Title: Bringing Agile to Non Agile Product Management


1
Bringing Agile to Non Agile Product Management
  • Andy Mulhearn
  • Thomson Financial

2
What happened and when?
  • June/July 2003 Project Approval
  • September 2003 team formed
  • October 2003 team reaches full strength
  • January 2004 take over as PM
  • Feb 2004, lost one team member
  • March and May 2004 Milestones
  • September 2004 enter Beta
  • October 7th 2004, Live!

3
Ive had to raise my game!
  • Ive had to raise my game!
  • but they pushed back on
  • Its easier to move the cards around
  • But I cant see the cards when Im at home
  • So what am I going to get in
  • it changed while I was doing a demonstration!
  • What do I book my time to?

4
And then we took our eye off the ball
  • We stopped doing Acceptance Tests
  • We got hauled into preparation for production
    releases
  • We got separated from our Product Managers
  • We stopped finding time for pink cards
  • Non-agile approval of work process

5
The Wall
6
The Wall
7
The Wall
8
But its not all bad
  • Very predictable timescales
  • No surprises in a release
  • We have an excellent product
  • Usability is good
  • With an extremely low number of defects
  • And it has been easy to enhance