ST. CLAIR COUNTY COMMUNITY COLLEGE
General Campus Renovations MONTHLY PROGRESS
REPORT August 2006
2
St. Clair County Community College Monthly
Progress Report
Table of Contents Tab 1 Executive Summary Tab
2 Project Status Report Attachments
3
St. Clair County Community College Monthly
Progress Report
Executive Summary Project Description The CEM
Science Building and College Center Addition and
Renovations includes a 15,000 square foot
addition and major renovations and upgrades to
both buildings. The addition is attached to the
east side of the existing College Center
building. This additional space along with
renovated space within the building will become
the new location for the Learning Resource
Center, currently housed in the CEM Science
Building. Renovations in the CEM Science
Building include new instructional laboratories
for Chemistry, Biology and Physical Science.
Other Math and Science lecture spaces are also
upgraded with the addition of instructor office
space. Renovations to both buildings include
significant upgrades to the current Mechanical
and Electrical systems. Both roof systems will
be replaced along with minor site work to support
the new addition.
Progress to Date College Center Addition
Carpet is scheduled to start August 7, 2006 in
the Open Seating area. Lighting continues in the
Open Seating area. Mobile shelving is currently
being installed. College Center Renovations
Lighitng in the bathrooms in area B continues to
be installed. New pendant lighting has been
installed. RTUs are currently being prepared for
startup. The seating area of the cafeteria is
completed. Terrazzo floor has been ground.
Sitework continues with sidewalks being complete
and site lighting is scheduled for early
August. CEM Building Renovations Fourth floor
terrazzo has been polished. Paint touch ups
continues throughout. Ceiling grid work is nearly
complete. Interior lighting continues to be
installed. Final system start ups begin this
month.
1
4
St. Clair County Community College Monthly
Progress Report
Progress to Date
Painting at the College Center and the CEM
Mobile Shelving Installation at the College Center
RTU Electrical and Duct Connections
2
5
St. Clair County Community College Monthly
Progress Report
Progress to Date
New Sidewalk Preparation and Placement
Sidewalk Installation
Electrical Separation
3
6
St. Clair County Community College Monthly
Progress Report
Progress to Date
Electrical Separation
Carpet at the College Center
Casework at the College Center
4
7
St. Clair County Community College Monthly
Progress Report
Project Schedule Summary CEM Building
Renovations Mechanical and Electrical work
continues throughout the CEM. Paint touch ups
continue throughout. Ceiling grid installation
continues. Interior lighting installation
continues. Ductwork continues at the
CEM. Electrical separation work is complete.
Pipe insulation continues throughout, College
Center Addition and Renovations Terrazzo
flooring has been completed. Ceiling tile
installation continues in the College
Center Electrical components continue to be
installed within the addition. Mobile shelving
has been installed. Sidewalks have been placed.
Painting continues throughout the College
Center. Contractor Construction Progress
Meetings are currently scheduled for 1000AM on
the 2nd and 4th Thursdays of each Month. The
Executive Overview Committee Meetings are
currently scheduled for 230PM on the 2nd and 4th
Thursdays of each Month.
5
8
St. Clair County Community College Monthly
Progress Report
Project Status Report Attachments Current Status
Review The Architectural and Engineering design
is complete. Shop drawings and Request for
Information Forms are currently being submitted
to the A/E for review and approval. All items
are on schedule. Construction progress is
identified on attached construction schedule as
well as following manpower chart. There has been
no safety issues on the project. Contractors
have submitted required safety manuals and MSDS.
These items are located within the College Center
Construction Office.
There are currently no critical issues impacting
the construction project.
6
9
St. Clair County Community College Monthly
Progress Report
7
10
St. Clair County Community College Monthly
Progress Report
8
11
St. Clair County Community College Monthly
Progress Report
9
12
St. Clair County Community College Monthly
Progress Report
10
13
St. Clair County Community College Monthly
Progress Report
11
14
St. Clair County Community College Monthly
Progress Report
12
15
St. Clair County Community College Monthly
Progress Report
13
16
St. Clair County Community College Monthly
Progress Report
14
17
St. Clair County Community College Monthly
Progress Report
15
18
St. Clair County Community College Monthly
Progress Report
16
19
St. Clair County Community College Monthly
Progress Report
17
20
St. Clair County Community College Monthly
Progress Report
18
21
St. Clair County Community College Monthly
Progress Report
19
22
St. Clair County Community College Monthly
Progress Report
20
23
St. Clair County Community College Monthly
Progress Report
21
24
St. Clair County Community College Monthly
Progress Report
22