Title: Accelerator Systems Overview
1Accelerator Systems Overview
F. Willeke, ASD Director 6th ASAC October 22-23,
2009
2Outline
- Comments on Charge
- Responses to last ASAC Meeting
- Conclusion of the RD Program
- Development in Overall Accelerator Design
- Technical Progress of Subsystems
- Cost and Schedule Performance
- Organizational Issues
- Outlook
3Charge
- Review AS recent progress near-term plans
technical, cost, schedule performance - ? overview presentation
- Review the plans for BPM system, comment on
in-house development regarding technical
performance, cost, and schedule - ? dedicated presentation
- Review the overall machine protection system and
the integration of personal protection system,
beam containment and top-off safety measures - ?3 dedicated presentations
- Comment on the Injection systems including the
plan for the pulsed magnet facility and the
procurement strategy for the booster - ?Injector presentation
- Review and comment on the NSLS-II power supply
systems - ?dedicated presentation
- Review the plans for production, assembly, and
installation of accelerator systems - ? dedicated presentation
- Review the plans for start-up, test, and
commissioning of accelerator systems - ? Dedicated presentation
4Response to the Committees Recommendations
Project acknowledges importance of comment, BB
monitor calibration planned to be used,
achievable precision ?2008 tech note Workshop
held, positive feedback This is being done, but
not systematically, so far given our present
solution, overall tune footprint shrinks with
positive xx Prototype would be too costly, not
in budget, vertical cold tests are planned, no
vendor decision yet comment is
acknowledged taken into account in the ongoing
design considerations Aggressive staffing plan
pursued, resources from other labs used (Al
Chamber welding, DW, controls) Magnet procurement
split into 5 packages, sextupole and quadrupole
packages split into 2 similar sub-packages
- Achievable precision of BPM offset by BBA
Introduce realistic errors into the orbit and
optics correction model! - In-depth workshop of the storage ring lattice and
tracking results in the near future - Investigate the performance of the Storage Ring
lattice at higher positive values of vertical
chromaticity, which are generally required to
control instabilities! - The Project should plan on building and testing a
(500MHz) superconducting cavity prototype,
especially if the contract goes to a company that
has no experience - Make an effort to decrease R/Q of the passive
cavity. - Keep focus on rapid staff-up. Look for resources
at other labs. - Give serious consideration to parallel awards and
easy escape clauses in contracts for magnets,
to facilitate a shift of scope from one vendor
(who might not be performing satisfactorily) to
another
5Nonlinear Dynamics Review
? Methods and procedures endorsed 3rd chromatic
knob recommended No preference of how to
implement
6Status Overview
- Accelerator Systems Design is coming to an
end - - Accelerator Lattice is stable now, do not
expect significant changes - - Design of Injector, SR Magnets, Girder,
Vacuum Chambers, Utilities completed or far
advanced Prototypes built and tested
successfully - -Outstanding Designs Power Supplies,
Insertion Devices, Instrumentation Safety
Systems, RF cavities (modifications to meet code) -
- Procurement of major systems started
- SR Magnets orders have been placed
- LINAC RFP published
- Vacuum Chambers and components production
started - Booster RFP in preparation
- Many procurements such components for
accelerator production and test facilities in
progress -
7Accelerator Physics
- Dynamic Aperture Magnetic field specifications
updated - Chromatic corrections improved
2?3 chromatic sextupole
families decision made - Integration of Damping wigglers improved
? acceptable DA with 3 DW
and up to 10 IVUs, work on EPU
accommodation started - Work on Beam confinement including planned
experiments, top-off safety study continued - Revision of fast orbit correction separated
function scheme reduces performance risk - Impedance calculations pursued, collaborating
with instrumentation and vacuum on suppression of
rogue mode, calculations and measurements (review
held in September) - Transv Damper conceptual design filtering (
Button BPM, locations, detector layout, Digital
filter layout 9-tapFIR, strip-line kicker)
8Lattice Functions for One Cell
9 Introduction of a Third Chromatic Knob
Center of Long Straight
Center of Short Straight
Center of Long Straight
- Symmetry in lattice
- Reflection symmetry about the center
- of the straights
- Reflection symmetry and translation symmetry
between super-periods
- Functions of the sextupoles
- 2 chromatic sextupole families to
- correct the linear chromaticity
- 7 geometric sextupoles to compensate
- the nonlinearity
- One more chromatic sextupole to
- correct the nonlinear chromatic
- effects.
10Dynamic Aperture with Insertion Devices
Frequency Map Simulation (RADIA kick map used)
basis lattice
with well compensated chromaticity and tune shifts
add IVU and
imperfections
Add DW
Effect of DW is mainly linear Optics
Distortion Can be well integrated (requires 3-f
symmetric installation)
Add EPUs
11Preliminary Layout of Transverse Damper
12Injector System
-
- The RFP of the 200MeV s-Band Linac will be
published end of October there are 4 strong
vendors - Booster will be semi turnkey, vendor responsible
for overall performance, some subsystems
(controls interfaces, BPM electronics,
installation labor contributed by BNL) - Transfer line design matured
- Transfer Line magnet design in progress
- Pulsed Magnets Workshop in August
- ? Pulsed Sextupole Injection Scheme abandoned,
baseline 4kicker-bump - Pulsed magnet laboratory installed
13Storage Magnet Systems
Orders have been placed for the industrial
production of NSLS-II Storage Ring Magnets
The 240 68mm aperture quadrupole magnets in 6
variants will be produced by Everson/Tesla and
BINP, orders placed Sept 23 The 68 mm sextupole
magnets will be produced by IHEP and Danfysik,
Orders placed October 16 The 60 large aperture
quadrupoles and the 30 large aperture sextupoles
will be produced by Buckley, orders placed
Oct. The vendor for the 54 35mm aperture and the
6 90mm dipoles has been selected. The 180 100mm
and 156mm hor./vert. correctors will be produced
by Everson Tesla.
14Girder, Supports and Integration
- Girder RD and Girder Design Completed
Manufacturing Drawings being completed -
- The precision alignment procedure is well defined
by having tested each step in the procedure -
- The RD and the design of the girder system is
complete, all the critical issues have been
addressed and solved. - Ultimate test After transport, all
magnets within 5mm aligned -
- Environmental Room equipped and functional
-
- The girder integration procedure re-planned only
one environmental room necessary, final magnet
adjustment performed manually - - optimizes procedure
- - this will save costs
- - helps to compensate the enhanced labor
needed in setting up the production facility and
performing RD ? dedicated
presentation
Fully Functional and Equipped Environmental Room
(DT lt 0.1 C ) for 30 mm Precision Alignment
15Final Demonstration of Feasibility of 30mm
Magnet-to-Magnet Alignment
June 2009
16Mechanical Systems, Front-Ends
- Front end design 80 complete
- Outside-Vacuum prototype of safety shutter built,
cycle-tested successfully - Compressed gas system redesigned and based on
compressed air - DI water systems (5 x CU 5 x AL, RF, Linac,
Booster, Cryo-Compressors) detailed system
design, component layout, service building
equipment room detailed design with 3-D layouts
17Vacuum Systems
Prototype chamber invar support on girder
- Vacuum Production Facilities Clean-room for
assembly prepared, vacuum conditioning lab is
now fully equipped and tested, vacuum cleaning
and measurement lab started to operate (late) ,
brazing oven installed, chemical cleaning
procurement delayed - Vacuum Chamber prototype extrusions successful,
orders for production of MP extrusions place,
dipoles will follow soon, dipole chamber bending
under control, but is considerable effort
contracts for prototype welding and machining in
place vacuum chamber bake-out iterated and
improved, Bi-metal flange in production - Collaboration with APS in place for Production
Chamber Welding - NEG Pump Design tested, support system iterated
and improved, Rogue mode shielding integrated - Novel Design for Shielded Bellows, 2nd prototype
being built - Commercial Ion pump comparative test
-
Dipole chamber bending
New Vacuum Chamber Profile
Novel Design Shielded Bellow Prototype
18RF Systems
- Storage Ring SC RF Cavities Nonlinear Stress
Analysis demonstrates compliance with equivalency
to pressure vessel code - Failure of over-pressured system
reproduced? benchmarked calculation - Procurement documents in preparation
- ? reviewed by lab safety committee which
confirms adequacy of the procedure - Optimization of Coupling for 500mA
- LLRF 2nd FPGA based prototype build, still basic
functionality , under test with Booster 7-cell
cavity (tuner loop) - Booster RF New tuner motors and electronics,
adaption of input coupler to co-axial waveguide - RF Power RF engineer hired,
- Cryogenic System Cryo engineer on board,
consultant help to refine valve and pipe
dimensions, design being wrapped up resulting in
preliminary specification for first iteration
with vendor
19Instrumentation
- BPM System still major activity
- RF button first article successfully tested,
production released - Commercially available BPM electronics meets
demanding NSLS-II requirements (resolution,
stability 0.1mm) - Concerns about obsolete electronics and
vendor support? in-house development seriously
considered - Efforts on other diagnostic systems started
Photon BPMs, Fast orbit control, transverse
damper system, fast orbit control, optical
monitoring, scraper systems, loss monitors -
New 7mm 2-in-1 RF Button First Articles with
Boron Nitride Washers
20Electrical Systems
- Main Dipole PS component design and prototype
testing well advanced, next step is system
integration - MP power supply design meets higher (25 ppm)
stability standards easily, order for DCCTs have
been placed - New dual corrector power supply in progress
- Equipment enclosure design completed and power
test on prototype with PS and heaters completed - Detailed cable plans developed, layout of cable
trays - Calibration system for PS DCCT developed
Full Power Test of NSLS-II Sealed Air-Cooled
Power Supply Rack with prototype PSs
AC Power Control Module
Power Converter
DCCT
Low noise regulator prototype for Main DP
switch-mode supply
21NSLS-II Insertion Devices
49
? Tanabes Presentation
22Possible NSLS-II DW Production by APS
Damping Wiggler APS provided a preliminary
design, a cost estimate and a schedule. However
APS has difficulties with NSLS-II DW
specifications.
Attractive APS fixed gap NSLS-II DW proposal with
horizontally moving in/out beam position
23Bldg. 832 3D-Layout
ISO-7 Clean Room for Measurement
ID Lab
Tech Shop
Pulsed Magnet Lab
RF Lab
24Safety Systems
- Design of SPPS and EPPS systems well advanced,
completion end of FY - Successful external reviews of the systems
conducted - Engineering prototypes in progress
? Johnsons Presentation
25Control System
- High Level Applications
- -Standard interface for orbit control running
using existing beam optics dynamics codes - -Data Description Service is deployed as
an interface/complement to basic channel access
mechanisms. -
- Database IRMIS API for machine lattice entry and
report is running and integrated into the online
model environment. - Equipment Controls Preliminary design docs for
vacuum, power supply, diagnostics, RF, Timing,
EPS/PPS -
- Prototype of Controls for Subsystems started
- Vacuum, beam line, PPS, beam correlated
applications, Diagnostics, power supplies, and
LLRF - Network preliminary design of network hardware
system
26Accelerator System Budgeted Cost
27Accelerator Systems Budgeted Costs
28Registered AS Cost Changes
Note Contingency is owned by Federal Project
Director. Numbers are just used as a measure of
cost increase!
29Project Cartoon Schedule
30Schedule
CD4
31Cost and Schedule Performance
32Assessment
- Trend since October 2008
- Cost variance becoming smaller
- Schedule Variance becoming negative reaching
5.8M at the end of FY09 - Reasons
- Late hires and Missing MOU Labor 36 FTE ( _at_
6.0M ) - Labor augmentation plan 36FTE to recover since
June, too early to see an effect - Should start to see improvement within the next 6
month -
- There is one remaining EVMS issue Controls has
worked on activities scheduled to - start in FY10? no earned value, self repairing in
FY10 -
- There are real delays Vacuum Chamber 1.5 M
due to technical issues and procurement or vendor
problems and slow progress with the vacuum
facility (recovering now) -
- Slow procurement process with many medium size
procurements behind schedule - ? Additional procurement support added (Liaison
Engineer AS, more buyers)
33ASD Shortage of Labor Resources
Causes Late Hires, Resource Leveling, MOU
contributing less than planned
ASD schedule variance at 4/30 associated with
this effect is -4M
FTE
FTE
Difference, Accumulated Difference
FTE
34Mitigation of Schedule Variances
Goal Stop Growth of SV within 3 months ?
recover the schedule within 24months
Preliminary Plan in Place to satisfy immediate
needs 18FTE, plan to complement by another 18FTE
Additional 18 FTE ? Slow recovery
35Schedule Recovery
FTE
36Accelerator Systems Division Staffing
Temporary Labor
Budgeted
Planned
Hired
MOU BNL
37FY09 AS Hires
- FY 09 Staffing
- 11 Controls System Experts
- 10 Engineers
- 7 Physicists
- 11 Technicians and Designers
- Present staff 103
- Supported 10 FTE MOU
38Organization
- 23 new key staff hired
- Deputy Division Director assigned E. Johnson
- Project Engineer hired G. Fries
- Organization augmented by task forces (FOF, BC)
N
39Conclusion
- Design of Accelerator Systems approaches
- conclusion Magnet, Vacuum Chamber design
- and prototyping ready for production
-
- Accelerator Systems entered the construction
- phase, major procurements and production
have - started SR Magnets, Vacuum Chambers,
Production - Facilities
-
- Negative Schedule Variance has built up is
mitigated by adding labor to make up for labor
resources not available the time work was
scheduled, - Focus in the next months will to award
construction contracts for magnets, vacuum
chambers, LINAC, booster and support systems - Accelerator systems in good shape, no major
technical issues, schedule under control