Title: Beams Division Startup Schedule


1
Beams DivisionStartup Schedule
  • Operating under the following
  • Fermilab establishes a goal of achieving 36x36
    stores by March 31, and the Beams Division
    creates a schedule that reflects this goal.
  • The accelerator schedule during the month of
    March will be under the control of the Beams
    Division and will reflect those activities that
    lead to the above goal.
  • Perform studies in orderly fashion and establish
    good working points for all machines
  • Assumptions
  • No major component failures
  • Some overhead for average downtimes and
    required accesses
  • No planned accesses or down days
  • Exception ComEd Kautz Road Substation outage
    (schedule under our control, 21 Mar?)

2
Beams DivisionStartup Schedule
  • Pbar Stacking Startup
  • 2 weeks of necessary tasks
  • Debuncher Cooling Phasing
  • Accumulator Cooling Phasing
  • 1.5 weeks of desired studies
  • AP1 magnet moves and alignment
  • Stacking and transfer tuneup
  • Overlaps with Recycler tunnel work
  • Evenings/owls only
  • Start 23 Feb

3
Beams DivisionStartup Schedule
  • Tevatron Startup
  • Appears can still have Tev cold by 1 Mar
  • Need to have 1 day of safety system testing
    (probably before 1 Mar -- need to make up
    interlocks by 28 Feb)
  • Magnet Power supply tests (may have partial
    access to halls) - 2 days
  • Commissioning of Central orbit - 3 weeks
  • Commissioning of Helical orbits - 2 weeks

4
Beams DivisionStartup Schedule
  • Pbar injectors ready for transfers
  • 19 March
  • Tevatron central orbit ready for 1x8 stores
  • 24 March
  • Allow for 3 days of 1x8 stores
  • Tevatron helical orbits ready for 36x36 stores
  • 9 April
  • Allow for 7 days of 36x36 stores
  • Access requests 16 April