Title: Ingen bildrubrik
1BALTREL Conference Towards a common Electricity
Market in the Baltic Sea Region Helsinki,
September 2002
Transmission Grid Issues BALTREL WG2
Electricity Systems Integration Results of the
works
Frank Berger, WG2 Chairman, Vattenfall Europe
Transmission GmbH Robert Paprocki, WG2 Vice
Chairman, PSE S.A.
2WG2 Presentation Agenda
I. Scope of the WG2 Work II. The BALTREL
Reference Grid Code III. Future Development of
the Grid within BSR IV. Financing of New
Transmission Infrastructure IV. Summarising
Aspects V. Further Steps of Work
3BALTREL Study Projects
Study Project 1 - Common Rules for Electricity
Trade Study Project 2 - Joint Implementation and
other appropriate environmental matters Study
Project 3 - Gas and Electricity
Integration Study Project 4 - Network
development aspectsof a Common Electricity
Market Study Project 5 - Operational network
aspects of a Common Electricity Market.
4Network Development Aspects
Initial scope of work
- Collection, analysis and comparison of already
existing grid codes in Baltic Sea Region - Elaboration of a list of planned interconnection
links and links under construction - Creation of a BALTREL Grid Code for development
aspects - Elaboration of a digital grid map of the BALTREL
grid regarding the existing maps of the three
involved interconnected systems
5Operational Network Aspects
Initial scope of work
- Transfer of the knowledge between the countries
to get a mutual understanding of the present
similarities and differences in operational rules
within Baltic Sea Region - Identification of those operational rules, which
are indispensable for creating a Common
Electricity Market in Baltic Sea Region - Agreement on common operational rules necessary
for efficient processing of transmission service
requests and reliable operation of systems in
order to support the development of a Common
Electricity Market conditions.
6The Organisation of WG2 work
BALTREL COMMITTEE
Working Group 1 Common Market and Supply
Working Group 2 Electricity Systems Integration
Data Analysis Team
TF 1.1 Common rules for trade
TF 1.2 Joint Implementation
TF 1.3 Gas and electricity integration
TF 2.2 Operational network aspects
TF 2.1 Development network aspects
7The Objective of WG2 Work
- The increasing complexity of interconnected power
- systems and the increasing volume of power
exchange - make the need for common planning standards,
- operating rules and trading rules more and more
urgent. - Since the liberalization in power sector there
are - no longer long term contracts in place.
- The load flow is much more volatile than in the
past. - The objective of WG2 is harmonization and
development - of a minimum set of common Baltrel Grid rules in
order - to enhance transmission system reliability while
supporting - introduction of a common electricity market in
the BSR, - where three different synchronous areas exist.
8Three Synchronous Areas in the BSR
Capacity 90 GW Peak load 60 GW Consumption 400
TWh Population 20 mln
NORDEL
Capacity 85 GW Peak load 60 GW Consumption 400
TWh Population 65 mln
Capacity 310 GW Peak load 180
GW Consumption 1200TWh Population 280 mln
UPS/IPS
ATSOI
UKTSOA
Capacity 510 GW Peak load 340 GW Consumption
2150 TWh Population 400 mln
UCTE
HVDC cables HVDC B2B stations HVAC
radial/island operation HVAC interconnectors
9BALTREL Reference Grid Code
- Three parts
- Operating Rules (TF 2.2)
- Planning Rules (TF 2.1)
- Glossary of Terms (TF 2.1 TF 2.2)
10BALTREL Reference Grid Code
- Main development steps
- collection of existing grid codes,
- identification of items relevant to the
international - co-operation,
- discussion of the terms (need for Glossary of
Terms), - comparison of technical rules,
- selection of justified items to be covered in
RGC, - elaboration of technical regulation,
- feedback from the industry,
- implementation non binding status, reference
document.
11BALTREL RGC Operating Rules
- Issues covered
- balance control,
- transmission,
- cross border exchange,
- system co-ordination,
- emergency operations,
- operation planning,
- telecommunications,
- metering,
- operator personnel and training.
12BALTREL RGC Operating Rules
- Document structure
- Part one explanatory memorandum
- - background information describing document
objectives basic assumptions and
explaining / commenting proposed rules, - Part two operating rules
- - containing specific rules in the form similar
to NERC Operating Manual (basic principles,
requirements, guides), - - nine chapters corresponding with mentioned
categories.
13BALTREL RGC Planning Rules
- Document structure
- main part
- - detailed comparison of different solutions
applied in grid codes of involved synchronous
areas (NORDEL, UCTE, Baltic, UPS) as well as - NERC, UK and DVG,
- - recommendations for BALTREL countries,
- annexes
- - further detailed description of some issues,
- - list of major transmission projects planned and
discussed within Baltic Sea Region, - - digital map of transmission network within BSR.
14BALTREL RGC Planning Rules
- Issues covered
- demand forecasting and scenario setting,
- congestion management (planning perspective,
long time), - network security,
- voltage and reactive power control,
- requirements for power plants (ancillary
services), - further development of Baltic Ring Network,
- exchange of information between TSOs in BSR.
- Cross border tariffication and operational (short
time) congestion management not covered in RGC as
they have rather organisational and economical
character (being worked out by ETSO).
15BALTREL RGC Glossary of Terms
- alphabetical list of terms and their definitions
- - all terms relevant to power system operation
and planning, - content based on
- - European glossaries (UCTE, ETSO, NGC, EU),
- - American glossaries (NERC, ERCOT, FERC, WEPEX,
NARUC, IMO, CALPX), - - Australian glossaries (NEC).
16BALTREL RGC Document Status
- due to existing differences between solutions in
the three synchronous areas and individual
countries direct implementation impossible at
this stage, - non binding reference document,
- framework of reference technical rules,
- aimed at facilitating the operation and
development of transmission infrastructure needed
for the market, - important step towards development of BSR common
electricity market.
17The Future Development of BSR grid
- Limited capacity between the
- three AC systems
- Congestion occurs also within
- synchronous areas/countries
- Short term solution
- congestion management (WG1)
- Long term solution
- increasing NTCs (investments)
- During the work on RGC the
- list of 15 major transmission
- projects within BALTREL
- area was compiled
- (planned and discussed,
- status end of May 2002)
1200
NORDEL
110
UPS/IPS
2550
80
0
3000
UCTE
HVDC cables HVDC B2B stations HVAC island
operation
18List of Planned and Discussed Projects
12
13
1. PL-RU 400 kV AC B2B 600 MW 2. PL-LT
400 kV AC B2B 600 MW 3. PL-BY 400 kV AC
radial operation 4. PL-SK 400 kV AC 5. PL-D
PST 6. PL-D 400 kV AC 7. DK-DK
HVDC 600 MW 8. D-N HVDC 600 MW 9.
DK-DK 400 kV AC 10. S-N 400 kV AC 350
MW 11. S-N 300 kV AC 120 MW 12. RU-N
330/132 kV AC B2B 250 MW 13. RU-FIN 330/400 kV
AC B2B 500 MW 14. RU-FIN 330/400 kV AC 400 MW
15. FIN-EST HVDCLight 315 MW expected
commissioning in the end of 2002
11
14
15
10
9
8
7
2
1
6
3
5
4
19Projects on UCTE UPS/IPS Interface
Kruonis
TBD
Kaliningrad
53 km
600 MW
Alytus
100 km
600 MW
154 km
152 km
TBD EBRD feasibility study 2002
Elblag
Elk
115 km
Matki
Narew
Berezowska power plant
(up to 800 MW)
240 km
Beloozerska
120 km
150 km
TBD option B2B in Ross (up to 1000 MW) ?
Podlaska
Siedlce/ Milosna
115 km
400 kV AC line 330 kV AC line HVDC B2B
station power plant in radial operation
Lublin
20Projects within UCTE
21Projects on UCTE NORDEL Interface
400 kV AC line 400 kV HVDC submarine cable
Sirdal
commissioning 2004
Aalborg
580 km Viking Cable 600 MW
117 km
Aarhus
Fraugde
Herslev
TBD
60 km Great Belt Cable 600 MW
postponed
Brunsbuttel
22Projects within NORDEL
commissioning 2002
Jarpstrommen
Nea
70 km
(thermal upgrade 120 MW)
Borgvik
400 kV AC line 300 kV AC line
Hasle
100 km
(thermal upgrade 350 MW)
commissioned 2001
23Projects on NORDEL UPS/IPS Interface
TBD
Kirkenes
200 km
Kola
250 MW
175 km
TBD
400 kV AC line 330 kV AC line 132 kV line HVDC
Light submarine cable HVDC B2B station power
plant in radial operation
500 MW
Pirttikoski
115 km
commissioning 2002
122 km
Vyborg
Kymi
130 km
?
North West TPP (400 MW)
100 km 315 MW
Veskimets
TBD
24The Need for Financing Mechanism
The mechanism facilitating the financing of
construction of new links should be worked out
- free trade may lead to new patterns of physical
flows thus calling for new transmission
lines - stable incomes as a basis for
financing cannot be guaranteed under market
conditions (e.g. no more long term contracts)
- in the deregulated environment transmission
infrastructure serves all market players
(highways of power) - funds collected by
TSOs in the process of congestion management
could be a potential source of finances
25Possible Solutions
In principle three ways for financing the
necessary investments in transmission
infrastructure can be identified 1. By the TSOs
acting as representatives for the whole
electricity market - normal way with highest
priority. 2. By investors who are interested in
using the connection - this is in conflict
with the basic principles of open markets. 3. By
public funding - for exceptional cases with high
social-economic but lowly economic benefits.
26Recommended Solution
TSOs acting as representatives of all electricity
market players should be responsible for new
investments under the following conditions -
the investments should reflect market needs
(e.g. relieving congestions, improving
reliability) - the electricity market must
send clear signals - TSOs should be allowed
to recover costs from network users
(congestion management, tariffs) - all
beneficiaries of new links should bear the costs
- it is proposed that the EU should minimise
the risk of economically difficult
interconnected projects (with low
forecasted returns)
27Summarising Aspects of WG2 Work
- The Baltrel RGC is a comparison of some grid
codes - existing around the world (NERC, UK and DVG).
- The compared grid codes are mainly dealing with
co-operation - of different electricity system within
synchronous areas. - In the future the Baltrel RGC could be the basis
for developing - a List of binding Requirements for joint
operation of power - systems in the BSR (asynchronous maybe
synchronous). - A close co-operation between TSOs and their
co-operating - organisations is advantageous and therefore
recommended.
28Further Steps of Work
A general political dialog and support between
the countries involved is necessary for
developing a common electricity market and
infrastructure.
There is a continuing need for economic
support, e.g. European wide funds.
- There is a need for profound analysis regarding
- Development of the three synchronous areas
- Well-functioning congestion management
- Cross-border tariffs and transmission costs
- Financing of new transmission infrastructure
- Harmonizing of rules and equipment.