Title: Current GB SQSS Approach
1Current GB SQSS Approach
- Cornel Brozio
- Scottish Power EnergyNetworks
Workshop 3 Birmingham, 10 January 2008
2This Presentation
- Overview of current SQSS methodology
- Interpretation of Planned Transfer and Required
Transfer - Variations on SQSS approach
- Comparison and Conclusions
3Approach 1 - SQSS Methodology
- Current method with wind AT 0.72
- Section 1.1, Appendix 3
- Different exporting and importing area wind AT
(0.72/0.05) - Section 1.3.1
- Variable wind A-factors
- Section 1.3.2, Appendix 4
4Current SQSS Methodology
1(a) 1
- Transmission boundary capability at ACS peak
- Planned Transfer (Appendix C of SQSS)
- Interconnection Allowance (Appendix D of SQSS)
- Required Capacity PTIA
5Setting up Planned Transfer
1(a) 2
- Ranking Order technique
- Set Plant Margin ? 20
- Assumption is that market will deliver around
20, but many closures are unknown - Plant least likely to run is treated as
non-contributory - Straight Scaling technique
- Scale generation to meet demand
- Scaling proportional to availability at time of
ACS peak
6Ranking Order Example
1(a) 3
For ACS demand of 60GW
Less likely to run
7Wind Equivalent in Ranking Order
1(a) 4
Average P available from equivalent thermal unit
Average P available from wind generation
Wind generation registered capacity
Average availability of a thermal unit (At ? 0.9)
Registered capacity of equivalent thermal unit
Wind generation winter load factor (LWind ? 0.36)
Re 0.4 RWind
8Straight Scaling
1(a) 5
Power output of generator i of type T
Registered capacity
PTi S ? AT ? RTi
Availability at ACS peak
Match generation and demand (Applies to entire
network)
With a plant margin of 20 and AT 1.0, S
0.833
9Availability Factors
1(a) 6
- SQSS does not prescribe AT values
- Thermal and hydro units
- AT 1.0
-
- Wind generation
- AT 0.72
-
10Planned Transfer Example
1(a) 7
?RTi 10000 MW D1 6000 MW G1 8333 MW
AREA 1
PT 2333 MW
AREA 2
? RTi 62000 MW D2 54000 MW G2 51667 MW
System in Planned Transfer condition Total ACS
peak demand 60GW
11Interconnection Allowance
1(a) 8
- Planned Transfer condition set up
- Select boundary, i.e. split system into two parts
- Find IA from the Circle Diagram
- Boundary capability
- PT IA for N-1
- PT ½IA for N-2 or N-D
12Circle Diagram
1(a) 9
13IA Application Example
1(a) 10
Circle diagram x-axis
?RTi 10000 MW D1 6000 MW G1 8333 MW
AREA 1
PT 2333 MW
AREA 2
? RTi 62000 MW D2 54000 MW G2 51667 MW
y-axis 2.1 IA 1260 MW
System in Planned Transfer condition
14What does the IA provide?
- Capacity for a generation shortage in one area to
be met by importing from another area (most of
the time) - N-2 or N-D requirement (PT½IA) can be met for
?95 of actual generation and demand outcomes at
ACS peak, assuming - Enough generation in the exporting area
- No local constraints
15Actual Boundary Transfer
Frequency
Boundary Transfer
Expected boundary transfer at ACS peak
16Variations Considered for Wind
- Keep PTIA and PT½IA at same percentile of
possible boundary transfers - Probabilities of exceeding N-1 or N-2
capabilities remain broadly constant - Variations considered
- Approach 1(b) Different wind A-factors for
importing and exporting areas - Approach 1(c) Variable wind A-factors based on
wind volumes in each area
17Different Export and Import Wind A-factors
1(b) 1
- PT½IA captures all but the highest ?5 of
boundary transfers - When imbalance in available power is highest
- Should include imbalance due to wind conditions
- At 60 in PT, support from wind generation in
importing area is over-estimated
18Importing Wind A-factor
1(b) 2
- In exporting area 60 is approximately P90 of
wind output - Mirror exporting area by using P10 of wind
generator power output - About 4 of rated capacity
- AT 0.05 (around 0.05 ? 0.833 0.04 in PT)
- Approach 1(b)
- Different (but constant) A-factors
- Exporting area AT 0.72 for wind (?60 in PT)
- Importing area AT 0.05 for wind (?4 in PT)
19Approach 1(c) Variable Wind A-factors
- Aims to find A-factors as functions of relative
wind generation volumes for any boundary - Monte-Carlo simulation to find distribution of
transfers and find P99 and P95 - Using SQSS approach for same boundary, adjust
wind A-factors until - PTIA (N-1) matches P99 and
- PT½IA (N-2) matches P95
- with minimum error.
20Exporting Area Wind A-Factor
1(c) 2
21Importing Area Wind A-Factor
1(c) 3
22Results for 2007/8
23Results for 2020/1
24Summary
- Approach 1(a) Single A-factor (0.72)
- Works well, but over-estimates wind contribution
in importing area - Approach 1(b) - Different A-factors (0.72/0.05)
- Extends existing approach
- System security remains broadly constant
- I.e. probability of exceeding N-1 or N-2
capability remains approximately constant - Approach 1(c) - Variable A-factors
- Difficult to find robust A-factor functions
(scatter on graphs) - Additional complexity
- Except high-wind export boundaries, very similar
RT to constant 0.72/0.05
25Drawback - Different PT for each Boundary
- Both variations of SQSS approach mean that PT
becomes boundary dependent - Different A-factors in each area
- Single PT condition no longer exists
- Importing and exporting areas not always clear
- By exchanging A-factors, direction of PT can be
reversed
26Recommendation
- As at present, approach would remain supported by
cost-benefit analysis - If existing SQSS approach is to be retained,
adopt Approach 1(b) - Different (but constant) A-factors in exporting
and importing areas (AT 0.72 or 0.05)