Title: Discussion on Power Tariff in Delhi
1Discussion on Power Tariff in Delhi
energywatch
By Sunder Lal
Jointly organized by Rajiv Gandhi Institute for
Contemporary Studies (RGCIS) energywatch 6th
May 2003, New Delhi
2Overview of presentation
energywatch
- Regulation of Electricity in India a background
- Budding Period
- Period of fast growth
- Experience Independence till pre-reform period
- Post-reform Period
- Experience Post-reform Period (Delhi)
- Issues Formulation of Electricity Supply Tariff
- Mandate of the Acts (Apex Courts judgment)
- Suggestions for Power Tariff
3Regulation of Electricity in India a background
-I
energywatch
- Budding period ( 1910-1947)
- Regulation by Indian Electricity Act 1910
- Objective
- Licensing of Electricity
- Regulations of rates
- Protective clauses
- Important Principles
- Bars undue preference to any consumer
- Advocates Tariff to be based on
- load factor or
- power factor or
- total consumption of energy during any stated
period or - the hours at which the supply of energy is
required
4Regulation of Electricity in India a background
-II
energywatch
- Period of fast growth (1947- upto reforms )
- Regulation by Indian Electricity Act 1910
Electricity (Supply) Act 1948 - Objective
- Industrial development
- advent of grid systems
- Development in semi-urban and rural areas
- Principles
- SEBs formed as autonomous bodies
quasi-commercial to - Control generation, grid systems
- Act as bulk licensees licensees in areas not
served by licensees - Act as they deem fit to formulate tariff
- Given un-guided and arbitrary powers
5Experience Independence till pre-reform period-
I
energywatch
- Achievements
- Generating capacity increased from 1712 MW to
1,04,000 - Gross generation 515 Billion KWh (2000-1)- 4th
largest in world - Transmission lines from 2708 ckm in 1950 to
200,000 ckm - 90 village electrified from a negligible figure
in 1947 - key role in Green Revolution- 63 pump-sets
energized
6Experience Independence till pre-reform period
energywatch
- Failures
- SEBs lost the objective
- never autonomous
- they usurped distributing licensees
- the very aim of cheapening of rates only in
undeveloped areas lost - loss of important sources of revenue
- Arbitrary Tariff formulations influenced by
political considerations - Became Cash starved
- Infrastructure became fragile for want of
overhaul - Alarmed legislators amended Supply Act in 1978
and 1983 - SEBs and the Electricity Sector as a whole
became unviable
7Post-reform Period- I
energywatch
- Electricity Regulatory Commissions Act, 1998
- State Electricity Regulatory Commission
established to regulate determine Tariff based
on - consumers interests
- efficiency
- economic use of resources
- performance
- optimum investment
8Post-reform Period- II
energywatch
- Delhi Reforms Act 2000
- DERC established
- DVB unbundled into
- Generation Transmission ( Transco)
- Distribution (BSES Tata with other licensees)
- Tariff to be determined by DERC on new principles
9Experience Post-reform Period (Delhi)
energywatch
- Old wine in new bottle
- Change reflected neither in tariff nor in
functioning of DVB/ DISCOMS - Irrelevant and obsolete provisions that
encouraged corruption and theft continued - Sanction of load ( e.g. requirement of MCD
Licence) - Misuse charges
- Connected Load
- Change from LT to HT
- Normative Charges
- Minimum Charges
- Surcharge
- Billing demand
- Categorization of consumers (Commercial,
residential etc) violative of Reform Act
10Issues Formulation of Electricity Supply Tariff
- I
energywatch
- Characteristics of Electricity
- To be generated as used
- Cant be stored
- Peak demand provisions
- Cost (Running cost Standing cost)
- Hopkins Principle
- Load factor/ Power factor/ manner quantum of
consumption
11Issues Tariff formulation of Electricity - II
energywatch
- Two part Tariff
- Block Rate Tariff
- Flat Rate Tariff
- Power Factor Tariff
- KVA Max. Demand
- Sliding Scale Power Factor Tariff
- KWH and KVArh/ KVAhTariff
12Mandate of the Acts (Apex Courts judgment)
energywatch
- No discrimination among consumers No cross
subsidization - Tariff formulation is duty of Regulatory
Commission - Return on investment to be weighed against
efficiency parameters - While formulating Tariff Commissions should take
into account that Central and State ERCs - Commission is not bound by the accounts submitted
by utilities - Utilities to also bear for inefficiency
- Losses cant be transferred entirely to consumers
- Watch consumer interests
13Suggestions for Power Tariff - I
energywatch
- Premise
- Because
- The Act bars differentiation on use of
electricity supply - Pattern of use changed dramatically Present
categorization no more based on specified
electrical characteristics - Continuous measurement of electrical
characteristics possible cause of Electronic
meters Especially by govt. bodies or SEBs - Choice of Consumer to either purchase or hire
from utility - Generating companies have adopted Availability
Based Tariff
14Suggestions for Power Tariff - II
energywatch
- Suggestions for Power Tariff - II
- Need to develop tariff
- which automatically works out different rates
- for different characteristics specified in Act
irrespective of the present categories. - fulfills the requirement of the Law
- encourages consumers towards better management of
their use of energy - improve efficiency of the system.
15Thank you
energywatch
- You are welcome
- to see details of energywatchs response on
- ARRs of DISCOMS and
- suggestions forwarded to DERC on Tariff
- at http//www.energywatch.org.in