THE KENYA UGANDA OIL PIPELINE PROJECT - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

THE KENYA UGANDA OIL PIPELINE PROJECT

Description:

MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA ... Ministry prefers location west of the city to lessen truck traffic through city ... – PowerPoint PPT presentation

Number of Views:82
Avg rating:3.0/5.0
Slides: 49
Provided by: Jan9236
Category:

less

Transcript and Presenter's Notes

Title: THE KENYA UGANDA OIL PIPELINE PROJECT


1
THE KENYA UGANDA OIL PIPELINE PROJECT
  • by
  • Ben Twodo
  • MINISTRY OF ENERGY AND MINERAL DEVELOPMENT, UGANDA

2
STRUCTURE
  • Project Inception
  • First Feasibility Study
  • Complementary Study
  • Highlights of the Report
  • Ownership and Management
  • Implementation
  • Conclusion

3
INCEPTION OF THE PROJECT
  • A Memorandum of Understanding (MOU) between Kenya
    and Uganda signed in May 1995
  • A Joint Coordination Commission (JCC) established

4
INCEPTION contd
  • The TOR of the JCC initially to coordinate the
    feasibility study for the pipeline extension.
  • TOR expanded in Oct 2000 to include
    implementation of the entire project.

5
INCEPTION contd
  • Agreed from start that the project be promoted
    and developed as a regional project.

6
THE FIRST FEASIBILITY STUDY
  • The European Investment Bank (EIB) financed the
    first feasibility study.

7
FIRST STUDY contd
  • An international consultancy firm contracted to
    undertake a feasibility study in 1997.
  • The consultant conducted the study in 1998 and
    presented its report in May 1999.

8
FIRST STUDY contd
  • The study concluded that the project is feasible
    and viable.

9
THE SECOND/COMPLENTARY STUDY
  • In 2001, a complementary study was commissioned
    to
  • update the first study and reconfirm the pipeline
    as the least cost mode
  • prepare documentation to invite bids from private
    sector investors

10
COMPLEMENTARY STUDY contd
  • Study financed by the two Governments under the
    auspices of the JCC.
  • Study carried out by another international firm.

11
COMPLEMENTARY STUDY contd
  • Report on Stage 1of the study submitted in Nov
    2001.

12
HIGHLIGHTS OF THE REPORT
  • Market demand
  • Present demand is about 580,000 m3 p.a.
  • Demand grows at 3.5 5 p.a

13
HIGHLIGHTS contd
  • Pipeline route
  • Pipeline to be extended from Eldoret in Kenya,
    through Malaba on the border (110 km), through
    Jinja (130 km from Malaba) then to Kampala (80 km)

14
HIGHLIGHTS contd
  • Total pipeline length approximately 320 km

15
HIGHLIGHTS contd
  • Pipeline size
  • An 8 inch diameter pipeline recommended

16
HIGHLIGHTS contd
  • Pipeline capacity
  • Pumping flow rate of 168 m3 per hour
  • Annual capacity is 1,200,000 m3

17
HIGHLIGHTS contd
  • No engineering design at this stage.

18
KAMPALA TERMINAL
  • A common user terminal to be located in Kampala
  • Terminal to be located east of the city

19
KAMPALA TERMINAL
  • Ministry prefers location west of the city to
    lessen truck traffic through city

20
KAMPALA TERMINAL contd
  • Kampala terminal capacity to be 72,000 m3
    comprising
  • 7 products
  • 4 interface tanks

21
KAMPALA TERMINAL contd
  • Tanks Configuration
  • MPS - 2 tanks - 32,500 m3
  • BIK - 2 tanks - 5,654 m3
  • JET - 2 tanks - 10,544 m3
  • AGO - 2 tanks - 22,570 m3
  • Interface - 4 tanks 904 m3

22
CAPITAL COST ESTIMATES
  • Cost estimates for basic development - 96.9
    million

23
CAPITAL COSTS contd
  • Design, engineering, supervision - 7.2 m
  • Preliminaries and general costs - 5.4 m
  • Pipe laying - 42.2 m
  • Eldoret terminal - 4.6 m

24
CAPITAL COSTS contd
  • Sindendet pump station - 3.4 m
  • Intermediate pump station - 3.4 m
  • Kampala terminal cost - 30.7 m

25
CAPITAL COSTS contd
  • Additional 12 million for
  • Improvement of pumping capacity at Burnt Forest
    in Kenya 5.1 m

26
CAPITAL COSTS contd
  • T-off to governments storage depot in Jinja
    additional facilities - 2.1 m
  • Re-locating terminal west of Kampala - 4.7 m

27
ECONOMICS
  • Current truck transportation rates vary 38 - 42
    per m3

28
ECONOMICS
  • Viability of the project tested for various
    tariffs and investment configurations.
  • The IRR in all cases showed the project to be
    viable 18 - 22

29
GOVERNMENTS POSITION
  • The complementary study report was accepted by
    JCC in 2001
  • The JCC recommended to the two Governments to
    implement the project.

30
GOVERNMENTS POSITION contd
  • Extension to be independent of existing Mombasa
    Eldoret pipeline (owned and managed by GoK
    through the Kenya Pipeline Company).

31
GOVERNMENTS POSITION contd
  • A legal framework be developed immediately by the
    two governments
  • Bilateral/International agreements defining
    legal, commercial, financial arrangements.

32
GOVERNMENTS POSITION contd
  • Host country laws on taxation, transportation,
    customs, etc.
  • Commercial agreements government/company or
    inter company.

33
GOVERNMENTS POSITION contd
  • Engineering design be undertaken parallel to
    identification of private sector investor
  • TOR for consultancy being drafted

34
GOVERNMENTS POSITION contd
  • Environment impact assessment study be carried
    out parallel to identification of private sector
    investor
  • TOR being drafted

35
OWNERSHIP AND MANAGEMENT
  • Ownership to be public-private partnership on boo
    terms
  • Private investor 51
  • Governments 49 (24.5 each)

36
OWNERSHIP MANAGEMENT contd
  • Private sector to manage and operate the pipeline

37
OWNERSHIP/MANAGEMENT contd
  • Governments shares to be offloaded to private
    investors in future
  • The two pipelines to be unified in future and
    operated as a single entity Msa Kla.

38
PROJECT FINANCING
  • Project financing to be used based on future
    stream of revenues.
  • Oil marketing companies willing to sign
    agreements with promoters.

39
WAY FORWARD
  • Prepare documentation to select private partner
    for the project
  • The selection will be through competitive process

40
IMPLEMENTATION TIMETABLE
  • Prepare documentation for bidding - 2 months
  • Open invitation for bidding - 6 months
  • Evaluation, negotiations and contract signing - 6
    months

41
IMPLEMENTATION TIMETABLE
  • Legal framework - 3 months
  • Engineering design - 4 months
  • EIA - 4 months
  • These to run concurrent with investor selection

42
IMPLEMENTATION TIMETABLE
  • Procure, Construction and Commissioning 27 32
    months

43
CONCLUSION
  • The Kenya Uganda oil pipeline project is
    feasible and viable.
  • Ready market exists
  • Attractive rates of return assured.

44
CONCLUSION
  • The project classified as high priority in both
    countries.

45
CONCLUSION contd
  • The project to be implemented as a regional
    project in the spirit of East African Community
    (EAC), the New Partnership for Africa (NEPAD), etc

46
CONCLUSION contd
  • Many financial institutions have indicated
    interest to support the project
  • World Bank Group, EIB, AfDB, PTA Bank, EADB, etc.
  • Bilateral sources and finance houses, etc.

47
CONCLUSION contd
  • A number of investors have expressed interest in
    the project

48
  • COME, LETS DO BUSINESS TOGETHER
  • THANK YOU!
Write a Comment
User Comments (0)
About PowerShow.com