Title: FINANCE, PERFORMANCE AND ACUTE COMMISSIONING REPORT
1FINANCE, PERFORMANCE AND ACUTE COMMISSIONING
REPORT
Jonathan Wise, Director of Finance Performance
2Contents
Part 1 Finance report (slides 2-9) Part 2
Performance report (slides 10-14) Part 3 Acute
commissioning report (slides 15-29) Finance
Appendices (slides 30-43) 1. Summary Operating
Cost Statement and variances by budget heading 2.
Balance sheet 3. Capital 4. Cash flow
3PART 1 FINANCE REPORTFinancial position -
Summary
- Statutory duties
- Forecast underspend against revenue resource
limit - Forecast underspend against capital resource
limit - Forecast achievement of cash limit
- The PCT is not in a position to forecast its
year-end outturn with confidence - The PCT is at high risk of receiving a weak
assessment in respect of a number of the ALE
criteria.
4Overview of month 11 year end forecast
-2,800
5- Reasons for movement in forecast outturn M9 to
M11 - Acute Commissioning (0.3 million deterioration)
- See analysis in section 3 of the report.
- Joint Commissioning (1.8 million deterioration)
- Continuing care savings lower than budgeted (see
next slide), offset by improvements in other
joint commissioning budgets - Primary care (1.1 million improvement)
- Improvement in prescribing underspend (0.6m),
plus other budget areas (0.5m) - Provider Arm (2.3 million improvement)
- More realistic forecast outturn (0.8m) plus
impact of actual capital charges.(1.5m) - PCT Management (0.2 million improvement)
6CONTINUING CARE -SUMMARY
- The PCT has been in discussion with London
Borough of Brent (LBB) since November 2006 in
respect of the funding arrangements for approx
140 clients - The basis of an agreement has now been reached
with LBB officers in principle as follows - approx 75 clients have been accepted as the
Councils responsibility, following review by
social care panels - approx 50 clients have been accepted as the PCTs
responsibility (mainly Old Long Stay) - a small number of clients still remain to be
agreed - The 07/08 budget assumed savings of 3.65m ( in
respect of all Councils) - The potential agreement with LBB provides the PCT
with forecast savings as follows - 07/08 FYE
- m m
- Agreed clients 1.0 2.2
- Disputed clients - 0.2
- Arrangements are being agreed with the Council to
recognise the 07/08 costs prior to the date of
LBB panels. This is estimated at 1.4m. - As prior year debtors included in the PCT
accounts in 06/07 (1.5m) will not accrue, a
provision has been made for this (included in the
risk debtors figure of 2.5m). - The above relates to the position with LBB.
Further work is needed in respect of the position
with other Councils.
7OUTSTANDING AREAS OF UNCERTAINTY
- Previous Board reports identified the areas of
major variability and why the PCT was not in a
position to forecast its year-end outturn with
confidence - Whilst most of these have been reviewed and
incorporated in the latest forecast, there remain
the following risks of material movement in month
12/final accounts production - Acute Commissioning the reported position is
based on month 10 activity extrapolated and there
remains potential volatility as activity for Q3
and Q4 is finalised - Financial systems and processes the continued
weaknesses across a range of financial accounting
areas means that the possibility of unpredicted
year-end movements remains - The year-end position as per the audited accounts
could therefore move significantly (in either
direction) from the month 11 forecast
8BALANCE SHEET,CAPITAL AND CASH
- Balance Sheet (Appendix 2)
- the main in-year movements are as follows
- Fixed assets a reduction of 18m due mainly to
transfer of assets to CNWL - Creditors a reduction of 32.8m due mainly to
the inclusion in 06/07 of an end of year RAB
adjustment with NW London and a concerted effort
to address prior year issues - Capital (Appendix 3)
- an underspend of approx 9m is forecast against
available capital resources - capital expenditure has been low due to a lack of
a Capital/Estates strategy and the consequent
Business Case approvals - Cash (Appendix 4)
- the forecast cash position, after full repayment
of the cash advance (loan) required to finance
the 06/07 deficit, is for a significant
under-drawing against the cash limit due to - Cash impact of forecast capital underspend
- Cash impact of forecast revenue underspend, plus
other non-cash items - Cash planning and forecasting during the year has
been weak, as evidenced by the closing month end
cash balances
9Next Steps/Actions re Financial Position
-
- Finalise year end outturn and produce final
accounts. - Implementation of action plan in respect of
financial capacity and capability - - detailed action plan produced
for EMT/Audit Committee for implementation - Jan-Mar 2008
- - being reviewed for completeness
in light of Taylor enquiry - - 08/09 plan being developed for
review at April Audit Committee -
10Part 2 Performance Report
- Performance dashboard updated for the period
ending January 2008 together with forecast
position at year-end. - The dashboard is consistent with the Strategic
Health Authoritys Performance report as at the
end of Q3 07-08. Brent PCT was rated as RED at
the end of Q3, based on the combined score of the
PCTs performance on Key targets (RED) and Other
targets (RED). - The RED areas are detailed with narrative on
reasons and the action taken.
11Performance Report- Q2 07-08, Q3 07-08 and
Current status
12Performance Report- Q2 07-08, Q3 07-08 and
Current status (2)
13Key Targets Narrative
- Non Admitted 18 week RTT target (Owner Director
of Strategic Commissioning) In January 77 of
patients completed their pathway in less than 18
weeks. Great progress has been made at NWLH, our
largest acute provider, and current performance
for this target is 95.4. The greatest risk is
now at other Trusts, especially the Royal Free
NHS Trust and UCL NHS Trust. - Admitted 18 week RTT target (Owner Director of
Strategic Commissioning) - In January 48 of
patients completed their pathway in less than 18
weeks. Although, this is not changed much since
December (at 48), progress continues to be made
with this target. The greatest risk is at NWLH
as our largest acute provider, and in the
surgical specialties, especially Trauma and
Orthopaedics. - AE 4 hr wait (Owner Director of Strategic
Commissioning) The underperformance of the AE
4hr Wait Target is currently being addressed in
partnership with NWLHT and has culminated in both
a performance trajectory plan and strategic
action plan. Several operational groups are also
working to this guide and these include a Daily
Bed meeting (to review potential discharges for
the day and available capacity within the
hospitals both in terms of staffing and bed
availability) and a Weekly Performance meeting
(review of last weeks activity, agree associated
actions to address any particular issues and to
update on actions already taken).  The AE
trajectory assumes that the Trust will meet 98
for All Types in June 2008. Primary Care
services at both hospital sites (provided by
Harrow and Brent PCT) have been assisting the
Trust in meeting the demand for treating patients
with a primary care need. - MRSA (Owner Director of Public Health)
Cumulative number of MRSA bacteraemias at NWLHT
has reduced significantly since last year but
remains above the target number YTD. Root cause
analysis of bacteraemias to date in 2007/08
indicate a significant majority are line
associated infections. The high impact
interventions around line care are being
implemented to tackle this at NWLHT and this will
be a major and challenging piece of work. Another
key priority is ensuring those patients
identified as positive on admission are
decolonised. To support decolonisation of MRSA
positive patients in the community prior to
routine admissions to NWLHT, the HCAI group has
now developed a consistent policy for
decolonisation in primary care. Other key
elements of the NWLHT action plan address hand
hygiene, full implementation of the high impact
interventions, antibiotic use, cohorting and
isolation, surveillance, cleaning and
decontamination, training, leadership and
governance. As part of its action plan, NWLHT is
launching an intensive hand hygiene campaign. - Smoking quitters (Owner Director of Public
Health) - The drop off in performance YTD in
2007/08 compared to performance in the latter
part of 2006/07 is due to discontinuation of the
community advisor scheme from 1st April 2007 as
part of the turnaround plan. The PCTs strategy to
reduce smoking rates focuses on the investment,
expansion and re-focus of the stop smoking
service. This will involve- - Stop before the Op targeting smoking cessation
at people referred for routine surgery to
maximise clinical outcomes - Supporting practices to contribute to smoking
cessation targets through Practice Based
Commissioning, referrals and service delivery - Training a proportion of Health Trainers from
target communities to become smoking cessation
community advisers - Maximising external investment into the service
e.g. Local Area Agreements. - The PCT plans to invest a further 520k in 08-09
to drive forward its smoking cessation
initiatives. The investment will consist of an
incentive scheme to encourage GPs to participate
in smoking cessation initiatives together with
additional resources for health promotion.
14Other Targets - Narrative
- Inpatient waits over 11 weeks (Owner Director of
Strategic Commissioning) The number of
inpatients waiting over 11 weeks has decreased
in January (542) compared to December (571),
with a variance from plan of 392. Our largest
acute provider, NWLH, was unable to maintain a
normal period of operating over the Christmas and
New Year period, due to medical and nursing staff
shortages. There has been some spill-over from
this into January. Although above plan the trend
has been that the actual number waiting over 11
weeks continues to decrease compared to previous
months. This trend has continued for February
where the number of patients waiting over 11
weeks at NWLH was 213,compared to 341 in January.
- Outpatient waits over 5 weeks (Owner Director of
Strategic Commissioning) -The number of
outpatients waiting over 5 weeks has decreased in
January (909) compared to December (1365), with a
variance from plan of 261. Although above plan
the trend has been that the actual number waiting
over 5 weeks continues to decrease compared to
previous months. Looking ahead, this trend has
continued for February where the number of
patients waiting over 5 weeks at NWLH was
223,compared to 541 in January. - Community Matrons and VHIUs (Owner Director of
Provider Development and Estates) Late
recruitment of Community Matrons - 2 started in
Sept 07, 1 started in Oct 07. Case finding and
patient list validation process will be
accelerated to increase number under case
management to 210 by March 08. - Choose and Book (Owner Director of Primary and
Community Commissioning Services) There are
still concerns regarding slot availability at
Provider Trusts which affects our current
performance. It is also apparent that initial IT
training is not sufficient to ensure that Choose
and Book is used routinely to deliver maximum
patient benefit. EMT have agreed that we should
look at improving the system with our current
resource this would include reviewing the IT
infrastructure with GP practices and upgrade any
noncompliant system, review current training
capacity, and PEC engagement with raising the
profile of CB, using the 18 week target as a
lever. - Blood pressure and Cholesterol Management (Owner
Director of Primary and Community Commissioning
Services)- Recording of this may be less than
target as CHD prevalence is lower than expected
in Brent. This will be a priority for QOF reviews
in 2008/09. QOF reviews have not taken place in
2007/08 and less than a third of practices were
visited in 2006/07. All practices will undergo a
QOF review in 2008/09 when the primary care
performance regime and team will be fully
established. - BMI recording status (Owner Director of Primary
and Community Commissioning Services)- BMI
position is poor as it is not part of QOF.
Currently 22 practices are participating in a
pilot being supported by Imperial College to
extract clinical data from practice clinical
information systems including BMI and smoking.
We are exploring the feasibility of extending
this to all practices for 2008/09 as part of the
incentive scheme to share health status data. - Crisis Resolution Services (Owner Director of
Strategic Commissioning)- Verbal Update to be
provided at meeting. - Chlamydia Screening (Owner Director of Strategic
Commissioning)- Plans introduced to increase
chlamydia screening include - - Expanding the size and staffing levels within the
Chlamydia Screening Programme (CSP) by joining
with Hillingdon PCT and thereby increasing
overall resources. - Increasing overall financial contribution of each
of the 3 PCTs in the CSP for the next two years.
Brent has introduced incentives to increase
screening in pharmacies. - Investigate the potential to develop incentives
through Locally Enhanced Service for sexual
health services in primary care. - Increase the number of testing sites.
15Part 3Acute Commissioning Report Summary
- Year to date overspend 2.9m at month 11 (based
on 10 months activity - data)
- Increased from 2.1m at month 9 (based on 8
months activity data) - Net YTD overspend movement between month 9 to
month 11 as follows -
-
M9
M11 -
m m - Acute contracts 3.4
2.9 5.2 3.6 - Other acute spend
- - Consortia
(0.2) (1.9) (0.4)
(2.3) - - High Cost Drugs (0.5)
(49.8) (0.7) (54.5) - - Non Contracted activity -
- (0.1) (3.9) - - Other budgets (0.5)
(15.5) (1.2) (30.1) -
2.1 1.5 2.9
1.7 - The remainder of this report focuses on the acute
contract activity
16DATA FLOWS/VALIDATION
- The PCT receives contract monitoring reports for
each acute provider approximate 4/5 weeks
after the end of the period - The month 11 acute commissioning report is
therefore based on 10 months activity
extrapolated and includes PCT review and
challenges (see below) - There is a set national timetable for quarterly
finalisation and agreement of acute activity and
payments, known as the flex and freeze
process. The key dates for validation and
agreement of Quarter 3 activity are as follows - March 14 last date by which PbR completed
spells and attendances relating to Q3 can be
submitted or amended by providers - March 28 last date for commissioners to send
queries - April 9 date by which invoices for Q3 must be
agreed for payment - The PCT raised a number of queries/challenges
with NWLH at Q1 and Q2 and the agreed outcome of
these is reflected in the position. An
assessment of the potential outcome of Q3 has
been made in compiling this report.
17SUMMARY VARIANCE ANALYSIS BY PROVIDER
- Month 8
Month 10 Detailed Analysis - 000
000 - NWLondon (1438) (2.5)
(1807) (2.6) Slides 19-22 - Hammersmith (1483) (12.9)
(2043) (14.3) Slides 23-24 - St Marys 139 0.8
(71) (0.3) Slide 25 - Royal Free (38) (0.7)
(282) (4.0) Slide 26 - Other Trusts (214) (1.4)
(497) (2.7) Slides 27-28 - Total (3033) (2.9)
(4700) (3.6) Slides 29-30 - The total overspend increased from 3m at Month
8 to 4.7m at Month 10
18VARIANCE ANALYSIS BY PROVIDERNORTH WEST LONDON
HOSPITALS
19Outpatient Attendances for NWLH (PbR)06/7
Outturn (M10) vs 07/8 M10 Plan and Actuals
- Overall OP Attendances variance against plan
increased from -6.1 at M8 to to 7.7 at M10 - Reduction on 06/07 outturn of 5
20Accident and Emergency Activity for NWLH
(PbR)06/7 Outturn (M10) vs 07/8 M10 Plan and
Actuals
- Total AE attendances planned was for a 10
reduction in 06/07 Outturn - Month 10 actuals are a 7.3 increase on 06/07
Outturn
21NWLH Excess Bed-days Increase in activity in
Non-Elective Non-emergency M8-M10
22VARIANCE ANALYSIS BY PROVIDERHAMMERSMITH
HOSPITALS
23Electives for Hammersmith (PbR)06/7 Outturn
(M10) vs 07/8 M10 Plan and Actuals
- Variance to plan continues at similar levels to
month 8 - Total Activity broadly constant 06/07 to 07/08
24VARIANCE ANALYSIS BY PROVIDERST MARYS HOSPITAL
25VARIANCE ANALYSIS BY PROVIDERROYAL FREE HOSPITAL
26VARIANCE ANALYSIS BY PROVIDEROTHER PROVIDERS
Adverse Variance of 100K detailed on next slide
27VARIANCE ANALYSIS BY PROVIDERANALYSIS BY CATEGORY
28VARIANCE ANALYSIS BY ACTIVITY TYPEALL PROVIDERS
29CHANGE OF VARIANCE BY ACTIVITY TYPE ALL PROVIDERS
30Appendix 1 Summary Operating Cost Statement 11
mths ending 29/2/08
31Appendix 1 Summary Operating Cost Statement 11
mths ending 29/2/08
32Appendix 1 Summary Operating Cost Statement 11
mths ending 29/2/08
33Appendix 1 Commissioning of Healthcare Summary
for 11 mths ending 29/2/08 (Joint Commissioning)
34Appendix 1 Commissioning of Healthcare Summary
for 11 mths ending 29/2/08 (Acute Commissioning)
35Appendix 1 Commissioning of Healthcare Summary
for 11 mths ending 29/2/08 (Joint Commissioning)
36Appendix 1 Primary care
37Appendix 1 Primary care
38Appendix 1 Provider services
39Appendix 1 Management HQ
40Appendix 2 Balance Sheet for 11 mths ending
29/2/08
41Appendix 3 Capital
42Appendix 3 Capital
43Appendix 4 Cash Flow Report to 29/2/08