Chapters 1 and 2 - PowerPoint PPT Presentation

1 / 30
About This Presentation
Title:

Chapters 1 and 2

Description:

A short history of Human Factors and Ergonomics, ... Approaches for both physical and 'thinking' tasks, A Short History ... No squashing or damaging objects. ... – PowerPoint PPT presentation

Number of Views:38
Avg rating:3.0/5.0
Slides: 31
Provided by: hay45
Category:

less

Transcript and Presenter's Notes

Title: Chapters 1 and 2


1
Chapters 1 and 2
  • Problem Solving Tools for Methods Engineering

2
Our Text Book Website
  • http//highered.mcgraw-hill.com/sites/0072468246/

3
Outline for today
  • A short history of Human Factors and Ergonomics,
  • Methods Engineering/Work Design
  • Example of Methods Engineering
  • Discussion of in-class exercise,
  • Approaches for both physical and thinking
    tasks,

4
A Short History of Human Factors and Ergonomics
5
Methods Engineering
  • Technique for
  • Increasing production per unit of time.
  • Example increasing the number of customers
    that can be handled per cashier by installing bar
    code readers.
  • Decreasing cost per unit output.
  • Example decreasing total cost of each cell
    phone by reducing the number of parts and thus
    the labor hours required for assembly.
  • It is critical to look at impact on whole system.

6
Methods Engineering Focuses Primarily on
improving productivity though (re)design of
Motivation Incentives/rewards
Organizational structure
Work Process
Work operations
Tools (Products)
Work environment
7
Methods Engineering
  • Often used synonymously with
  • Corporate re-engineering
  • Work design
  • Operation analysis
  • The difference between these terms in the level
    of detail.

Big picture level
Detail level
8
Methods Engineering
  • Select project
  • I.D. product or service experiencing
    difficulties.
  • Get and present data
  • Study situation, take measurements to
    determine where difficulties really lie,
  • Analyze the data
  • Figure out which of many problems are most
    critical
  • Develop ideal method(s)
  • Identify alternative approaches which may
    address most critical problems.
  • Present and install method
  • at the work site
  • Develop a job analysis
  • To insure operators are adequately selected,
    trained, rewarded, etc.
  • Establish time standards
  • Establish fair and equitable standards for
    work performance.
  • Follow up the method
  • Take measurements to determine if changes
    really did improve situation as predicted.

9
Example Mission Planning and control for the
Mars Exploration Rover
  • Researchers introduced automated planning tool,
    MAPGEN
  • Tool had to fit with users existing way of
    thinking about plans,
  • Introduction of new tools caused the planning
    process to change,
  • Product and processes were evolved together, over
    time.

10
Many methods can be used in many stages of the
design process
A typical spiral design process
Prototype Testing
Requirements Gathering
Final Performance Evaluation or Comparison
Design Specification
Design Review
11
Problem Solving Tools for Methods Engineering
help to identify what the most important problem
is
  • Observational tools
  • Site walk-thrus
  • Observation and interviews of workers and
    managers
  • Ethnographic studies

12
Problem Solving Tools for Methods Engineering
(Ch. 2.1)
  • Exploratory tools
  • Pareto Analysis (Vilfredo Pareto)
  • Fish Diagrams (from Japan, 60s)
  • Gantt and PERT charts (40s wartime).

13
Pareto Analysis
  • Items of interest are identified (e.g. types of
    product flaws that result in scrapped parts, time
    spent on each activity required to manufacture a
    product or perform a service.
  • Items are measured on a common scale (such as
    frequency total cost, total time, etc.)
  • Items are ordered in descending order

14
Example of a Pareto Chart
15
Fish Diagrams
  • Cause and effect diagrams
  • Effect is a problem fish head
  • Causes fish bones
  • Typical causes
  • Environment
  • Methods
  • Materials
  • Administrative
  • Machine
  • Human

16
Gantt Charts
  • Activities shown as bars with
  • Anticipated start times
  • Anticipated completion times
  • Actual start and completion times
  • Use a vertical line to show current time
  • May use color codes to show various things
  • Completed activities (grey)
  • On going activities, on schedule (green)
  • Overdue activities (red)
  • Almost over due activities (yellow)

17
PERT ChartsProgram Review and Evaluation
Technique
  • Project networks
  • Like Gannt charts, PERT charts show activities,
    start and end times
  • Also show variation in activity durations
    optimistic, average, pessimistic,
  • Show dependencies between activities,
  • Can identify a critical path (longest path) that
    constrains minimum completion time of whole
    project,
  • Analyze how crashing activities can shorten
    duration of whole project.

18
Problem Solving Tools (cont.)
  • Recording and Analysis tools
  • Operation Process Chart
  • Flow process chart
  • Flow diagram
  • Worker and Machine Process Charts
  • Gang Process charts
  • Synchronous servicing

19
Operation Process Charts
  • Chronological sequence of operations
  • Show operations as a flow chart though the
    worksite.
  • Show the types of operations
  • Operation
  • Transport
  • Inspection
  • Delay
  • Storage
  • Decision

20
Operation Process Chart Manufacture of a
telephone stand
21
Flow Process Chart
  • More detail than Operation Process Chart
  • Not usually used for entire assemblies,
  • Used for just one component (or operator)
  • Add in information on
  • Operation duration (time to complete)
  • Distance traveled (for transport operations)
  • Good for showing savings of a new method.

22
Flow Diagram
  • Show layout of work area
  • Show the flow of work through that area
  • Show congestion areas, crossing worker paths,
    total travel.
  • Identify how layout can be redesigned to reduce
    travel, motion, collisions, etc.
  • Store materials near where they are used.
  • Increase efficiency and safety.

23
Worker and Machine Process Chart
  • Show one worker, many processes
  • Identify idle time for each,
  • Reorganize operations to reduce idle time.
  • Identify how many machines worker can manage

24
Gang Process Charts
  • Show one machine, many workers,
  • Identify idle time for each,
  • Re-arrange tasks between workers to reduce idle
    time.

25
Tools for Time and Motion Studies
  • Tools can be simple and low cost
  • Stop watch,
  • Pen and paper,
  • Maybe a video camera. The task determines if it
    is necessary.
  • The technique is low-tech, but can still result
    in major cost savings!

26
Common themes in Human Factors approaches
  • Observation of human activities in performance of
    tasks,
  • Re-engineer many aspects of the task (tools,
    process, etc.) to improve effectiveness
  • The tools and techniques are often simple but
    powerful!

27
In-Class Exercise
  • Each group will be given a set of objects to
    assemble into a box.
  • The items will be varied in
  • shape
  • size,
  • flexibility,

28
In-Class Exercise
  • Figure out how to fit all the objects in the box
  • Decide what actions constitute therbligs or
    elements
  • Develop and record a procedure (in terms of
    therbligs)
  • Figure out how to do it fast
  • Time your procedure (minutes, seconds)
  • Did your therblig descriptions change?
  • Did your procedure descriptions change?
  • Did other things change?

29
Rules of Exercise
  • Take all objects out and set them separately on
    desk.
  • Fit all objects in the box so that you can close
    the lid all the way.
  • No squashing or damaging objects.
  • You may wish to assign different roles to the
    people on your team packer, time keeper, process
    recorder, observer, etc.
  • You will get several minutes to practice, then we
    will have a competition.

30
Exercise (continued)
  • Each group please report
  • Your best time to complete the task
  • Your therbligs
  • Your procedure (sequence of therbligs)
  • What you did to improve your time? (did you
    develop new therbligs? New sequence? Other?)
Write a Comment
User Comments (0)
About PowerShow.com