About This Presentation
Title:

Instructions for Completing the Supplier Verification of Purchased Product Package

Description:

When completing fields for notes, be as specific as possible. ... 17 The supplier is responsible for completing these columns with either 'Y' or 'N' ... – PowerPoint PPT presentation

Number of Views:56
Avg rating:3.0/5.0
Slides: 17
Provided by: thadros
Category:

less

Transcript and Presenter's Notes

Title: Instructions for Completing the Supplier Verification of Purchased Product Package


1
Instructions for Completing the Supplier
Verification of Purchased ProductPackage
2
What does SVPP consist of?
3
When is SVPP Required?
  • New Product
  • Engineering Change
  • New revision level
  • Part number change, etc.
  • Process Change
  • Change of equipment.
  • Change of sub-tier supplier.
  • Tooling / Die / Mold change.
  • Manufacturing Location Change
  • As suporting documentation for
  • To document relevant MDA (Material Deviation)
    information.
  • To verify the part after an MDA has expired.
  • To document Corrective Action results /
    information.
  • Other changes to part or process????

4
Submitting the SVPP Report
  • Any discrepancies MUST be communicated prior to
    sending the SVPP report.
  • If a discrepant SVPP Report is sent without prior
    approval, an MRN will be generated for the lot
    and will affect the suppliers quality report.
  • SVPP reports must be submitted separately to each
    Climate Control facility.
  • Only the Quality Manager (or designated
    representative) at the receiving facility may
    waive this requirement. If the requirement is
    waived, a copy of another facilities SVPP may be
    submitted. Please note, this option is for
    special cases only and should not be requested
    for each submittal.

5
How to Complete the PAR Form
  • The supplier completes 1 - 7 with the
    appropriate information. The grayed areas are
    completed by Climate Control upon receipt of SVPP
    Package.

6
How to Complete the PAR Form
  • 8 The Symbol field is used for reference symbols
    as appropriate.
  • It is used to allow the actual dimension to
    remain numeric, therefore enabling the automatic
    calculations used in other portions of the
    document.
  • Symbols may be used other than those shown.

7
How to Complete the PAR Form
  • 9 10 Whenever possible, use only numeric
    values in these columns.
  • Under normal conditions, do not add units of
    measure (mm, in, etc.) here. Again, this enables
    automatic calculations. In the case of
    documenting notes, please be as specific and
    detailed as possible.

8
How to Complete the PAR Form
  • 11 Following the numeric format wherever
    possible, enter the measured or observed values
    for the actual samples.
  • When completing fields for notes, be as specific
    as possible. In most cases OK will not be
    accepted.
  • Note the Green and Red formatting. This is used
    as an aid to identifying out of spec conditions.
    However, the supplier remains responsible for
    identifying in-spec and out-of-spec conditions.
  • This is automatic when purely numeric values are
    used and when the nominal and tolerance values
    are completed correctly.
  • In the case where non-numeric values are used,
    the format defaults back to black. This is OK.

9
How to Complete the PAR Form
  • 17 The supplier is responsible for completing
    these columns with either Y or N.
  • If numeric data is used properly, this column
    should complete automatically. For notes and
    other non-numerical data, VALUE! or similar
    may appear. If so, manual completion is
    necessary.
  • If the data does not meet the specifications, the
    supplier must initiate communication with Climate
    Control to determine the next action.on results.
  • The extent that these fields are completed are at
    the discretion of the receiving plant.

10
How to Complete the PAR Form
Questions????
11
Examples of Completed FormsSheetmetal Assembly
Example
Example of a top level sheetmetal assembly. (As
Purchased)
12
Examples of Completed FormsSheetmetal Assembly
Example
The SVPP requirements would cascade as shown
here.
13
Examples of Completed FormsSheetmetal Assembly
Example
14
Examples of Completed FormsSheetmetal Assembly
Example
15
Examples of Completed FormsCable Assembly Example
16
Questions????
  • Contact
  • Supply Chain Support
  • supplychainsupport_at_irco.com