no
    impact (gt100 km separation)

33
PROJECTED EMISSIONS
  • 1 Actual reported emissions based on stack
    testing of October 2001
  • 2 Projections from Pollutech Analysis Boilers
    1 to 4 at 34, new Boiler at 90

Current Emission Rate (tpy)1 Old Boilers at 34 Cap (tpy) New Boiler at 90 Cap (tpy) Total Plant Emissions2 Emissions Change (tpy) Emissions Change ()
CO 2458 1091 229 1320 -1138 -46.3
SOx 2.1 0.9 0.01 0.91 -1.2 -55.3
Nox 482 214 225 439 -43 -9.0
PM10 385 171 27 198 -187 -48.6
VOC 157 70 9 79 -78 -50.0
Total 3484 1547 489 2036 -1448 -41.6
34
CROP BURNING
  • In addition to the Air Quality Permit for the
    Plant, the RGVSG also has a Crop Burning Permit
    under Order 94-35
  • The cane burning is authorized only until such
    time that an alternative method of harvesting
    becomes technologically practicable and
    economically reasonable and which would not
    require outdoor cane burning

35
CROP BURNING
  • Permit was developed through input of the
    Sugarcane Burning Task Force which included the
    Sierra Club
  • There are a number of conditions that must be met
    that include
  • - RGVSG shall report each year on program to
    stimulate development of harvesting methods that
    eliminate outdoor burning
  • - Submission of a comprehensive map of burn
    areas prior to harvesting
  • - A series of preharvet burning conditions that
    limits burns to specific times and conditions
    and maximum number of acres per day in each
    quadrant (200 acres)
  • - RGVSG was required to monitor cane burn for a
    1 year period after permit was issued in 1994 by
    an environmental firm for PM10 emissions before,
    during and after burns to set the baseline.

36
CROP BURNING
  • RGVSG is continuing to evaluate alternative
    technologies to cane burning at this time
  • This past year the RGVSG reported that almost 30
    of the cane was green harvested and that they
    project this to increase in the future

37
ENVIRONMENTAL ASSESSMENT
  • TCB has provided an environmental assessment of
    the project in support of the Step 2 Report
  • These findings are summarized below
  • - Air Quality impacts are significantly reduced
  • - Project promotes the use of renewable energy
    sources
  • - Project reduces reliance on fossil fuels
  • - There are no water/wastewater issues, Plant is
    effectively Zero Discharge although a Discharge
    Permit is in effect

38
ENVIRONMENTAL ASSESSMENT
  • RGVSG has a Stormwater Pollution Prevention Plan
    with proactive monitoring
  • Cumulative Impacts are positive to the
    environment
  • Positive socioeconomic impact through short-term
    impacts due to construction and long-term due to
    increased sustainability and efficiency
  • RGVSG is proactive towards environment as
    evidenced by P2 Site Assistance Visit/Small
    Business Compliance Audit/TCEQ Pilot EMS Program

39
BECC CRITERIA
BECC CRITERIA COMPLIANCE
Alternative Analysis ?
International Treaties and Agreements ?
Human Health and Environment ?
Compliance with State and Federal Regulations ?
Environmental Impact Assessment ?
Technical Feasibility ?
Appropriate Technology ?
Operation and Maintenance Plan ?
Design Regulations and Standards ?
Financial Feasibility ?
Community Participation Plan ?
40
PROJECT STATUS
  • Currently, the design has been completed for the
    Phase 1 and Phase 2 Expansions with some portions
    of Phase 1 already being bid with analysis of
    contractor bids
  • RGVSG is seeking certification approval by the
    BECC in March 2003
  • The Step 2 Report and Technical Evaluation by
    NADB will be completed by February 3, 2003

41
PROJECT SCHEDULE
  • Project approval on March 27, 2003
  • Completion of PPA and Loan Closings in late
    2003/early 2004
  • Completion of Bagasse Handling Facilities in 2004
  • Completion of Boiler/Generator Facilities by
    April 2005 (12 months lag time from order to
    delivery of boiler)

42
PUBLIC COMMENT
  • Remember to sign the attendance log and survey
  • If you do not wish to speak, written comments may
    be submitted to
  • Rio Grande Valley Sugar Growers, Inc.
  • P.O. Box 459
  • Santa Rosa, Texas 78593
  • Attention Jack Nelson, President
  • Comments will be accepted up to February 3, 2003
Write a Comment
User Comments (0)
About PowerShow.com