Title: SECURING COAL SUPPLY THROUGH INDIGENOUS AND FOREIGN SOURCES
1SECURING COAL SUPPLY THROUGH INDIGENOUS AND
FOREIGN SOURCES
- T.K. Chatterjee
- E.D.(FM),NTPC
2Basic Coal Facts
- Countries Fall under distinct categories due to
uneven distribution of coal resources - TierI Countries Self Sufficient or better
North America Russia - Tier- II Countries Prime Exporter Australia,
Indonesia Colombia - Tier-III Countries Facing possible shortfall
from indigenous supply India China - Tier-IV Countries Facing possible shortfall of
imported Coal Japan, Korea and much of Europe
3World Coal ScenarioTop Ten Hard Coal Producers
in the World in 2007
Source BP, IEA,WEC
4Coal in World Electricity Generation
Source BP,IEA,WEC
5GLOBAL PRIMARY ENERGY SUPPLY AND TOTAL WORLD
ELECTRICITY GENERATION BY FUEL
Source BP,IEA,WEC
6Coal Reserves in India(as on 01-01-08) Billion
tonnes
Source MOC
7RAW COAL PRODUCTION IN INDIA
- Growth of coal production is 6.0 whereas demand
for electricity has been growing at an average
growth rate of 7 to 8 and demand supply gap has
widened over the years.
8Existing Generating Capacity- Sept, 2009
Fuel wise break-up (MW)
(All figures provisional from
CEA) FOR NTPC COAL BASED-24395MW
GAS BASED 3955 MW
9COAL REQUIRMENT, AVALIABILITY DURING XI PLAN FOR
POWER SECTOR SourceCEA Presentation made on
30.09.09 in the Fuel Infrastructure Meeting under
the Chairmanship of Member(Energy)
10Vision 2017 and beyond..2030
NTPC GROWTH STRATEGY
INSTALLED CAPACITY
MULTI-PRONGED GROWTH STRATEGY
- MULTI PRONGED APPROACH TO CAPACITY ADDITION
- GREENFIELD PROJECTS
- BROWNFIELD EXPANSION
- JOINT VENTURES
- ACQUISITIONS
- DIVERSIFICATION IN RELATED BUSINESS AREAS
- HYDRO PROJECTS
- COAL MINING
- POWER TRADING
- OIL / GAS EXPLORATION
- LNG VALUE CHAIN
- RENEWABLE
- NUCLEAR
11Vision 2017 and beyond..2030
NTPCs Vision By 2017
A 75,000 MW Integrated Power Company by the year
2017
11
12COAL SUPPLY TO NTPC STATIONS
The graph shows an ever increasing demand for
more coal as NTPC kept on building additional
generation capacity over the years
13In the current year, coal shortage of 20 million
tes is envisaged which NTPC plans to bridge
through import
14Areas of Concern in Eastern Region-I Shortfall
mitigation at Farakka Kahalgaon
- The import supplement required for Farakka
Kahalgaon is 6 million tonnes. The domestic coal
availability for Farakka Kahalgaon is 15
million tes on the basis of assurance of CIL. - As blending of imported coal with domestic coal
cannot be increased beyond 15, we need to
mandatorily tie up 6 million tons of domestic
coal from CIL. Coal production and evacuation
arrangements to be expedited at Chuperbhita and
Hurra C. - The import requirement would then be reduced to 3
million tonnes.
15 Areas of Concern in Eastern Region-I
- Railway bottle necks for Farakka and Kahalgaon
- Railways are ensuring supply of 10 rakes/day but
Andal-Saithia and Sahibganj -Kahalgaon single
line route is congested. - Less Availability of BOBR rakes is also a concern.
16Eastern Region-I Enablers for Coal sufficiency
at Farakka Kahalgaon
- Coal can be transported through Inland waterway
no-1 i.e Ganga passes through Farakka, Kahalgaon
and Barh where NTPCs 03 super thermal stations
are located. The receiving port for imported coal
can be Haldia. - Feasibility of receiving imported coal via IWT is
being studied - Availability of more Railway rakes_at_10 rakes a day
as per their assurance. - Augmentation of existing unloading infrastructure
at Farakka to handle 8 railway rakes a day. - 9 to 10 rakes a day of Total coal on offer from
Lalmatia to be supplied to Kahalgaon. - Augmentation of unloading arrangements at
Kahalgaon-II to handle 9-10 rakes a day. - Continue Supplying imported coal at Kahalgaon and
Farakka - Early Coal Availability from Captive Block of
Pakri Barwadih - Early availability of coal from Brahmini mines
17Areas of Concern in Eastern Region-II Shortfall
mitigation at Talcher Kaniha
- Expeditious development of Kaniha mines and MGR
link to Kaniha wharf wall. - Railways to assure supply of 7 rakes a day on
sustained basis. - Sustained supply of 35,000 TPD from Lingaraj mine
by MCL. - Augmentation of present MGR network to facilitate
Additional number of Railway and MGR Rakes - Improvement of Surface miner availability/reliabil
ity from 1 to 3 numbers. - Supply of Imported Coal to continue.
- Inland water transport route to be explored.
18Fuel Tie up Status for XI Plan projects
- Fuel has been tied up for all projects envisaged
to come up in the 11th plan except Farakka-III,
Mauda U2 and VSTPP-IV - Railway movement clearance has been obtained for
all 11th plan projects except Vallur-II,VSTPP-IV
and Muzaffarpur which is awaited.
19Coal Requirement for 11th plan projects
20Coal Requirement for 12th plan projects
21Projected Coal deficit (Gap) for Existing and
projects coming up in 11th and 12th planin the
terminal year 2016-17
The Deficit coal requirement is planned to be met
through captive mining of coal blocks allotted
to NTPC and import Substitution
22Reasons for Coal shortage
23Coal availability scenario for NTPC
- Out of expected coal based capacity addition of
about 30,000 MW by 2016-17, about 19, 000 MW
will be on linkage mode and balance 11,000 MW on
integrated mode. - The total coal shortage for power sector is
expected to be about 87 million tes by 2016-17
FUTURE SCENARIO
24Reasons for coal shortage
- The long term linkage for NTPC stations
correspond to 85-90 PLF level whereas the
generation target is at 92 PLF. - Growth in the coal sector not commensurate with
nations requirement of 8 GDP growth.
25Reasons for coal shortage
- Slow clearance of projects. In some cases linked
mines are yet to be developed even though the
power projects have been implemented on schedule.
This is resulting into under utilization of
installed capacity. - Ad hoc coal supply arrangements incurring
additional expenditure. - Further burdening of already burdened Rly
transportation network.
26Reasons for coal shortage
- More focus on open cast mining coal quality
takes a hit. - Inferior quality increases coal requirement.
- A huge loss for long distance consumers to
transport waste. - Affects the power plant equipment enhancing
maintenance cost.
QUALITY
27Reasons for coal shortage
Logistic Constraints
- Coal reserves are generally localized.
- Transportation of coal is an issue.
- Judicious rationalization of coal supply not done
due to various political and other reasons.
28Long term Measures to mitigate coal shortage
- Backward integration into coal mining.
- Resorting to integrated power project with
captive coal source concept. - NTPC is contemplating acquiring assets abroad as
a measure of long term fuel security and to beat
the current volatility in the coal prices in the
international market.
29Strategies forCoal Sourcing
30MEDIUM TERM
IMMEDIATE
LONG TERM
DEVELOP CAPTIVE MINING BLOCKS ON FAST TRACK MODE
INLAND WATER TRANSPORT
FUEL SUPPLY AGREEMENT
MINING OF POTENTIAL COAL BLOCKS THRU JV ROUTE
WITH CIL
DEDICATED FREIGHT CORRIDOR
IMPORT
PARTICIPATE IN PORT DEVELOPMENT
ACQUISION OF COAL BLOCKS ABROAD
E-AUCTION
SETTING UP COAL WASHERIES
Bi-Lateral Arrangement over And above ACQ
31Fuel Supply Agreement
- As per NCDP, power utilities to be supplied 100
of the normative coal requirement with FSA.
(Normative requirement not frozen so far). - NTPC has already signed a Model Fuel supply
agreement with Coal India Limited for 90 coal
requirement for existing stations of NTPC. The
process of signing of FSAs for individual
stations is in progress.
32IMPORT(FIG IN Million Tonnes)
NTPC is partially mitigating its
domestic coal shortage for existing stations by
importing coal through third parties and the
percentage of import coal is Increasing every
year. In the current Financial year NTPC planned
to import 12.5 Million Tonnes
33E-AUCTION
- PROCURE COAL THROUGH
- E-AUCTION FOR ALL NTPC STATIONS AS HAS BEEN DONE
IN CASE RSTPS FROM SCCL. - AS PER NCDP, ALL COAL COMPANIES UNDER CIL SHALL
SELL 10 OF THEIR COAL PRODUCTION THROUGH
E-AUCTION. - THE QUANTITIES (MT) PROJECTED BY CIL FOR SALE
THROUGH E-AUCTION ARE - ECL BCCL CCL NCL WCL SECL MCL
NEC CIL - 08-09 3.1 2.65 4.7 6.125 4.3
9.6 9.9 0.12 40.5 - 09-10 3.2 2.8 4.9 6.65
4.5 10.6 11.13 0.12 43.9 - 10-11 4.5 2.85 6.2 6.8
4.45 10.63 12.2 0.3 47.93 - 11-12 4.6 3.0 7.8 7.0
4.5 11.1 13.7 0.35 52.05 - Source CIL
- LOBBY FOR MORE COAL SUPPLIES DURING MONSOON
SEASON WHEN GRAIN MOVEMENT BY RAILWAYS IS LESS
AND MORE RAILWAY RAKES ARE AVAILABLE IN ORDER TO
BUILD UP COAL STOCKS. - EVEN IF WE PROCURE 20 OF THE E-AUCTION QUANTITY
EACH YEAR, THE QUANTITIES (MT) WORK OUT TO BE -
08-09 09-10 10-11 11-12 - _at_ 20 of E-Auction Qty 8.1 8.78 9.56
10.41 - (Million Tonnes)
34Coal security-Augmentation of unloading
- NTPC has already started Augmentation of
unloading infrastructure like Wagon Tipplers at
pithead stations for absorbing more IR rakes. - This would enable the stations to absorb more
coal through railway system.
35NTPC Captive Mining BlocksBackward Integration
Production from Captive mines not likely to
commence in the near future
36ACQUISITION OF COAL BLOCKS ABROAD
- Participate in acquisition of coal blocks in
prospective countries like Indonesia, Mozambique,
Australia. - Leverage government support for tie up with
interested host country for expeditious
acquisition and development of mines and
development of transportation logistics at the
exporting country. - This could be a long term Fuel security measure
and shall also help to partially offset the
volatility of coal prices in the international
market.
37DEDICATED RAILWAY FREIGHT CORRIDOR
- Has potential to meet long term Requirement.
38Mitigating Coal Shortage The Way Forward
- Stepping up domestic coal production by
allotting blocks to central and state public
sector units and for captive mines to notified
end users -
- Coal Import needs creation of necessary
infrastructure. Will also put pressure on
domestic coal industry to be efficient. NTPC has
imported about 5.43 Mt of coal in 2008-09 and is
targeting to import more than 12.5 Mt of imported
coal during 2009-10. - Amendment in Coal Mines Act to facilitate (a)
private participation in coal mining for purposes
other than those specified and (b) offering of
future coal blocks to potential entrepreneurs. - Technology for economic exploitation of coal
lying at greater depths
39MAJOR CONSTRAINTS IN IMPORT
-
- Two major constraints in the import of coal
apart from Supply constraints in the
international coal market are - Port infrastructure
- Railway infrastructure
- .
40AREAS OF CONCERN
- As per indications, the port development
projects/plans would fall short of required
capacity addition to handle thermal coal imports
of 100 MMTPA. - These projects are not mapped and positioned
against Geographical demand centres. Most port
development projects are along the east coast of
India and very few on the west coast - No visible plan of Indian Railways in place to
cater to the excess cargo to be handled by these
ports except the dedicated freight corridor
which in all likelihood would not come before
2017. - Plans to expand the railway network to connect
these ports to inland destinations do not also
seem to be in place. - Source CII
41Fuel Security Thinking beyond
- For a utility as large as NTPC, it is imperative
that we align ourselves completely with the fuel
business in line with the Vision of becoming a
fully integrated company by 2017. - Take fuel as a business.
- Enter partial/ full Coal value chain.
- Formation of a new subsidiary to handle fuel
business with complete autonomy to source fuel.
42