Current GB SQSS Approach - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

Current GB SQSS Approach

Description:

Overview of current SQSS methodology. Interpretation of Planned Transfer and Required Transfer ... In exporting area 60% is approximately P90 of wind output ... – PowerPoint PPT presentation

Number of Views:36
Avg rating:3.0/5.0
Slides: 27
Provided by: ble6
Category:
Tags: sqss | approach | current | p90

less

Transcript and Presenter's Notes

Title: Current GB SQSS Approach


1
Current GB SQSS Approach
  • Cornel Brozio
  • Scottish Power EnergyNetworks

Workshop 3 Birmingham, 10 January 2008
2
This Presentation
  • Overview of current SQSS methodology
  • Interpretation of Planned Transfer and Required
    Transfer
  • Variations on SQSS approach
  • Comparison and Conclusions

3
Approach 1 - SQSS Methodology
  • Current method with wind AT 0.72
  • Section 1.1, Appendix 3
  • Different exporting and importing area wind AT
    (0.72/0.05)
  • Section 1.3.1
  • Variable wind A-factors
  • Section 1.3.2, Appendix 4

4
Current SQSS Methodology
1(a) 1
  • Transmission boundary capability at ACS peak
  • Planned Transfer (Appendix C of SQSS)
  • Interconnection Allowance (Appendix D of SQSS)
  • Required Capacity PTIA

5
Setting up Planned Transfer
1(a) 2
  • Ranking Order technique
  • Set Plant Margin ? 20
  • Assumption is that market will deliver around
    20, but many closures are unknown
  • Plant least likely to run is treated as
    non-contributory
  • Straight Scaling technique
  • Scale generation to meet demand
  • Scaling proportional to availability at time of
    ACS peak

6
Ranking Order Example
1(a) 3
For ACS demand of 60GW
Less likely to run
7
Wind Equivalent in Ranking Order
1(a) 4
Average P available from equivalent thermal unit
Average P available from wind generation
Wind generation registered capacity
Average availability of a thermal unit (At ? 0.9)
Registered capacity of equivalent thermal unit
Wind generation winter load factor (LWind ? 0.36)
Re 0.4 RWind
8
Straight Scaling
1(a) 5
Power output of generator i of type T
Registered capacity
PTi S ? AT ? RTi
Availability at ACS peak
Match generation and demand (Applies to entire
network)
With a plant margin of 20 and AT 1.0, S
0.833
9
Availability Factors
1(a) 6
  • SQSS does not prescribe AT values
  • Thermal and hydro units
  • AT 1.0
  • Wind generation
  • AT 0.72

10
Planned Transfer Example
1(a) 7
?RTi 10000 MW D1 6000 MW G1 8333 MW
AREA 1
PT 2333 MW
AREA 2
? RTi 62000 MW D2 54000 MW G2 51667 MW
System in Planned Transfer condition Total ACS
peak demand 60GW
11
Interconnection Allowance
1(a) 8
  • Planned Transfer condition set up
  • Select boundary, i.e. split system into two parts
  • Find IA from the Circle Diagram
  • Boundary capability
  • PT IA for N-1
  • PT ½IA for N-2 or N-D

12
Circle Diagram
1(a) 9
13
IA Application Example
1(a) 10
Circle diagram x-axis
?RTi 10000 MW D1 6000 MW G1 8333 MW
AREA 1
PT 2333 MW
AREA 2
? RTi 62000 MW D2 54000 MW G2 51667 MW
y-axis 2.1 IA 1260 MW
System in Planned Transfer condition
14
What does the IA provide?
  • Capacity for a generation shortage in one area to
    be met by importing from another area (most of
    the time)
  • N-2 or N-D requirement (PT½IA) can be met for
    ?95 of actual generation and demand outcomes at
    ACS peak, assuming
  • Enough generation in the exporting area
  • No local constraints

15
Actual Boundary Transfer
Frequency
Boundary Transfer
Expected boundary transfer at ACS peak
16
Variations Considered for Wind
  • Keep PTIA and PT½IA at same percentile of
    possible boundary transfers
  • Probabilities of exceeding N-1 or N-2
    capabilities remain broadly constant
  • Variations considered
  • Approach 1(b) Different wind A-factors for
    importing and exporting areas
  • Approach 1(c) Variable wind A-factors based on
    wind volumes in each area

17
Different Export and Import Wind A-factors
1(b) 1
  • PT½IA captures all but the highest ?5 of
    boundary transfers
  • When imbalance in available power is highest
  • Should include imbalance due to wind conditions
  • At 60 in PT, support from wind generation in
    importing area is over-estimated

18
Importing Wind A-factor
1(b) 2
  • In exporting area 60 is approximately P90 of
    wind output
  • Mirror exporting area by using P10 of wind
    generator power output
  • About 4 of rated capacity
  • AT 0.05 (around 0.05 ? 0.833 0.04 in PT)
  • Approach 1(b)
  • Different (but constant) A-factors
  • Exporting area AT 0.72 for wind (?60 in PT)
  • Importing area AT 0.05 for wind (?4 in PT)

19
Approach 1(c) Variable Wind A-factors
  • Aims to find A-factors as functions of relative
    wind generation volumes for any boundary
  • Monte-Carlo simulation to find distribution of
    transfers and find P99 and P95
  • Using SQSS approach for same boundary, adjust
    wind A-factors until
  • PTIA (N-1) matches P99 and
  • PT½IA (N-2) matches P95
  • with minimum error.

20
Exporting Area Wind A-Factor
1(c) 2
21
Importing Area Wind A-Factor
1(c) 3
22
Results for 2007/8
23
Results for 2020/1
24
Summary
  • Approach 1(a) Single A-factor (0.72)
  • Works well, but over-estimates wind contribution
    in importing area
  • Approach 1(b) - Different A-factors (0.72/0.05)
  • Extends existing approach
  • System security remains broadly constant
  • I.e. probability of exceeding N-1 or N-2
    capability remains approximately constant
  • Approach 1(c) - Variable A-factors
  • Difficult to find robust A-factor functions
    (scatter on graphs)
  • Additional complexity
  • Except high-wind export boundaries, very similar
    RT to constant 0.72/0.05

25
Drawback - Different PT for each Boundary
  • Both variations of SQSS approach mean that PT
    becomes boundary dependent
  • Different A-factors in each area
  • Single PT condition no longer exists
  • Importing and exporting areas not always clear
  • By exchanging A-factors, direction of PT can be
    reversed

26
Recommendation
  • As at present, approach would remain supported by
    cost-benefit analysis
  • If existing SQSS approach is to be retained,
    adopt Approach 1(b)
  • Different (but constant) A-factors in exporting
    and importing areas (AT 0.72 or 0.05)
Write a Comment
User Comments (0)
About PowerShow.com