Title: Rompre avec le pass
1Contracts FP6
2 PRESENTATION OUTLINE
- Legal Framework
- Participation
- Contract Structure
- Collective Approach
- signature and entry into force
- collective Responsibility
- consortium Agreement
- Provisions of general conditions, special
reference to - financial provisions
3 Legal Framework
EC TREATY
INTERNATIONAL AGREEMENTS
PARTICIPATION AND DISSEMINATION RULES
FRAMEWORK PROGRAMME
CONTRACTS
SPECIFIC PROGRAMMES
GUIDELINES ON EVALUATION AND SELECTION
PROCEDURES
Other relevant EC Regulations FINANCIAL
REGULATION
WORK PROGRAMMES
Calls for proposals
4Guidelines
- Will provide explanations and guidance notes
- Financial guidelines
- Negotiation guidelines
- Consortium agreement guidelines
5Minimum number of participants 1
- At least 3 independent legal
entities established - in 3 different Member States or Associated
States, of which at least 2 in Member States
or Associated Candidate Countries. Must include
only - public bodies responsible for financing or
managing research activities carried out at
national or regional level - other national or regional organisations that
finance or manage such research activities - bodies operating at European level that include
as part of their mission the pan-European
coordination of nationally-funded research.
6Minimum number of participants 2
?Other legal entities such as charities or other
private organisations, which also manage research
programmes that are strategically planned and
executed at national or regional level, may
participate without restriction in addition to
the minimum number of participants. ? 1 single
legal entity for specific support actions
established in 1 Member State or Associated State
7Entities established in other countries and
International organisations
- STRUCTURING REINFORCING PARTS
- Participation
- COUNTRIES WITH CO-OPERATION AGREEMENT under the
Agreements conditions - COUNTRIES WITHOUT CO-OPERATION AGREEMENT if
necessary to carry out the project or if
foressen by the Work Programme or the call - Funding if essential to carry out the project or
if foressen by the Work Programme or the call
8Participation
- New Every legal entity that contributes to the
project (incl. Project Managers) - General Rule Participant contractor
- Every legal entity contributing to a project
must have a contractual link with the Community - Exceptional cases subject to very restrictive
rules - Third parties identified in Annex I
- Subcontractors
-
9Participation
- Third parties identified in Annex I
- In most of the cases they do not participate,
they simply make their resources available to a
contractor, this is not a case of participation
but only a question of eligibility of the cost
of these resources - In exceptional cases participation of
members of entities such as EEIG,UMR, SMEs
Associations - these entities are contractors (EEIG, SMEs
Assoc.) - their members can do some of the work on the
project - contractor and third parties must have a previous
agreement - the third parties, the agreement and the
- tasks must be identified in Annex I
10Participation
- Subcontracting
- Contractors shall ensure that the work to be
performed can be carried out by them. - Exception where it is necessary to
subcontract certain elements of the work, this
should be clearly identified in Annex I. - Minor services may be subcontracted
- which do not represent core elements of the
project - which cannot be directly assumed by contractors
- where necessary for the performance of
- the project
11Coordinator
- A contractor among other contractors
- No leadership
- No additional rights
- BUT
- Additional obligations
- Administrative tasks single entry point for
communication, payments, reporting, signature,
amendments, etc. -
12Contract Structure
- Core contract (standard with specifics of
project) - Annex I (technical tasks - the project)
- Annex II General Conditions
- (applicable to every instrument)
- Annex III Instrument specific provisions
(specific to instrument) NON APPLICABLE
FOR SSA AND COORDINATION ACCTIONS
13Contract Structure
- Annex IV - Form A
- Consent of contractors identified in the
contract (article 1.2) to accede to the
contract. - To be signed by the contractor concerned and by
the coordinator. -
- Annex V - Form B
- Accession of new legal entities to the contract.
To be signed by the new contractor concerned
and by the coordinator - Annex VI - Form C
- Financial statement per activity. Specific to
each Instrument and/or type of action. To be - filled periodically by each contractor
14Signature
- Contractual link of all contractors with the
Commission - New Contract enters into force upon signature of
coordinator and Commission - Coordinator must ensure other contractors sign
within delays - All the contractors are identified in the core
contract Art. 1.2
15Entry into force of the contract/start date of
the project
- Entry into force of the contract and payment of
advance - Several options available signature or
coordinator / minimum number of participants/all
participants - Distribution of advance by the coordinator after
minimum requirements met - Project begins in the date established in the
contract (this can be before the contract enters
into force but usually later)
16Amendments
- Core Contract Annex II
- Request in writing
- New at the request of the coordinator, deemed to
act on behalf of the consortium - New Tacit amendments with implicit agreement of
the Commission within 6 weeks only for
modification of the consortium composition
17Consortium agreement
- Regulates internal organisation and management of
consortium - New Compulsory unless otherwise mentioned in the
call for proposal NOT COMPULSORY FOR ERA-NET - Between contractors - NOT signed nor approved by
the Commission - Non binding guidelines provided by the Commission
18NewCollective responsibility
- Technical Responsibility
- Financial Responsibility
- Used as a last resort
- Limited in proportion to the participants share
to the project, up to the total amount they are
entitled to receive - International Organisations, public bodies or
entities guaranteed by MS/AS solely responsible
for their own debts - Exceptions for specific actions for SMEs and
fellowships, and when duly justified for
specific support actions