Title: Wisconsin Height Modernization Program (WI-HMP)
1Wisconsin Height Modernization Program (WI-HMP)
- Improving the Vertical Component of the Geodetic
Network - Colorado Height Modernization Forum
- 1 December 2006
- Paul J. Hartzheim, P.E.
2WI-HMP Early Development
- Wisconsin Height Modernization Program (WI-HMP)
was started by WisDOT in 1998 to improve the
vertical component of Geodetic Control in
Wisconsin - As part of the growing development of WI-HMP, a
Wide Area Global Positioning System (GPS)
Real-Time Kinematic Network is being established.
3Height Modernization Objectives
- Eliminate inconsistencies between horizontal and
vertical control data and supplemental control
where marks have been destroyed or are deemed
unusable - Utilize GPS technology as a cost effective
positioning tool (achieve 2-cm positional
accuracy) - Decrease the cost of surveying required for
transportation related projects - Provide a much more accurate vertical database to
a wide variety of data users throughout the state - Complete initial efforts by 2011
4Example of WI-HMP BenefitState Agency
- WisDOT compared a static GPS survey and
conventional leveling (before WI-HMP) verses a
RTK GPS survey (after WI-HMP) for the
establishment of photogrammetric targets for a
highway improvement project - Horizontal and Vertical (elevations) positions
were all within 2 cm (.07) - Static GPS w/Leveling 280 staff hours
- RTK GPS 30 staff hours
- WI-HMP with RTK provided over a 91 time savings!
5Example of WI-HMP BenefitCounty Agency
- Digital Orthophotography field survey for
accuracy check - A survey was needed by a County to verify 10
horizontal and vertical positions derived from
digital orthos in one 36 square mile township - It was estimated (from past projects) to take 24
hours to perform these checks using conventional
(static GPS, total station, and leveling)
procedures before WI-HMP - With WI-HMP in place, RTK GPS procedures were
utilized to perform these checks in just 4 hours - WI-HMP with RTK provided 61 time savings!
6Funding and Management
- Funding
- State Transportation Funds
- FHWA State Planning Research Funds
- National Oceanic and Atmospheric Administration
(NOAA) - Federal Congressional Earmark Funds - Resource Structure
- DOT Program Manager
- Three Geodetic Specialists (all Project
positions) - Two Limited Term Employees
- Up to 32 consultant staff personnel
7Height Modernization Layout
HARN station Primary Base Network Secondary
Base Network Local Base Network
Existing NGS Level line Decimated NGS Level
line New WI-HMP Level line
8WI-HMP Phases
9Status of WI-HMP
- Phases 1, 2, 3, and 4 Fully Completed (Project
Data Available on NGS Web) - Phase 5 Nearly Completed (Monuments w/ Posts
Installed Survey Complete GPS Data Available on
NGS Web Awaiting Publication of Leveling Data by
NGS) - Phase 6A Underway (Monuments w/Posts Installed
Leveling Completed (Processing Underway) GPS
Primary Survey of Field Observations Completed
(Processing Underway) Secondary and Local GPS
Survey of Field Observations Underway since
August 2006 Scheduled Publication in 2007) - Phase 6B Survey Planned in 2007
- Phase 7A Monuments w/Posts Installed
Descriptions for Marks Completed Survey Planned
in 2007
10Status of WI-HMP
- Phase 7B Monuments Installed Witness Posts
Installation Underway since August 2006 - Phase 7C Reconnaissance Completed
- Phase 8 Reconnaissance of Existing Bench Marks
Completed - Statewide Wisconsin Continuous Operating
Reference Network (WI-CORS-NET) Compiling
existing stand alone base stations developing
planning maps for installation of CORS
researching other established CORS networks
completed pilot test project to determine spacing
requirement of CORS and accuracies
11WI-HMP Mark Maintenance
GPS Stations Orange 4x4 Plastic Guard Posts
- Installed 3 witness posts around each monument
- Established 866 number to report endangered,
damaged, or destroyed monuments - Created the Preservation of Geodetic Survey
Stations Committee
Bench Marks White T Plastic Witness Posts
12Benefits of Wide Area RTK Network
(Implementation of Technology Advancement to
Height Modernization)
- Eliminates the need and cost for another GPS
receiver which acts as a base - Eliminates the resource time associated with
equipment setup at the base site - Greatly enhances consistency of coordinate
determination - Eliminates the need for permanent monumentation
on a local level - Reliability and redundancy is ensured
Hence, WIsconsin Continuously Operating Reference
Stations NETwork (WI-CORS-NET) is Being
Implemented
13Concept of Wide Area RTK Network
- Utilizes network RTK solutions to provide high
accuracy GPS positioning over wide areas - At least four GPS reference stations are needed
- Users connect into system using wireless
connection - Software acknowledges the users field position
and allows them to operate as though there is a
reference station next to the rover - Software uses reference stations to calculate
virtual reference station position for the rover
14Development of Pilot Projectfor WI-CORS-NET
- Goal is to determine spacing requirement of
permanent GPS base stations while achieving 2-cm
three-dimensional positioning accuracy standard - Pilot network consisted of two permanent sites
(Franklin and Watertown) and two temporary sites
(Germantown and Palmyra) - Equipment utilized on the project included a
Trimble GNSS R8 receiver for the rover and
Trimble NetR5 receivers for the bases - Pilot project performed with the cooperation and
assistance from Seiler Instruments
15WI-CORS-NET Pilot Project Configuration
16Construction of Marshfield CORS(Concrete Pillar)
17Construction of Marshfield CORS(Concrete Pillar)
18Construction of Marshfield CORS(Concrete Pillar)
19Construction of Marshfield CORS(Concrete Pillar)
20Construction of Marshfield CORS(Concrete Pillar)
21Concrete Pillar Issues
- Remove 1 ½ PVC conduit and place outside
monument - Redesign antenna mount utilizing stainless steel
shaft
22Palmyra CORS(Building Mount)
23Palmyra CORS(Building Mount)
24Remote Locations of CORS(Alternative Power and
Internet Connections)
USGS Installation - 1999
Hayden Valley instrument enclosure, solar panels,
communications antenna, and battery enclosure.
Monument is barely visible in the distance, near
bottom of channel midway between worker and
instrument enclosure (shoulder level, directly
behind partly buried battery enclosure).
25Coordinate Determination of Pilot CORS
- Need to have temporary Pilot CORS on same datum
and adjustment as WI-HMP, i.e., NAD 83 (1997.0) - GPS survey was performed to tie HARN and WI-HMP
Primary Base Stations to temporary Pilot CORS
sites - Variety of problems with coordinate determination
- Using correct datum and adjustment is vital to
accurate testing
26WI-CORS-NET Pilot Project AreaWI-HMP Marks
27Results of Pilot Project Testing
- Utilized Trimble GNSS R8 receiver with Survey
Controller - Majority of area tested utilized Verizon for
communication link, remaining area used Cingular
as communication provider - 10 second observations collected at each mark
- Results indicate 2 cm accuracy standard in
horizontal and vertical (orthometric height)
components are achievable on a reliable basis
28Sample of Results
29Development of WI-CORS-NET(Funding)
- Received approval on extension and budget
revision for FFY05 NOAA Earmark Grant - Approximately 300,000 would be allocated towards
funding the establishment of nearly 24
WI-CORS-NET sites - Grant expires on 31 May 2007
- Plan is to revise FFY06 NOAA Earmark Grant to
allow funding for completion of initial
installation and more in later 2007
30Development of WI-CORS-NET(Technical)
- Initial plan is to establish 25 permanent CORS
throughout the eastern half of Wisconsin - Permanent sites would have concrete pillar design
- Plan is to incorporate existing single base
station receivers through possible upgrade
replacement - Reconnaissance already underway for location of
monuments - GPS hardware and software would be acquired
through bid process - Determination needs to be made on distribution of
licenses - Determination needs to be made on the
availability of communication services for
transmitting data
31WI-CORS-NETPhase 1 Preliminary Design
32WI-CORS-NETPhase 1 Preliminary Design
33WI-CORS-NETPhase 1 Preliminary Design
34Development of WI-CORS-NET(Management)
- Coordination and management on the development
and implementation of WI-CORS-NET by WisDOT - Assistance being solicited from the stakeholders
(our Regions, public entities, and consultants) - Master information list containing POCs, current
CORS sites, etc. compiled and updated frequently - Development of WI-CORS-NET status report is
on-going - Cooperative agreement finalized, to be
distributed to Partners
35Tentative Implementation Timeline
36Questions/Comments?