1
IRIS Project Update
  • IRIS Steering Committee
  • November 29, 2005

2
Todays Agenda
  • FI Update and General Ledger Report Approach
    (Austin)
  • HR Update and HR Organizational
    Structure (Bliffen)
  •  
  • MM Update Hospital Go Live (Stevens)
  • CM Update (Nordin)
  • Training Update, Class Cancellations (Sage) 
  • Upgrade Status (Nelson)   
  • Conclusion (Nash)

3
Financial (FI) Update
  • Tasks recently completed
  • GO LIVE FINANCIALS

4
Financial (FI) Update
  • Issues with Go-live
  • Completion of month end closing
  • Interfaces
  • Indirect Cost
  • Ledger replacements
  • BW reporting
  • Formats
  • Distribution
  • Training
  • Reporting (lack there-of)

5
Financial (FI) Update
  • Tasks currently being worked on
  • ERP2005 upgrade
  • Faculty Effort
  • Ledgers
  • Indirect Cost

6
Financial (FI) Update
  • Tasks forthcoming
  • Continued Report Development
  • Scheduling of Batch processing
  • Phase II

7
Financial (FI) Update
  • Ledger Replacement Prototype

8
Financial (FI) Update
  • Ledger Replacement Prototype

9
Financial (FI) Update
  • Ledger Replacement Prototype

10
Human Resources/Payroll (HR) Update
  • Work continues in comparison testing on entire
    population.
  • Monthly
  • Cycle II tested 5,970 monthly employees out of
    6,891
  • Net difference 1,036,444.24
  • Cycle III tested 7,182 monthly employees out of
    7,184
  • Net difference 52,032.54
  • Biweekly results are currently being analyzed
    and should be complete by December 2.

11
Human Resources/Payroll (HR) Update
  • Parallel testing on sample population will begin
    on December 7 for biweekly payroll number 11.
  • Close to 100 parallel testers from across campus
  • Current activities
  • Expectations
  • Support during parallel testing
  • Importance of timing of testing
  • Meeting with parallel testers (for review) is
    scheduled for November 29 and November 30.

12
HR Organizational Structure
  • Structural Authorizations
  • Working with Area Security Officers to identify
    roles
  • Looking at the entire organizational structure as
    it relates to
  • Organizational Units
  • Positions
  • People

13
HR Organizational Structure
14
HR Organizational Structure
15
HR Outstanding Issues
  • Data quality issues in HRS
  • Handling of working retirees who are also in
    direct bill
  • Changes to NRA processing requirements
  • Process for employee transfers between payroll
    areas (monthly and biweekly)
  • Retirement plan limits

16
Materials Management
17
Materials Management (MM) Update
  • Procurement
  • Approvers
  • Procurement Card
  • Begin Daily Load of Transactions

18
Materials Management (MM) Update
  • Hospital Inventory
  • Go-Live Date
  • Integration Testing
  • EDI

19
Campus Management (CM) Update
  • Student Accounting
  • Student Administration

20
Title
Training Update Steering Committee 11/29/2005
  • Name

21
End User Maintenance Training Update
  • We continue to train employees on the
    Financial/Materials Management/Student
    Accounting/Business Warehouse courses (currently
    teaching 16 classes per week)
  • Approximately 1500 training events are still
    needed by individuals, yet we are canceling
    classes due to low enrollment
  • We continue to develop UK specific context
    sensitive help and make it available to end users
    via SAP and through the IRIS website

22
End User Future Training Update
  • Hospital Inventory/KMSF 2006 go-live
  • Human Resources Curricula
  • Human Resources Training Client Data Plan

23
Title
Cancellations for IRIS Training
  • Name

24
Cancellation Picture
  • August November 2005
  • 3773 Class Cancellations
  • Results
  • 19,163 hours of lost training opportunities
  • Classes were cancelled or classes were held with
    smaller number of participants

25
All Class Cancellations
26
Cancellation Reasons GU 300
27
Repeat Offenders
  • Employees who have cancelled at least three times
    in one course August November 2005
  • 132 individuals
  • Account for 1267 cancellations

28
Repeat Offenders (gt 3 in any one class)
29
Proposed Actions
  • Keep things as they are and risk the ability to
    train all individuals in the tight time frame for
    the HR go-live or have folks without access when
    we go live
  • Provide an incentive for people who do not cancel
  • Impose some disincentive for people who cancel
  • Impose punishment for repeat offenders
  • What is the threshold?
  • What is the punishment?

30
Upgrade Status
  • Upgrade schedule has been changed from Spring
    2006 to Winter 2005/2006.
  • Upgrade Test Run- Completed 11/11. Second Test
    Run has been eliminated, and installation of the
    Upgrade Test system in in process and scheduled
    for completion by 12/2.
  • Upgrade Testing Troubleshooting 12/5 01/13.
  • Go/No Go Decision 01/16
  • Upgrade of Development, Test, Production 01/16
    01/31

31