Title: CEO Briefing
1CEO Briefing
2Countdown
Jarrow Count Down To Go Live as at 10th April
2002 Just 33 Total Days 22 JSE Business Days
Remaining
3A note of Thanks
We would like to thank Members and Users for all
their efforts to date resulting in us being on
track for Go Live on the 13 May 2002
4Timeline
2001
2002
June
Aug
Oct
Sept
Feb
Jan
Dec
Nov
July
Mar
April
May
4/6/01
3/8/01
JSE Design
19/10/01
6/8/01
JSE Development
4/6/01
19/10/01
JSE Build and Test of
Technical
Infrastructure
22/10/01
JSE/LSE Prepare and Execute
Integration Test
18/01/02
4/6/01
3/8/01
9/11/01
Prepare and Execute Business Operations Proving
12/4/02
21/1/02
Design of JSE Front End Solution
Build and Test of JSE
Front End Solution
2/03/02
LCON
16/03/02
Design, Build and Test of Data Vendor / Member
Front End Solution
LCON
27/6/01
18/01/02
30/03/02
LCON
13/4/02
1st DR
31/03/02
18/7/01
27/6/01
4/6/01
27/04//02
JSE / LSE Draft Spec
JSE / LSE Final Spec
Prepare and Execute Customer Test
26/11/01
2nd DR
Go-live
5CEO Brief
Agenda
- Objectives
- Principles
- Timeline
- Participation and Responsibility
- Test Schedule
- Business Freeze
- Other
- Questions
6CEO Brief
Agenda
- Objectives
- Principles
- Timeline
- Participation and Responsibility
- Test Schedule
- Business Freeze
- Other
- Questions
7Objectives
- Practise the JSE, LSE, FTSE and User cut over
activities required for Go Live - Practise the 1st and 2nd trading day activities
of the new JSE SETS and InfoWiz systems solution
- Gauge the overall level of readiness across the
JSE, LSE, FTSE and the JSE NSX Users to cut
over to the new solutions - Identify any critical issues that need to be
addressed prior to Go live - Ensure the overall solution meets JSE
requirements - Build internal and external confidence for Go
Live - Minimise the risk of unexpected issues on Go Live
day - Provide Users with an opportunity to test and
verify the accuracy and integrity of their NEW
front-end solutions for trading and information
dissemination - Provide Users with an opportunity to test
accuracy and integrity of related systems and
feeds
8Objectives
- Confirm internal JSE, LSE and FTSE readiness for,
and effectiveness of, new / changed business
processes, to ensure smooth future operations - Provide Users with an opportunity to test and
familiarise themselves with the new JSE trading
model functionality and revised rules in a
live-like environment - Prove existing internal JSE application readiness
for Go live. e.g. BDA, EMIS etc - Prove the effectiveness of the new JSE regulatory
requirements
9CEO Brief
Agenda
- Objectives
- Principles
- Timeline
- Participation Responsibility
- Test Schedule
- Business Freeze
- Other
- Questions
10Principles
- All Dress Rehearsals are compulsory for all
Equity Trading users and subscribers of InfoWiz. - Dress Rehearsals will be undertaken in the Live
JSE, LSE User Environments. - The Live environment of the JSE , LSE FTSE will
be restored after the rehearsals in readiness for
business as usual on the following Mondays - Only Users that have passed their LCON tests will
be allowed to partake in the Dress Rehearsals - All Dress Rehearsals will be supported by
internal JSE departments on a proof of concept
basis - The test schedule will be structured around
normal business operations - Dress rehearsals are planned to test system
functionality and integrity. These are not
stress tests!!! - Users are expected to behave in an orderly manner
and to simulate a live trading day with realistic
order details and related prices - All User applications to be used in the live
environment must be tested in the Dress Rehearsal - All terminals connecting to production must be
manned by adequately skilled staff for the test
11CEO Brief
Agenda
- Objectives
- Principles
- Timeline
- Participation and Responsibility
- Test Schedule
- Business Freeze
- Other
- Questions
12Deployment Timeline
April
May
March
3 Apr
DR 1 Brief (JHB)
2 May
Cont DR Brief (tbc)
4 Apr
DR 1 Brief (CT)
LCON 1
Dress Rehearsal 3 (CONT)
JSE LSE Internal Dress Rehearsal
Sat/ Sun4-5 May
Sat2 Mar
Sat6 Apr
8 May
Final Cut-Over Brief (JHB)
CEO Brief (JHB)
10 Apr
9 May
Final Cut-Over Brief (CT)
Sat/ Sun13-14 Apr
LCON 2
Dress Rehearsal 1
10 May
CEO Brief (tbc)
Sat16 Mar
17 Apr
DR 2 Brief (JHB)
LEGEND LCON Live Connectivity Testing DR Dress
Rehearsal CONT Contingency ASR Alternate Site
Recovery (LSE) Internal External
Tests completed
18 Apr
DR 2 Brief (CT)
JSE LSE ASR Test
Dress Rehearsal 2
Sat/ Sun27-28 Apr
Sat23 Mar
JHB Brief
LCON 3
Sat30 Mar
CT Brief
13CEO Brief
Agenda
- Objectives
- Principles
- Timeline
- Participation and Responsibility
- Test Schedule
- Business Freeze
- Other
- Questions
14 Participation
- MANDATORY Participation is required during the
Saturday live trading day simulation from - - All JSE and NSX Equities traders 100
participation in all scheduled DR tests - All relevant user IT support staff.
(e.g.networks, applications, PC support etc) - All information users who will be
subscribing to InfoWiz - All basket trading and client order entry
applications - All other user applications interfacing with
their front-end applications - The test starts at 10h30 and ends at 18h00
(traders 12h00 18h00) - All primary and backup(on site) terminals
must be tested - NOTE From go live, members accept full
responsibility for all order and trades submitted
by their traders. Dress Rehearsals therefore
facilitate testing in a live-like environment to
avoid errors and prepare traders for the new JSE
rules and trading model.
15 Participation
- OPTIONAL Participation - (However, strongly
recommended) - All Equity Institutional traders
- User Off-site Disaster recovery terminals
JSE will be testing TALX DRP terminals - All customers receiving JSE overnight
End-of-Day (EOD) files - Sundays trading day simulation testing
between 08h30 and 10h00 is optional, but - recommended
- JET testing 11h00 13h00 on Sunday to
ensure ready for business as usual
16Responsibility
USERS are responsible for ensuring
- They participate throughout the test between
10h30 18h00 on all the test days - Full participation from all traders (12h00
18h00). - Full participation from all relevant User IT
support staff (e.g Networks, applications, PC
support etc) - Full support from relevant software providers
- Identifying the responsible person per User to be
used by the JSE as the key contact person. Users
must provide the contact details to the JSE
helpdesk by Wednesday (10 April) by 12h00 on
(011) 520-7309 - All Users follow the test plan and schedule -
PLEASE READ TEST PLAN/SCHEDULE!!!! - ONLY realistic prices and order details are used
for all orders failure to do so, will result in
unnecessary disruptions and potential delays to
the test schedule. The JSE will be monitoring
all test data and this behaviour will result in a
User Dress Rehearsal FAIL!!!!! - Staff are aware of problem escalation procedures
to ensure problems logged with the correct
helpdesk. E.g Front-end queries are logged with
software providers not the JSE - All problems are reported and logged with the JSE
Customer Support (011) 520 7777
17Responsibility
USERS are responsible for ensuring (cont..)
- All user test data is removed from their
production environments after the Dress
Rehearsals - All traders have attended conceptual training
prior to the Dress Rehearsals - All traders have attended front-end training
prior to the Dress Rehearsals - All JSE test scripts and procedures are
downloaded from the JSE web prior to the test - That all users are informed this is NOT a stress
test and that attention should be given to
functionality and data integrity. Users are
responsible for ensuring data accuracy. - Members make use of the JET testing on Sunday to
ensure they can continue with trading the Monday
after each test. - Ensuring users keep track of all actions in the
event of a problem to assist with problem
determination. - Relevant monitoring of their infrastructure and
related applications is performed during the
dress rehearsals - NOTE PATIENCE IS REQUIRED AS ALL TRADERS WILL
BE TESTING - THIS WEEKEND
18Responsibility
- JSE is responsible for ensuring
- Support will be through the JSE Customer Support
helpdesk - All queries are allocated a reference number
- Ensure all queries are addressed and resolved
- First line support for all TALX related queries
- Monitoring of all test data and users to ensure
compliance with the test schedule and scripts
(including errors generated by users) - Test schedule execution and adjustments as
required watch the market messages for
adjustments - Evaluate Dress Rehearsal participation and
success and GO LIVE readiness - Contact Number during test
- JSE Customer Support (011) 520-7777
19CEO Brief
Agenda
- Objectives
- Principles
- Timeline
- Participation and Responsibility
- Test Schedule
- Business Freeze
- Other
- Questions
20Market Structure
- The trading platform has been divided into
several functional segments to facilitate trade
and efficient running of the market. - Functional segments and sectors facilitate the
setting of common trade parameters for
instruments with similar characteristics. - The segments are determined by grouping stocks
with similar liquidity classifications as they
have similar characteristics.
JSE Top Companies ZA01
JSE Medium Liquid ZA02
JSE Less Liquid ZA03
NSX ZA11
- ALSI40 equities and related instruments.
- Functional sectors obey the same trading
schedules and similar trade period rules.
- Liquid and Medium liquid equities and related
instruments which are not part of the ALSI40. - Functional sectors obey the same trading
schedules and similar trade period rules.
- Less liquid equities and related instruments.
- Functional sectors obey the same trading
schedules and trade period rules. - Intra-day liquidity auctions are used to
facilitate trade.
- NSX instruments.
- Functional sectors may obey different trading
schedules and trade period rules. - Intra-day liquidity auctions will be used to
facilitate trade.
21Dress Rehearsals Schedule
Proposed schedule - under discussion
Systems Startup Ref Data Download
Normal Trading Schedule
SystemsShutdown
JSE Batch Processing
1
2
Saturday
Pre Open
MktClose
11h00
24h00
18h00
12h00
Batch Processing(contd)
2
Checking of Batch Results
2
00h00
08h00
06h00
Software VendorFeedback
Internal JSE/LSE Checkpoint
JSE Prep Session
Sunday
12h00
08h30
10h30
09h30
SystemsStartup RefData Download
Normal Trading Schedule (partial)
1
ContinuousTrading
Pre-Open
06h00
08h30
10h00
Colour Legend
- Trading Schedule will be condensed to fit into
shorter window (details on next slide). - Batch processing will be done during the 1st
Market Dress Rehearsal (13-14 Apr). - Intraday checkpoints with Users will be indicated
in the detailed schedule. - All times reflected are SA standard time (SAST)
JSE/LSE Internal
Notes
JSE User Participation
JSE User Feedback
JSE/LSE Checkpoint
22Test Schedule Saturday
Certain period names may differ depending on
which segment or sector they are used in
23CEO Brief
Agenda
- Objectives
- Principles
- Timeline
- Participation and Responsibility
- Test Schedule
- Business Freeze
- Other
- Questions
24Business Freeze
25Business Freeze
26Business Freeze
JET GTC Freeze Everyday thereafter will be
reduced by one (1) day Traders responsible for
keeping records for large orders
27CEO Brief
Agenda
- Objectives
- Principles
- Timeline
- Participation and Responsibility
- Test Schedule
- Business Freeze
- Other
- Questions
28BDGs for Release 1
NSX BDGs NO1, NO2, NO3, NO4
Optional Added Product
J50 JSE News Service SENS
J51 FTSE / JSE Africa Index
Value Add Products
Currently Free
J25 JSE Cumulative Number and Volume of Trades
J24 JSE VWAP
Level 2 J20 Full Order Book
Level 1 J21 Best Bid and Ask
Level 2
Level 1
NOTE These are included in the
membership fees
29JSE Systems NOT Available
On these dates no JSE Applications are available
for normal production activity
30Major Milestones
31Monitoring Success / Pass Criteria
- User ability to connect and trade
- 100 interactive participation throughout
the test period - Adherence to the test schedule and
conditions - Adherence to realistic order details and
prices - Adherence to normal trading and volume
activity (NB!! NOT a stress test) - Completed and signed test checklists/results
returned to the JSE - Completed and signed declaration that
functionality and data integrity was intact - All problems logged with JSE Help Desk
before end of each test day - Key responsible person identified and
communicated to JSE prior to test - No excessive re-requests for data during
tests - Limited system errors generated by users in
system logs - All user participation
- Number of traders logged on
- Time of first and last message sent per
trader - Order and trade data generated per trader
- All messages per user
- Errors generated
- Order and trade summary of all client
application trader ids
32Questions