Peaking Generation for Connecticut - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Peaking Generation for Connecticut

Description:

Lack of market response to build peaking assets. ... Strategic Realignment. w/ LT CapEx Program. COS Regime Operations. UI/NRG JV. Strategic Alignment ... – PowerPoint PPT presentation

Number of Views:30
Avg rating:3.0/5.0
Slides: 17
Provided by: ctpo
Category:

less

Transcript and Presenter's Notes

Title: Peaking Generation for Connecticut


1

Peaking Generation for Connecticut
Tony Marone October 14, 2009
2
Background
  • 200?-2007 Insufficient fast start peaking
    generation resources necessary to meet local
    operational requirements (LRFM) of the electric
    system.
  • This shortage resulted in higher customer costs
    and the need to operate older less efficient
    units as peaking resources.
  • Lack of market response to build peaking assets.
  • 2007 Section 50 of Public Act 07-242, An Act
    Concerning Electricity and Energy Efficiency
    directed the CT DPUC to solicit proposals to
    build new peaking generation that would operate
    under a cost-of-service pricing structure.
  • Electric distribution companies and merchant
    generators were allowed to participate in a
    competitive selection process.

3
The Formation of GenConn
Experienced Developer/Generator Existing Sites,
Projects, Permits Completed or Queued
interconnections ISO NE FCA Qualified
Electric Distribution Company Long Relationship
with Policy Makers Strategic Realignment w/ LT
CapEx Program COS Regime Operations
UI/NRG JV Strategic Alignment Regulatory
Compliance Commercial Advantage
4
CT DPUC Process
  • DPUC Rules Docket established bidder and proposal
    requirements along with a long-term contract
    (Cfd) template.
  • Peaking Generation Proposals were submitted to
    the DPUC on 3/3/08.
  • Seven competitors offered thirteen options
  • Over 1800MW offered vs. DPUC claimed need of
    500MW
  • GenConn offered four options ranging from
    200-500MW
  • GenConn was selected to build 400MW of fast start
    peaking
  • GenConn Option 2 (400M) consisting of 187.6MW
    in Devon and 187.6MW in Middletown Ct.
  • Devon COD 6/1/2010
  • Middletown COD 6/1/2011

5
Projects
6
GenConn Project Structure
The United Illuminating Company
NRG Energy, Inc.
50
50
GCE Holdings LLC
LandLease and Shared Facility Agreements
CommercialOperationsContract
ConstructionManagementAgreement
OMContract
Administrative Agreement
100
(Borrower)
Direct
EWGs
GenConn Devon LLC
GenConn Middletown LLC
Engineering Contract
ISO-NE(Revenues)
ProceedsOffset RevenueRequirements
Construction Contract
Cost-of-ServiceContract(Regulated)
CTG and Other Equipment Purchase Agreements
The Connecticut Light and Power Company
Connecticut Ratepayers
7
Cfd Contract
  • Revenue requirements cover fuel, capital costs,
    fixed and variable OM, taxes, financing costs
    and fixed return
  • Projects participate in ISO-NE
  • Shortfall in revenues from market paid to
    projects by CLP excess paid by projects to CLP

Revenue Framework
8
Financing
  • Anticipated Financing (3/08 proposal)
  • A non-recourse permanent financing back-stopped
    by underwritten construction financing at the
    GenConn Energy level.
  • Permanent financing from private placement market
    with back-stop from bank market
  • Term for the debt to match 30-year term of the
    CfD
  • Recourse limited to assets with no requirement of
    parental support beyond equity commitments
  • An actual or implied investment grade rating
    (i.e., Baa3/BBB- or greater) expected based on
    the strong credit profile of the projects with
    30-year CfD supported by rate base
  • An equity bridge loan to fund equity requirements
    during the construction period was proposed
  • The global credit crisis of the fall of 2008
    changed everything!
  • 30-year private placement rates exceeded ROE
  • No underwriting available
  • Very shallow market banks had limited capital
  • Very few willing to lend above 50 million
  • Credit risk must be investment grade
  • Upfront and spreads had approximately doubled
    even for investment grade deals

9
Pro Forma Simplified Lending Structure
10
Construction Strategy Update
  • Strategy
  • Leverage existing infrastructure and skilled
    workforce at brownfield sites.
  • Maximize use of fixed price contracts.
  • Leverage synergies and timing of engineering,
    equipment purchases, and construction between
    Devon and Middletown locations.
  • Maintain project scope, schedule and budget while
    maximizing customer and project benefits.
  • Update
  • 70 of Total Project Costs were fixed prior to
    financing.
  • All major equipment supplied by vendors directly
    contracted by GenConn for both facilities.
  • Barton Malow contracted as General Contractor.
  • NRG Construction is acting as Construction
    Manager, pursuant to Construction Management
    Agreement (CMA).
  • Construction budget and schedule are on track to
    meet contractual obligations and provide customer
    benefits starting 6/1/2010.
  • GenConn preparing file its first rate case with
    CT DPUC in November.

11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
(No Transcript)
16
Questions
Write a Comment
User Comments (0)
About PowerShow.com