Accelerator Systems Overview - PowerPoint PPT Presentation

1 / 39
About This Presentation
Title:

Accelerator Systems Overview

Description:

The Project should plan on building and testing a (500MHz) superconducting ... vacuum chamber bake-out iterated and improved, Bi-metal flange in production ... – PowerPoint PPT presentation

Number of Views:77
Avg rating:3.0/5.0
Slides: 40
Provided by: miller64
Category:

less

Transcript and Presenter's Notes

Title: Accelerator Systems Overview


1
Accelerator Systems Overview
F. Willeke, ASD Director 6th ASAC October 22-23,
2009
2
Outline
  • Comments on Charge
  • Responses to last ASAC Meeting
  • Conclusion of the RD Program
  • Development in Overall Accelerator Design
  • Technical Progress of Subsystems
  • Cost and Schedule Performance
  • Organizational Issues
  • Outlook

3
Charge
  • Review AS recent progress near-term plans
    technical, cost, schedule performance
  • ? overview presentation
  • Review the plans for BPM system, comment on
    in-house development regarding technical
    performance, cost, and schedule
  • ? dedicated presentation
  • Review the overall machine protection system and
    the integration of personal protection system,
    beam containment and top-off safety measures
  • ?3 dedicated presentations
  • Comment on the Injection systems including the
    plan for the pulsed magnet facility and the
    procurement strategy for the booster
  • ?Injector presentation
  • Review and comment on the NSLS-II power supply
    systems
  • ?dedicated presentation
  • Review the plans for production, assembly, and
    installation of accelerator systems
  • ? dedicated presentation
  • Review the plans for start-up, test, and
    commissioning of accelerator systems
  • ? Dedicated presentation

4
Response to the Committees Recommendations
Project acknowledges importance of comment, BB
monitor calibration planned to be used,
achievable precision ?2008 tech note Workshop
held, positive feedback This is being done, but
not systematically, so far given our present
solution, overall tune footprint shrinks with
positive xx Prototype would be too costly, not
in budget, vertical cold tests are planned, no
vendor decision yet comment is
acknowledged taken into account in the ongoing
design considerations Aggressive staffing plan
pursued, resources from other labs used (Al
Chamber welding, DW, controls) Magnet procurement
split into 5 packages, sextupole and quadrupole
packages split into 2 similar sub-packages
  • Achievable precision of BPM offset by BBA
    Introduce realistic errors into the orbit and
    optics correction model!
  • In-depth workshop of the storage ring lattice and
    tracking results in the near future
  • Investigate the performance of the Storage Ring
    lattice at higher positive values of vertical
    chromaticity, which are generally required to
    control instabilities!
  • The Project should plan on building and testing a
    (500MHz) superconducting cavity prototype,
    especially if the contract goes to a company that
    has no experience
  • Make an effort to decrease R/Q of the passive
    cavity.
  • Keep focus on rapid staff-up. Look for resources
    at other labs.
  • Give serious consideration to parallel awards and
    easy escape clauses in contracts for magnets,
    to facilitate a shift of scope from one vendor
    (who might not be performing satisfactorily) to
    another

5
Nonlinear Dynamics Review
? Methods and procedures endorsed 3rd chromatic
knob recommended No preference of how to
implement
6
Status Overview
  • Accelerator Systems Design is coming to an
    end
  • - Accelerator Lattice is stable now, do not
    expect significant changes
  • - Design of Injector, SR Magnets, Girder,
    Vacuum Chambers, Utilities completed or far
    advanced Prototypes built and tested
    successfully
  • -Outstanding Designs Power Supplies,
    Insertion Devices, Instrumentation Safety
    Systems, RF cavities (modifications to meet code)
  • Procurement of major systems started
  • SR Magnets orders have been placed
  • LINAC RFP published
  • Vacuum Chambers and components production
    started
  • Booster RFP in preparation
  • Many procurements such components for
    accelerator production and test facilities in
    progress

7
Accelerator Physics
  • Dynamic Aperture Magnetic field specifications
    updated
  • Chromatic corrections improved
    2?3 chromatic sextupole
    families decision made
  • Integration of Damping wigglers improved
    ? acceptable DA with 3 DW
    and up to 10 IVUs, work on EPU
    accommodation started
  • Work on Beam confinement including planned
    experiments, top-off safety study continued
  • Revision of fast orbit correction separated
    function scheme reduces performance risk
  • Impedance calculations pursued, collaborating
    with instrumentation and vacuum on suppression of
    rogue mode, calculations and measurements (review
    held in September)
  • Transv Damper conceptual design filtering (
    Button BPM, locations, detector layout, Digital
    filter layout 9-tapFIR, strip-line kicker)

8
Lattice Functions for One Cell
9
Introduction of a Third Chromatic Knob
Center of Long Straight
Center of Short Straight
Center of Long Straight
  • Symmetry in lattice
  • Reflection symmetry about the center
  • of the straights
  • Reflection symmetry and translation symmetry
    between super-periods
  • Functions of the sextupoles
  • 2 chromatic sextupole families to
  • correct the linear chromaticity
  • 7 geometric sextupoles to compensate
  • the nonlinearity
  • One more chromatic sextupole to
  • correct the nonlinear chromatic
  • effects.

10
Dynamic Aperture with Insertion Devices
Frequency Map Simulation (RADIA kick map used)
basis lattice
with well compensated chromaticity and tune shifts
add IVU and
imperfections
Add DW
Effect of DW is mainly linear Optics
Distortion Can be well integrated (requires 3-f
symmetric installation)
Add EPUs
11
Preliminary Layout of Transverse Damper
12
Injector System
  • The RFP of the 200MeV s-Band Linac will be
    published end of October there are 4 strong
    vendors
  • Booster will be semi turnkey, vendor responsible
    for overall performance, some subsystems
    (controls interfaces, BPM electronics,
    installation labor contributed by BNL)
  • Transfer line design matured
  • Transfer Line magnet design in progress
  • Pulsed Magnets Workshop in August
  • ? Pulsed Sextupole Injection Scheme abandoned,
    baseline 4kicker-bump
  • Pulsed magnet laboratory installed

13
Storage Magnet Systems
Orders have been placed for the industrial
production of NSLS-II Storage Ring Magnets
The 240 68mm aperture quadrupole magnets in 6
variants will be produced by Everson/Tesla and
BINP, orders placed Sept 23 The 68 mm sextupole
magnets will be produced by IHEP and Danfysik,
Orders placed October 16 The 60 large aperture
quadrupoles and the 30 large aperture sextupoles
will be produced by Buckley, orders placed
Oct. The vendor for the 54 35mm aperture and the
6 90mm dipoles has been selected. The 180 100mm
and 156mm hor./vert. correctors will be produced
by Everson Tesla.
14
Girder, Supports and Integration
  • Girder RD and Girder Design Completed
    Manufacturing Drawings being completed
  • The precision alignment procedure is well defined
    by having tested each step in the procedure
  • The RD and the design of the girder system is
    complete, all the critical issues have been
    addressed and solved.
  • Ultimate test After transport, all
    magnets within 5mm aligned
  • Environmental Room equipped and functional
  • The girder integration procedure re-planned only
    one environmental room necessary, final magnet
    adjustment performed manually
  • - optimizes procedure
  • - this will save costs
  • - helps to compensate the enhanced labor
    needed in setting up the production facility and
    performing RD ? dedicated
    presentation

Fully Functional and Equipped Environmental Room
(DT lt 0.1 C ) for 30 mm Precision Alignment
15
Final Demonstration of Feasibility of 30mm
Magnet-to-Magnet Alignment
June 2009
16
Mechanical Systems, Front-Ends
  • Front end design 80 complete
  • Outside-Vacuum prototype of safety shutter built,
    cycle-tested successfully
  • Compressed gas system redesigned and based on
    compressed air
  • DI water systems (5 x CU 5 x AL, RF, Linac,
    Booster, Cryo-Compressors) detailed system
    design, component layout, service building
    equipment room detailed design with 3-D layouts

17
Vacuum Systems
Prototype chamber invar support on girder
  • Vacuum Production Facilities Clean-room for
    assembly prepared, vacuum conditioning lab is
    now fully equipped and tested, vacuum cleaning
    and measurement lab started to operate (late) ,
    brazing oven installed, chemical cleaning
    procurement delayed
  • Vacuum Chamber prototype extrusions successful,
    orders for production of MP extrusions place,
    dipoles will follow soon, dipole chamber bending
    under control, but is considerable effort
    contracts for prototype welding and machining in
    place vacuum chamber bake-out iterated and
    improved, Bi-metal flange in production
  • Collaboration with APS in place for Production
    Chamber Welding
  • NEG Pump Design tested, support system iterated
    and improved, Rogue mode shielding integrated
  • Novel Design for Shielded Bellows, 2nd prototype
    being built
  • Commercial Ion pump comparative test

Dipole chamber bending
New Vacuum Chamber Profile
Novel Design Shielded Bellow Prototype
18
RF Systems
  • Storage Ring SC RF Cavities Nonlinear Stress
    Analysis demonstrates compliance with equivalency
    to pressure vessel code
  • Failure of over-pressured system
    reproduced? benchmarked calculation
  • Procurement documents in preparation
  • ? reviewed by lab safety committee which
    confirms adequacy of the procedure
  • Optimization of Coupling for 500mA
  • LLRF 2nd FPGA based prototype build, still basic
    functionality , under test with Booster 7-cell
    cavity (tuner loop)
  • Booster RF New tuner motors and electronics,
    adaption of input coupler to co-axial waveguide
  • RF Power RF engineer hired,
  • Cryogenic System Cryo engineer on board,
    consultant help to refine valve and pipe
    dimensions, design being wrapped up resulting in
    preliminary specification for first iteration
    with vendor

19
Instrumentation
  • BPM System still major activity
  • RF button first article successfully tested,
    production released
  • Commercially available BPM electronics meets
    demanding NSLS-II requirements (resolution,
    stability 0.1mm)
  • Concerns about obsolete electronics and
    vendor support? in-house development seriously
    considered
  • Efforts on other diagnostic systems started
    Photon BPMs, Fast orbit control, transverse
    damper system, fast orbit control, optical
    monitoring, scraper systems, loss monitors

New 7mm 2-in-1 RF Button First Articles with
Boron Nitride Washers
20
Electrical Systems
  • Main Dipole PS component design and prototype
    testing well advanced, next step is system
    integration
  • MP power supply design meets higher (25 ppm)
    stability standards easily, order for DCCTs have
    been placed
  • New dual corrector power supply in progress
  • Equipment enclosure design completed and power
    test on prototype with PS and heaters completed
  • Detailed cable plans developed, layout of cable
    trays
  • Calibration system for PS DCCT developed

Full Power Test of NSLS-II Sealed Air-Cooled
Power Supply Rack with prototype PSs
AC Power Control Module
Power Converter
DCCT
Low noise regulator prototype for Main DP
switch-mode supply
21
NSLS-II Insertion Devices
49
? Tanabes Presentation
22
Possible NSLS-II DW Production by APS
Damping Wiggler APS provided a preliminary
design, a cost estimate and a schedule. However
APS has difficulties with NSLS-II DW
specifications.
Attractive APS fixed gap NSLS-II DW proposal with
horizontally moving in/out beam position
23
Bldg. 832 3D-Layout
ISO-7 Clean Room for Measurement
ID Lab
Tech Shop
Pulsed Magnet Lab
RF Lab
24
Safety Systems
  • Design of SPPS and EPPS systems well advanced,
    completion end of FY
  • Successful external reviews of the systems
    conducted
  • Engineering prototypes in progress

? Johnsons Presentation
25
Control System
  • High Level Applications
  • -Standard interface for orbit control running
    using existing beam optics dynamics codes
  • -Data Description Service is deployed as
    an interface/complement to basic channel access
    mechanisms.
  • Database IRMIS API for machine lattice entry and
    report is running and integrated into the online
    model environment.
  • Equipment Controls Preliminary design docs for
    vacuum, power supply, diagnostics, RF, Timing,
    EPS/PPS
  • Prototype of Controls for Subsystems started
  • Vacuum, beam line, PPS, beam correlated
    applications, Diagnostics, power supplies, and
    LLRF
  • Network preliminary design of network hardware
    system

26
Accelerator System Budgeted Cost
27
Accelerator Systems Budgeted Costs
28
Registered AS Cost Changes
Note Contingency is owned by Federal Project
Director. Numbers are just used as a measure of
cost increase!
29
Project Cartoon Schedule
30
Schedule
CD4
31
Cost and Schedule Performance
32
Assessment
  • Trend since October 2008
  • Cost variance becoming smaller
  • Schedule Variance becoming negative reaching
    5.8M at the end of FY09
  • Reasons
  • Late hires and Missing MOU Labor 36 FTE ( _at_
    6.0M )
  • Labor augmentation plan 36FTE to recover since
    June, too early to see an effect
  • Should start to see improvement within the next 6
    month
  • There is one remaining EVMS issue Controls has
    worked on activities scheduled to
  • start in FY10? no earned value, self repairing in
    FY10
  • There are real delays Vacuum Chamber 1.5 M
    due to technical issues and procurement or vendor
    problems and slow progress with the vacuum
    facility (recovering now)
  • Slow procurement process with many medium size
    procurements behind schedule
  • ? Additional procurement support added (Liaison
    Engineer AS, more buyers)

33
ASD Shortage of Labor Resources
Causes Late Hires, Resource Leveling, MOU
contributing less than planned
ASD schedule variance at 4/30 associated with
this effect is -4M
FTE
FTE
Difference, Accumulated Difference
FTE
34
Mitigation of Schedule Variances
Goal Stop Growth of SV within 3 months ?
recover the schedule within 24months
Preliminary Plan in Place to satisfy immediate
needs 18FTE, plan to complement by another 18FTE
Additional 18 FTE ? Slow recovery
35
Schedule Recovery
FTE
36
Accelerator Systems Division Staffing
Temporary Labor
Budgeted
Planned
Hired
MOU BNL
37
FY09 AS Hires
  • FY 09 Staffing
  • 11 Controls System Experts
  • 10 Engineers
  • 7 Physicists
  • 11 Technicians and Designers
  • Present staff 103
  • Supported 10 FTE MOU

38
Organization
  • 23 new key staff hired
  • Deputy Division Director assigned E. Johnson
  • Project Engineer hired G. Fries
  • Organization augmented by task forces (FOF, BC)

N
39
Conclusion
  • Design of Accelerator Systems approaches
  • conclusion Magnet, Vacuum Chamber design
  • and prototyping ready for production
  • Accelerator Systems entered the construction
  • phase, major procurements and production
    have
  • started SR Magnets, Vacuum Chambers,
    Production
  • Facilities
  • Negative Schedule Variance has built up is
    mitigated by adding labor to make up for labor
    resources not available the time work was
    scheduled,
  • Focus in the next months will to award
    construction contracts for magnets, vacuum
    chambers, LINAC, booster and support systems
  • Accelerator systems in good shape, no major
    technical issues, schedule under control
Write a Comment
User Comments (0)
About PowerShow.com