Title: Master Production Scheduling
1Master Production Scheduling
2Master Production Schedule
- A master production schedule (MPS) is a
production plan (anticipated build schedule) for
an individual product, a customer order, or a
product option and common parts - Make-to-stock finished product
- Make-to-order customer order
- Assemble-to-order product option and common parts
3MPC System
4Master Production Scheduling
- Effective MPS provides the basis for
- Making customer delivery promises
- Utilizing plant capacity effectively
- Attaining firms strategic objectives (from
production plan) - Resolving trade-offs between production and
marketing
5MPS Activities
- Operational levelprocessing MPS transactions,
maintaining MPS records and reports, having a
periodic review and update cycle (rolling
through time), responding to exception
conditions, and measuring effectiveness of
schedules - Daily basismarketing and production coordinate
through order promising (shipment date for a
customer order)
6MPS TechniquesTime-Phased Record
- Record (by periods)
- Forecast
- Available projected inventory balance at the end
of the period. available from prior period
MPS forecast - MPS quantity and time of completion of
production - On hand beginning inventory for the first period.
7MPS TechniquesTime-Phased Record
- Strategies
- Leveling MPS constant. Excess inventory to meet
future forecasts - Chase MPS matches forecast. No inventory except
safety stock - Mixed (hybrid) lot-sizing approach that falls
between the two strategies. Inventory for future
periods called cycle stock
8MPS TechniquesRolling through Time
- MPS is periodically updatedchanges in forecast,
orders, production, etc., may require adjustments
for future periods - One pointer would be negative available
balances - A counter-balancing force would be feasibility of
change
9MPS TechniquesOrder Promising
- Available-to-promise deduct existing booked
orders from available inventory. (See Figures
6.8, 6.9, 6.10) - Time-phased MPS record conventionuse the greater
of forecasts or booked orders to calculate
available inventory balance. - Accurate order promising helps a firm to reduce
inventory by using buffer delivery promise dates
instead.
10MPS TechniquesConsuming the Forecast
- Forecast estimates versus actual booked orders.
- Negative Availableneed a MPS lot (if feasible).
- ATP calculated by using only actual orders and
scheduled production. - Use both available and ATP rows for MPS planning
negative available quantities represents a
potential problem, but a negative ATP is a real
problem.
11BOM Structuring for the MPS
- BOMengineering document specifying subordinate
components. - Single-level BOM.
- Indented BOM.
- Assemble-to-order may represent almost unlimited
number of end items (options multiply), leading
to other BOM options for MPS planning.
12Modular Bill of Materials
- Establish the MPS at option or module level. BOM
links options/modules to components but not to
end items. Not Buildable. - MPS can be stated in fewer units.
- Hill-Rom example (p. 231) 160 end item
possibilities, but only 19 time-phased MPS
records needed. - Customer ordera unique end item.
13Planning Bill of Materials
- Planning Bill Created expressly for forecasting
and master scheduling - Unique configuration, not buildable
- Store in BOM file
- Revise with engineering changes
- Phantom Bill A bill for a subassembly whose
components are consumed during the assembly of
its parents
14Super Bill of Materials
- Super bill describes the options or modules that
make up an average end item. - Is used as the MPS unit the plan would be to
build per the average option proportions. - Adds complexity to order entry (ATP logic must be
applied to each option in the order).
15Final Assembly Schedule (FAS)
- States exact set of end products to be produced
over give time period (final assembly lead time). - MPSanticipated build schedule FAS is actual
build schedule. In assemble-to-order MPS stated
in super bills and options, FAS stated in end
items per customer order. - Hill-Rom example, Figures 6.16-6.19.
16Master Production Scheduler (Master Planner)
- Consolidate all sources of requirements
forecasts, customer orders, interplant orders,
service parts orders, etc. - Carefully evaluate MPS changes to see effect on
material and capacity plans. (Resolving competing
demands.) - Issue production and assembly orders.
17Master Production Scheduler (Master Planner)
- Understand trade-offs between customer needs and
MPC system objectives. - Resolve conflict on production requirements among
functions. - Report performance and problems to top management.
18MPS Stability
- Firm planned ordersquantity, timing are set by
the master planner, not adjusted automatically by
the software. - Frozen time periodsno changes in the stated time
periods are possible. - Time fencingspecify periods in which differing
types of changes are possible (e.g., ice, slush,
water zones)
19Managing the MPS and Data Base
- MPS Data Base
- Maintain data integrity
- Define clear functional responsibilities
- Proper control of changes to BOM
- Have a realistic MPS do not overstate the MPS
20Managing the MPS and Data Base
- Stability and proper buffering
- Force the sum of the MPSs to equal the
production plan. - Measures
- Output/period (dollars or units) vs. the MPS or
the budget. - Customer service (hitting order acknowledgement
or promise dates).
21Concluding Principles
- The MPS should reflect the companys approach to
the business environment in which it operates. - The MPS is one part of an MPC systemthe other
parts need to be in place as well for a fully
effective MPS system. - Time-phased MPS records should incorporate useful
features of standard MRP record processing.
22Concluding Principles
- Customer order promising activities must be
closely coupled to the MPS. - Available-to-promise information should be
provided to both the master planner and the sales
department. - A final assembly schedule (FAS) should be used to
convert an anticipated build schedule (MPS) into
an actual build schedule.
23Concluding Principles
- The master planner must keep the sum of the parts
(MPS) equal to the whole (production plan). - The MPS activities must be clearly defined in an
organization. - Firm planned orders can be used in the MPS.
- Stability should be designed into the MPS.
- The MPS should be evaluated with a formal
performance measurement system.
24Chapter 6 Assignments
- Problems 6.4, and 6.12 a b, and 6.14
- Due Tuesday, Sept. 24
- Use Excel to do Problems 6.4 6.14