Title: U.S. Domestic Reactor Conversion Programs
1U.S. Domestic Reactor Conversion Programs
- Eric Woolstenhulme
- Dana Meyer
2007 TRTR Conference
September 2007
2Background on the current U.S. Domestic
Conversion Program at the INL
- Support the National Nuclear Security
Administrations Global Threat Reduction
Initiative to reduce the amount HEU by converting
7 U.S. research and training reactors from
HEU-to-LEU fuel by 2009
3The Conversion Generally Includes
- Revision of the facilities Safety Documents and
supporting analysis - Fabrication of new LEU fuel
- Change-out of the reactor core
- Removal of the used HEU fuel (by INL University
Fuels Program)
4Three major Reactor Conversion Program milestones
have been accomplished since 2006
- The conversion of the TRIGA reactor at Texas AM
University Nuclear Science Center - The conversion of the University of Florida
Training Reactor - The conversion of the Purdue University Reactor
5The major entities involved are
- U.S. Nuclear Regulatory Commission
- University reactor department
- Fuel and hardware fabricators
- Spent fuel receipt facilities
- SNF shipping services
- U.S. Department of Energy and their subcontractors
various branches reactor operations, radiation
protection, shipping, procurement, and etc
BWXT, CERCA, GA SRS, INL/Idaho Nuclear Tech. and
Eng. Center NAC, STS, INL ANL, INL
6Lessons Learned Overview
- Purpose To benefit future conversion and project
teams - Conversion Activities were scored 1 to 5 on
performance difficulty - 1 (extremely challenging) / 5 (exceptional easy)
- Activity Grouping
- Project Initiation
- Conversion Proposal to the NRC
- Fuel Fabrication and Hardware
- Core Conversion
- Spent Nuclear Fuel
- Issues and Recommendations
7Lessons Learned Project Initiation
- Average Score 3.9
- Issues
- University felt that the Conversion Project Team
was sometimes segregated and was not certain that
all necessary information was shared
appropriately - Was not always clear that the Universitys needs
were being addressed - Recommendations
- Kick-off meetings involving all of the Conversion
Project Team - Clarify roles and expectations better
- Determine technical requirements for the
activities - Direct the universities to provide a list of
individuals that will be reviewing drawings,
specifications, etc
8Lessons Learned Conversion Proposal
- Average Score 3.6
- Issues
- Due to the age and history of the reactors,
changes in designs and equipment are likely - Over conservatism in analyses can limit reactor
operations and make fabrication difficult - Recommendations
- Advise Universities early to recover historical
documents, drawings, etc - Involve ALL parties (e.g. analysis, design,
fabricators, and university) in ALL conversations
that will impact them directly/indirectly - Involve the NRC in the process as soon as
possible - Observation
- The NRC discussed their issues and questions with
Licensee while reviewing the proposals. This
practice eased the Request for Additional
Information process.
9Lessons Learned Fuel Fabrication and Hardware
- Average Score 3.2
- Issues
- Assumptions with regard to design, fit, and
function proved invalid, requiring correction - Trucks arriving at the universities to deliver
the new LEU fuel were not what was anticipated - Unfamiliarity with the shipment process when
returning empty containers - Recommendations
- Verify existing equipment (drawings dont
necessarily match existing) - Ensure the university and the shipper communicate
with regard to logistics, restrictions, tools
needed, etc - Make time early in the process to inform the
university about the requirements for return
shipment
10Lessons Learned Core Conversion
- Average Score 3.4
- Issues
- Downtime maintenance created additional schedule
impacts - New hardware had to be re-machined because of
lack of information - Reactivity at intermediate points of loading had
not been calculated - Recommendations
- Schedule activities that can be performed prior
to reactor loading as soon as possible - Pay close attention to the details of the
reactors - If needed, provide for onsite expertise to
resolve startup issues and have a detailed
plan/procedure with a number of hold points
11Texas AM University Nuclear Science Center
- TRIGA conversion reactor, 1 megawatt
- Spent LEU core shipped before conversion
- Conversion milestone accomplished on 27
September, 2006 - Final HEU SNF shipment complete
- Unirradiated HEU element removed
12University of Florida Training Reactor
- Argonaut type reactor, 100 kilowatt
- Spent core shipped before conversion
- Conversion milestone accomplished on September
28, 2006 - Final partial plate assembly completed in August
2007
13Purdue University Reactor
- LW moderated pool, plate fuel,1,000 watt
- Spent core to be shipped after conversion
- Conversion milestone accomplished on September 8,
2007
14Our near-term projects are to
- Convert Washington State University Nuclear
Radiation Center reactor by Sept 30, 2008 - Convert Oregon State University TRIGA Reactor by
Sept 30, 2008 - Convert University of Wisconsin Nuclear Reactor
by Sept 30, 2009 - Convert Neutron Radiography Reactor Facility by
Sept 30, 2009
15Washington State University Reactor
- TRIGA conversion reactor, 1 megawatt
- Spent core to be shipped after conversion
- Conversion Proposal submitted to NRC on 8/16/07
16Oregon State University
- TRIGA Mark II, 1.1 megawatt
- Spent core to be shipped after conversion
- Conversion Proposal to be submitted to NRC 9/30
- Fuel is being fabricated
17University of Wisconsin
- TRIGA conversion reactor, 1 megawatt
- Conversion Proposal to begin in October 2008
18Neutron Radiography Reactor Facility
- TRIGA conversion reactor, 1 megawatt
- Spent core to be shipped after conversion
- Safety Analysis work has begun