U.S. Domestic Reactor Conversion Programs - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

U.S. Domestic Reactor Conversion Programs

Description:

Support the National Nuclear Security Administration's Global Threat Reduction ... This practice eased the Request for Additional Information process. ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 19
Provided by: trtr
Category:

less

Transcript and Presenter's Notes

Title: U.S. Domestic Reactor Conversion Programs


1
U.S. Domestic Reactor Conversion Programs
  • Eric Woolstenhulme
  • Dana Meyer

2007 TRTR Conference
September 2007
2
Background on the current U.S. Domestic
Conversion Program at the INL
  • Support the National Nuclear Security
    Administrations Global Threat Reduction
    Initiative to reduce the amount HEU by converting
    7 U.S. research and training reactors from
    HEU-to-LEU fuel by 2009

3
The Conversion Generally Includes
  • Revision of the facilities Safety Documents and
    supporting analysis
  • Fabrication of new LEU fuel
  • Change-out of the reactor core
  • Removal of the used HEU fuel (by INL University
    Fuels Program)

4
Three major Reactor Conversion Program milestones
have been accomplished since 2006
  • The conversion of the TRIGA reactor at Texas AM
    University Nuclear Science Center
  • The conversion of the University of Florida
    Training Reactor
  • The conversion of the Purdue University Reactor

5
The major entities involved are
  • U.S. Nuclear Regulatory Commission
  • University reactor department
  • Fuel and hardware fabricators
  • Spent fuel receipt facilities
  • SNF shipping services
  • U.S. Department of Energy and their subcontractors

various branches reactor operations, radiation
protection, shipping, procurement, and etc
BWXT, CERCA, GA SRS, INL/Idaho Nuclear Tech. and
Eng. Center NAC, STS, INL ANL, INL
6
Lessons Learned Overview
  • Purpose To benefit future conversion and project
    teams
  • Conversion Activities were scored 1 to 5 on
    performance difficulty
  • 1 (extremely challenging) / 5 (exceptional easy)
  • Activity Grouping
  • Project Initiation
  • Conversion Proposal to the NRC
  • Fuel Fabrication and Hardware
  • Core Conversion
  • Spent Nuclear Fuel
  • Issues and Recommendations

7
Lessons Learned Project Initiation
  • Average Score 3.9
  • Issues
  • University felt that the Conversion Project Team
    was sometimes segregated and was not certain that
    all necessary information was shared
    appropriately
  • Was not always clear that the Universitys needs
    were being addressed
  • Recommendations
  • Kick-off meetings involving all of the Conversion
    Project Team
  • Clarify roles and expectations better
  • Determine technical requirements for the
    activities
  • Direct the universities to provide a list of
    individuals that will be reviewing drawings,
    specifications, etc

8
Lessons Learned Conversion Proposal
  • Average Score 3.6
  • Issues
  • Due to the age and history of the reactors,
    changes in designs and equipment are likely
  • Over conservatism in analyses can limit reactor
    operations and make fabrication difficult
  • Recommendations
  • Advise Universities early to recover historical
    documents, drawings, etc
  • Involve ALL parties (e.g. analysis, design,
    fabricators, and university) in ALL conversations
    that will impact them directly/indirectly
  • Involve the NRC in the process as soon as
    possible
  • Observation
  • The NRC discussed their issues and questions with
    Licensee while reviewing the proposals. This
    practice eased the Request for Additional
    Information process.

9
Lessons Learned Fuel Fabrication and Hardware
  • Average Score 3.2
  • Issues
  • Assumptions with regard to design, fit, and
    function proved invalid, requiring correction
  • Trucks arriving at the universities to deliver
    the new LEU fuel were not what was anticipated
  • Unfamiliarity with the shipment process when
    returning empty containers
  • Recommendations
  • Verify existing equipment (drawings dont
    necessarily match existing)
  • Ensure the university and the shipper communicate
    with regard to logistics, restrictions, tools
    needed, etc
  • Make time early in the process to inform the
    university about the requirements for return
    shipment

10
Lessons Learned Core Conversion
  • Average Score 3.4
  • Issues
  • Downtime maintenance created additional schedule
    impacts
  • New hardware had to be re-machined because of
    lack of information
  • Reactivity at intermediate points of loading had
    not been calculated
  • Recommendations
  • Schedule activities that can be performed prior
    to reactor loading as soon as possible
  • Pay close attention to the details of the
    reactors
  • If needed, provide for onsite expertise to
    resolve startup issues and have a detailed
    plan/procedure with a number of hold points

11
Texas AM University Nuclear Science Center
  • TRIGA conversion reactor, 1 megawatt
  • Spent LEU core shipped before conversion
  • Conversion milestone accomplished on 27
    September, 2006
  • Final HEU SNF shipment complete
  • Unirradiated HEU element removed

12
University of Florida Training Reactor
  • Argonaut type reactor, 100 kilowatt
  • Spent core shipped before conversion
  • Conversion milestone accomplished on September
    28, 2006
  • Final partial plate assembly completed in August
    2007

13
Purdue University Reactor
  • LW moderated pool, plate fuel,1,000 watt
  • Spent core to be shipped after conversion
  • Conversion milestone accomplished on September 8,
    2007

14
Our near-term projects are to
  • Convert Washington State University Nuclear
    Radiation Center reactor by Sept 30, 2008
  • Convert Oregon State University TRIGA Reactor by
    Sept 30, 2008
  • Convert University of Wisconsin Nuclear Reactor
    by Sept 30, 2009
  • Convert Neutron Radiography Reactor Facility by
    Sept 30, 2009

15
Washington State University Reactor
  • TRIGA conversion reactor, 1 megawatt
  • Spent core to be shipped after conversion
  • Conversion Proposal submitted to NRC on 8/16/07

16
Oregon State University
  • TRIGA Mark II, 1.1 megawatt
  • Spent core to be shipped after conversion
  • Conversion Proposal to be submitted to NRC 9/30
  • Fuel is being fabricated

17
University of Wisconsin
  • TRIGA conversion reactor, 1 megawatt
  • Conversion Proposal to begin in October 2008

18
Neutron Radiography Reactor Facility
  • TRIGA conversion reactor, 1 megawatt
  • Spent core to be shipped after conversion
  • Safety Analysis work has begun
Write a Comment
User Comments (0)
About PowerShow.com