Title: AJJ Engineering and Consulting
1AJJ Engineering and Consulting
Leo Burnett High Rise Structural Design Project
- Team Members Clients
- Justin Schueler John Peronto
- Joseph Schmidt Christopher Erwin
- Annika Liem
2Site Location
35 West Wacker Drive Downtown Chicago, IL
3Overview
- 48 Story Office Building about 650 feet tall
- Code Guideline International Building Code 2006
(IBC) - ASCE 7
- AISC 13 Ed.
- Completed Tasks
- Building Frame System Analysis
- Wind, Seismic, Gravity Load Analysis
- Beam and Column Design
- 3-D Building Model (Revit Structure 2008
- Core Wall Design and Structural Analysis (SAP
2000) - Connection Detailing
- Foundation Design
- Creation of Complete Set of Structural Drawings
4Building System
- Systems Reviewed
- -Pure Steel Moment Frame
- -Braced Frame
- -Tube System
- -Core Wall
- System Selected
- -Concrete Core wall with Steel Moment Frame
- -Provides solid core protection of stairs,
elevators, and mechanical units - -Provides open interior space free of large
columns, and provides open exterior bays. - -Maximized rental space and quality for future
owner.
5Gravity Loads
- Floor-by-Floor Loading Cases per Architectural
Drawings
6Wind and Seismic Analysis
- Wind Load Analysis Exposure C, proximity to
Lake Michigan, Followed ASCE Code Procedures
based on variables - Seismic Load Analysis Structure Weight, Soil
Type Hard Clay , Followed ASCE Code Procedures,
typically south of central Wisconsin-seismic
controls
7Beam and Girder Design
- Used LRFD method
- Applied factored per square foot loadings
- Designs controlled by deflection limitation of
L/360 - Selected Members
- -Girders
- W21x50 Office
- W21x68 Lobby/Entrance Floor/ Retail
- W30x99 Mechanical Area
- -Beams
- W12x16 Office/Lobby/Entrance/Retail
- W14x30 Mechanical
8Composite Beam Design and Floor Selection
- Used LRFD method
- Applied factored per square foot loadings
- Designs controlled by deflection limitation of
L/360 - Used Vulcraft 1.5VLR17 (4 Total Concrete Slab on
metal deck) - Design
- -Beams
- W10x12 Office/Lobby/Entrance/Retail W12x16
- W12x30 Mechanical W14x30
- NOTE Non-Composite sizing used for conservative
design
9Column Design
- Use LRFD Method
- Effective Length Factor 1.0
- Tributary Area Loading
- Axial Load Capacity Met
- Selected Members
- -Columns
- W14x61 (floors 33 48)
- W14x120 (floors 14 32)
- W14x159 (floors 1-12)
10Connections
- 3 Types of Connections
- Steel Wide Flange Girders To Reinforced Concrete
Core Wall (Embedded Plate) - Steel Wide Flange Girders to Steel Wide Flange
Columns (Full Moment Restrained
Connection) - Steel Wide Flange Beams to Steel Wide Flange
Girders - (Simple Shear)
Typical Office Floor Corner Beam and Girder
Framing
11Embedded Plate
- Steel Wide Flange Girders Connecting to
Reinforced Concrete Core Walls
12Full Moment Restrained
- Steel Wide Flange Girders to Steel Wide Flange
Columns
13Simple Shear
- Steel Wide Flange Beams to Steel Wide Flange
Girders
14Foundation Design
- Geotechnical Firm Recommendations
- Reinforced Concrete Belled Pier
- Grade Beams
15Concrete Core Wall
- Preliminary Design
- -cantilever beam analysis
- -resolved wind and earthquake
- loading values
- -determined moment of inertia
- to meet deflection limit of H/600
- Sizing
16Core Wall Reinforcement
- Rectangular Analysis
- Treat core wall as box
- Neglect door openings
- Cantilever beam analysis
- I-Beam Analysis
- Initial Approach
- Core Wall acts as a single unit
17Core Wall Reinforcement
- Designed as a beam column
- Core wall must resist gravity and lateral loads
- Area of Steel Required
- Designed on a per foot basis
- ACI 318-05 Code for Vertical and Horizontal
Reinforcement - Vertical 0.0015Ag
- Horizontal steel was sized based on the shear
strength of the concrete - Vertical Reinforcing Steel
- No. 5 bars _at_ 12 O.C.
- Horizontal Reinforcing Steel
- No. 4 bars _at_ 18 O.C.
- Use of an Interaction Diagram
183-D Building Model
- AutoDesk Revit Structure 2008
19SAP 2000 Model
- Old Model
- Global grid is based on Architectural Drawings
- 4 created I-Beams connected by link beams
- Each flange consist of one shell element
- Issues
- Connections between individual items
- Proper functioning as one unit
20SAP 2000 Model Updates
- Refined upper floors
- Complete remodel of flange sections and link
beams - Each flange consisting of 4 shell elements
- Model functions as one unit when loading applied
to nodes
Yellow Flanges of I-Beam Green Link
Beams Pink Concrete Wall Orange - Web
21SAP 2000 Model / Core Wall
Link Beam
22SAP 2000 Model Updates
Loading Scenarios
Case 1
Case 2
Case 3
Case 4
Sample Analysis
23Schedule
9/28/07 - Deliverable 1 Lateral and
Gravity Loads 10/26/07 - Deliverable 2
Initial Revit 3-D Model 11/21/07 - Deliverable
3 Beam and Composite Beam
Design 12/7/07 - Deliverable 4
Column Design 1/25/08 - Deliverable 5
Shear Wall Design 3/7/08 - Deliverable 6
SAP 2000 Analysis, Finalize Columns and
Shear Wall 4/4/08 - Deliverable 7
Creation of Detail Sheets 4/25/08 - Deliverable
8 Foundation Design 5/2/08 - Final
24Budget Issues
- Reinforcement Calculations
- 1st Approach Caused Errors
- I-Beam vs. Rectangular Box
- Revit Model
- Constant Model Update
- Building Additional Floors for Plan Sets
- SAP 2000
- Software Use Permission Issue - Waiting Period
- Created Model From Scratch
- Determining Most Realistic Loading
25THANK YOU!