Title: Finance strategic outputs


1
Finance strategic outputs
  • Presented byMr Onesmus AyayaChief Financial
    OfficerDepartment Water Affairs (DWA)18 August
    2009

2
outline
  • Key functional areas
  • Overview of the past key achievements
  • Past challenges facing the branch
  • Key Performance Areas
  • Rationale for selecting the KPAs
  • Funding
  • WTE
  • MEA
  • Monitoring
  • Departmental expenditure trends
  • Departmental indicate 2010 MTEF allocations

3
Key functional areas in the branch
  • Supply Chain and Asset Management
  • Revenue and debtors management
  • Financial Accounting and Reporting
  • Management Accounting
  • Budget and Planning (including expenditure
    management)

4
Overview of past Key achievements
  • The separation of the Departments two accounts,
    namely Main Account and the Water Trading Entity
  • The strengthening of the capacity was also
    realized through the filling of key management
    position to provide effective leadership in
    financial management
  • Verification and valuation of major bulk water
    supply assets
  • Creation of an updated asset register
  • Development of financial management processes and
    policies
  • Implementation of Enterprise Resource Planning
    systems for WTE
  • Verification and valuation of biological assets

5
Past Challenges facing finance
  • Clean audit (financial management and skills)
  • Non-integrated financial systems for MEA
  • Minimal transformation in terms of organisational
    systems and processes
  • Financial governance relationship between
    regions and head office

6
Past Challenges facing finance (cont)
  • Systems that requires proper implementation and
    post implementation refinements long term, user
    requirements (SAP, LOGIS etc)
  • Inadequate capacity (lack of skilled resources)
  • Improperly linked staff to either Main Account or
    Trading Entity
  • Extensive infrastructure assets magnitude,
    spatial distribution/location Auditable assets
    plans needed

7
Wte specific challengesextent of infrastructure
  • 240 schemes
  • 334 dams (34 billion cum storage)
  • 6929 km canals
  • 171 km tunnels
  • 990 km pipelines
  • 56 pump stations 211 MW
  • Other infrastructure
  • 28 wastewater treatment works
  • 34 water treatment works
  • 2581 buildings
  • 3006 measuring facilities (1070 hydro, 1724
    geohydro,212 meteorological stations)
  • Land 795,563 Ha plus 137,264 Ha servitudes

8
WTE CHALLENGES
  • Escalating risk of service failure
  • renewal backlogs are R10 billion and growing
  • infrastructure maintenance is insufficient
  • insufficient funding - price capping and
    exemptions reduce potential income from R4.4
    billion pa (adequate) to actual of R1.8 billion
    pa (completely inadequate)
  • Customer complaints over raw water tariff
    increases
  • Ineffective and inefficient structure of the
    sector as a whole
  • Multiple WTE roles regulator, custodian,
    planner, constructor
  • Organisations technical capacity eroded (even
    if additional funding made available, the WTE
    will need commensurate increase in skills and
    capacity, and improved systems)
  • Less than satisfactory processes for billing,
    collection, budgeting, expenditure control, and
    reporting
  • Less than satisfactory financial and asset
    management systems
  • Negative cash-flow

9
Key Performance Areas
Strategic Goal Strategic objectives
Create a value driven, effective and responsive department Improve financial management
Create a value driven, effective and responsive department Organisational growth and development
10
Rationale for selecting the KPAs
  • Qualified audit reports and opinions of the
    previous financial years
  • Financial management is crucial to the successful
    functioning the org since it relates to how
    resources available to the organisation are used.

11
Main Account Funding specific to financial
Management
Cost element Amount 2009/10 Amount 2010/2011 Amount 2011/2012 Amount 2012/2013
Compensation to employees 63,741 65,783 69,965 73,463
Goods and services 30,714 48,199 53,380 56,049
Payments for capital assets 5,181 7,297 9,095 9,550
Total 99,636 121,278 132,441 139,063
12
Monitoring
  • Review of milestones achieved in the action plan
    formulated to address financial weaknesses
    identified by AG
  • Bi-weekly review of specific projects supported
    by external service providers at dedicated
    steering Committee meetings.
  • In Year monitoring (financial and non financial
    reports)
  • Quarterly reports
  • Financial statements as at 30 September
  • Inputs to the Annual Report

13
DEPARTMENTAL EXPENDITURE TRENDS
Year Actual R000 Budget R000
2004/05 3,776,946 3,823,112
2005/06 3,717,088 3,935,636
2006/07 4,305,650 4,660,303
2007/08 5,385,461 5,862,513
2008/09 6,511,300 7,036,616
Expend
99
94
92
92
93
14
2008-09BUDGET VS Actual Expenditure
Programme 2008/09 Budget R000 2008/09 Actual R000 Under-spending
Administration 682 088 681 758 330
Water resource management 3 499 812 3 001 347 498 465
Water Services 2 348 031 2 341 816 6 215
Forestry 506 685 506 648 37
Total 7 036 616 6 531 569 505 047
15
MAIN ACCOUNT REASON FOR UNDERSPENDING
  • The unspent budget allocation of R505,047 million
    is mainly due to the under expenditures on the De
    Hoop Dam project.
  • The Department requested the National Treasury to
    utilise the funds that could not be spent on this
    project for other projects (Nandoni and Inyaka
    water treatment works and the Hluhluwe regional
    water scheme), but the request was not approved-
    R265m
  • Unpaid invoices as at 31 March 2009 R227m
  • Action taken by the department
  • The Department requested the National Treasury to
    roll-over R272,3 million of the underspending to
    the 2009/10 financial year for the continuation
    of the De Hoop Dam project.

16
Explanation
  • Disbursements of the funds i.r.o De Hoop was not
    made as a result of the delays in the conclusion
    of the negotiations to finalise a memorandum of
    agreement with the 23 different mines.
  • The memorandum records the principles for the
    sharing of the project cost and was essential to
    conclude the negotiations prior to the
    commencements with preparations for project
    implementation.
  • Against this situation, the DWA requested the NT
    for approval to utilised the unspent funds for
    the benefit of other bulk water supply
    infrastructure projects that were nearing
    completion.
  • The necessary approval was not received from the
    National Treasury and consequently these funds
    remained unspent within the Vote while WTE
    continued to implement the relevant bulk water
    services projects using funds meant for recurrent
    expenditure items.
  • Had the approval from NT been received R262,67
    million would have been paid out to the WTE to
    augment the Capex on other bulk water
    infrastructure projects.

17
Challenges identified
95 expenditure trends Possible decline in donor funding Significant portion of the budget that is earmarked
Funding of new programs, projects and structure changes Possible establishment short funding and capacity constraints
Opex and CAPex plans Inflation costs and possible implementation delays Office accommodation costs to be provided for regions
Internal and external coordination of projects Multi-sector programme risks Specialised service delivery consultants possible budget shortfalls
18
2009/10 Earmarked Vs Un- earmarked
19
Exchequer funding earmarked in 2009/10
  • Thus the total amount earmarked for the 2009/10
    financial year for the Department amounts to R3
    170 163 000 for the following purposes
  • Rent of buildings 138 331 000
  • Working for Water 455 724 000
  • Working on Fire 123 608 000
  • Refurbishment of water scheme 30 000 000
  • De Hoop Dam (Phases 2B to 2G) 600 000 000
  • Additional capacity Internal Audit and Finance
    6 000 000
  • Sanitation at school and clinics 350 000 000
  • Regional Bulk infrastructure 611 500 000
  • Operating subsidy (Water Services) 855 000
    000
  • Total earmarked funding 3 170 163 000

20
Changes on 2009 MTEF Baseline
21
Office of the DG2009/10
Chief Directorate Main Appropriated Adjusted Appropriated
Director-General and Personnel 104,235 104,235
Chief Operating Officer 5,032 5,032
Director Corporate Planning 3,878 3,878
CD Internal Auditing 15,649 15,649
Director Transformation 5,679 5,679
DDG Special Programmes 3,000 3,000
DDG Regulations 3,000 3,000
CD Nat Water Resource Infrastructure 4,703 4,703
Total Office of the DG 145,176 145,176
22
Branch Corporate Services 2009/10
Chief Directorate Descriptions Main Appropriation Adjusted appropriation
Office of DDG Corporate Services 5,868 5,868
Chief Information Officer 86,336 86,336
Director Administration 231,256 231,256
Director Legal Services 12,213 12,213
CD Human Capital Solutions 98,416 98,416
Director Gender and Disability 8,747 8,747
CD Communication Services 26,550 26,550
Total Branch Corporate Services 500,518 500,518
23
Branch Finance 2009/10
Chief Directorate Descriptions Main Appropriation Adjusted appropriation
Office of Chief Financial Officer 22,042 22,042
CD Pers Finance 99,636 99,636
Total Branch Finance 121,678 121,678
24
Branch Policy and Regulation 2009/10
Chief Directorate Descriptions Main Appropriation Adjusted appropriation
Office of DDG Policy and Regulation 3,515 3,515
CD Resource Directed Measures 23,000 23,000
CD Institutional Oversight 94,000 94,000
CD Intergrated WR Planning 90,000 90,000
CD Policy and Strategic Coordination 18,822 18,822
CD International Relations 21,178 21,178
CD Information Management 165,000 165,000
CD Water Use and Conversation 248,706 248,706
Total Summary Policy and Regulation 664,221 664,221
25
Branch National Water Resource Infrastructure
2009/10
 Chief Directorate Descriptions  Main Appropriation  Adjusted appropriation
Infrastructure Development and Rehabilitation - Augmentation to WTE 1,989,201 1,989,201
Infrastructure-KOMATI BASIN WATER AUTHORITY (KOBWA) 180,000 180,000
Total 2,169,201 2,169,201
26
Branch Operations Regions (WRM) EXPENDITURE TO
DATE 31 JULY 2009
Chief Directorate Descriptions Main Appropriation  Adjusted appropriation
Office of DDG Operations Regions 8,267 8,267
Eastern Cape Region 137,923 137,923
Western Cape Region 101,906 101,906
KwaZulu Natal Region 72,763 72,763
Mpumalanga Region 63,271 63,271
Gauteng Region 44,173 44,173
North West Region 41,275 41,275
27
Branch Operations Regions (Cont) 2009/10
Free State Region 35,911 35,911
Northern Cape Region 52,293 52,293
Limpopo Region 91,835 91,835
Working For Water - Cape Town Office 272,851 272,851
Regional Support and Co-ordinations 32,275 32,275
Augmentation to WTE - Proto CMA's 107,835 107,835
Total Summary operations regions 1,062,578 1,062,578
28
Branch Operations Regions (WS) EXPENDITURE TO
DATE 31 JULY 2009
Chief Directorate Descriptions Main Appropriation  Adjusted appropriation
Eastern Cape Region 334,110 334,110
Western Cape Region 32,557 32,557
KwaZulu Natal Region 200,737 200,737
Mpumalanga Region 288,943 288,943
Gauteng Region 67,817 67,817
North West Region 156,045 156,045
29
Branch Operations Regions (WS) EXPENDITURE TO
DATE 31 JULY 2009
Free State Region 95,125 95,125
Northern Cape Region 103,792 103,792
Limpopo Region 959,906 959,906
Manager National Transfer 15,990 15,990
Manager Sanitation 86,393 86,393
CD Regional Support and Co-ordination 315,758 315,758
Total Summary operations regions 2,657,173 2,657,173
30
MAIN ACCOUNT 2009 MTEF ALLOCATIONS-
Economic Classification MTEF Estimate MTEF Estimate MTEF Estimate
2009/10 R000 2010/11 R000 2011/12 R000
CoE 1 327 863 1 314 086 1 399 588
Goods and Services 2 113 255 2 902 964 3 318 860
Capital assets 1 114 223 972 685 1 623 420
Total 7 893 827 8 292 925 9 463 127
31
2010-MTEF Allocation New Programme Stricture
2009/10 R000 2010/11 R000 2011/12 R000 2012/13 R000
Administration 805,095 863,798 900,728 945,766
Water Management 345,0777 365,782 387,729 407,115
National W.R. Infrastructure 2,277,036 2,433,360 2,618,057 2,739,959
Regional Management 3,360,935 3,858,721 4,693,521 4,936,092
Water Services 184,716 213,818 241,188 253,247
TOTAL 6,972,859 7,735,479 8,841,223 9,282,179
32
Donor funding (R000)
33
WTE Revenue Vs Expenditure
34
MTEF allocation - WTE
Operational activities Operational activities 2009/10 2010/11 2011/12
Revenue 1,599,784 1,599,784 1,798,403 2,074,410
Raw Water 1,563,784 1,563,784 1,762,403 2,038,410
Sundry Income 36,000 36,000 36,000 36,000
35
MTEF allocation WTE (cont..)
Operation Maintenance costs 1,206,811 1,265,944 1,336,040
Compensation of Employees 340,506 357,191 373,264
Goods Services 588,256 617,081 644,850
Support services 278,048 291,672 317,926
36
MTEF- allocation WTE (cont)
Operating surplus/deficit from core business 392,973 532,458 738,370

CAPEX FUNDED FROM OPERATIONS 392,973 532,458 738,370
Movable assets   - -
Refurbishment 392,973 436,986 485,928
Betterment - 95,472 252,441
37
MTEF allocation WTE (cont)
INFRASTRUCTURE DEVELOPMENT 1,744,913 1,853,806 1,992,036
Support services (Schedule) 416,453 465,934 508,633
Movable assets 104,570 13,480 106,327
Less allocated to operations (278,048) (291,672) (317,926)
Projects direct side support 1,501,938 1,666,064 1,695,001
Funded by Augmentation 1,744,913 1,853,806 1,992,036
38
MTEFallocation WTE (cont)
SUBSIDISED ACTIVITIES
CMA (Proto)
Revenue 184,740 193,792 202,513
Raw Water 184,740 193,792 202,513
Operational Costs 279,332 316,617 349,124
Compensation of Employees 165,455 181,244 194,489
Goods Services 113,877 135,373 154,636
Capital Expenditure - - -
Movable assets   - -
Operating surplus/deficit (94,592) (122,825) (146,611)
Funds by Augumentation 94,592 122,825 146,611
39
  • I thank you