Title: HAPL - 19
1Fission Reactor Operations and Availabilityand
How These Influence Our Choices for IFE
C. A. Gentile
HAPL - 19 University of Wisconsin Madison,
Wisconsin October 22 - 23, 2008
2Motivation
- Compare fission light water PWRs operations,
maintenance, and outages for comparison with
conceptual design of IFE direct drive power
reactor. Evaluate advantages and disadvantages of
both technologies. - Begin to define maintenance requirements, duty
cycle, ESH items. Where possible relate to
current ESH criteria for DOE, NRC, CFR (i.e.
10CFR835 / 10CFR part 20). Begin to consider
PSAR, Technical Specifications. - Establish lines of communication with people who
are currently producing electricity with fission
power reactors. Identify areas of common ground.
Develop a common technical / regulatory language.
Provide solutions to those aspects which hinder
greater exploitation of fission generated power.
Perception with some that fission is not safe.
Spent fuel a very big problem. On-site fission
reactor spent fuel pools are reaching capacity.
Building new on-site storage for spent fuel
capacity, or high density storage racks, not
always embraced by the public. - Pointed out at TOFE - 18 that in the book The
World is Flat Thomas Friedman does not mention
fusion energy as a future power source.
Interactions with the fission community healthy
in getting our message understood.
3Presentation Outline
- PWR fission reactor operations / outages - Palo
Verde Nuclear Generating Station. Three PWR light
Water Reactors costing 9.3B. Entering the
second 20 year cycle of operational life. NSSS
Combustion Engineering, A/E Bechtel - Producing 3825 MW(e). Approximately twice the
output of the Hoover Dam. - Unit 2 (with new steam generators) _at_ 1335 MW(e)
is currently the largest US reactor - Remote Maintenance for IFE
- ESH
- Summary
4 PWR Refueling Outages / Operations
- Palo Verde Unit 1 Coasts to Continuous
Operation Record PHOENIX--(BUSINESS WIRE)--Oct.
1, 2002 Palo Verde Nuclear Generating Station's
Unit 1 operated for its entire fuel cycle --
running "breaker-to-breaker" for a unit-record
502 continuous days -- when it shut down for its
scheduled 10th refueling over the weekend. In
1999, Palo Verde Unit 2 set the station's
existing record of 515 days of continuous
operation, prior to its eighth refueling. In
2000, Unit 3 completed a run of 509 continuous
days prior to its eighth refueling.Unit 1's
refueling is expected to be completed in about 40
days. Palo Verde's previous refueling -- the 10th
for Unit 2 -- was completed this past April in 32
days, the second shortest for the site and part
of an ongoing record of short refueling
durations. - During PWR refueling outage, 25 to 40 of the
fuel assemblies are typically replaced depending
on the cycle length and number of fuel assemblies
in the reactor.
5Cost Savings and Reliability
- Reducing the refueling outages at the station by
1 day saves the rate payers gt 1M due
to the replacement fuel costs _at_ gt 1 M / day
when the reactor is not producing electricity
(not including replacement by hydro-power). - Efficient refueling / maintenance outage planning
second only to operating the reactor safely. Same
as in fusion. - Limited supply of qualified / certified nuclear
workers. The cost of occupational radiation doses
a factor in fission outage planning and will be
the same for fusion. Robotic and remote handling
can help alleviate this problem. - Nuclear power becoming more relied upon. The
South Texas Project (2 - PWRs) sited 60 miles SW
of Galveston stayed on-line throughout hurricane
Ike, although Waterford - 3 and River Bend - 1
(both in Louisiana ) were taken off-line during
hurricane Gustav. - Deregulation has emphasized the need for
affordable power to ratepayers.business,
municipalities.
6IFE power reactor - PWR Fission light water
reactor. The two technologies lead to
similarities in general arrangement. Goal of
bothproduce safe, economical electricity.
7Most significant maintenance task at PWR is
repair and replacement of steam generator(s). Can
take up to 1 year but have been completed at some
stations in 6 months. Occupational
radiation doses in fission industry coming down.
Average PWR annual dose last year was 97 person
rem. IFE will need to address the change out of
primary components.
8 Palo Verde Nuclear Generating Station
-
- Site construction started in 1976. Unit 1 came
on-line 1986. Unit 2 3 came on-line1988. Site
cost 9.3B - Palo Verde Unit 1 rated at 1,314 MW (e). After
house power requirements the reactor sends out
1250 MW to the US South Western grid ( note 1 MW
runs 400 houses ) - Location 40 miles west of Phoenix, AZ
- Combustion Engineering PWR
- Noterefueling / maintenance outage durations are
on the order of 30 - 40 days. Outages planned
for non-peak periods -
-
9Palo Verde, the USA largest nuclear power site.
Palo Verde 2 was recently uprated to 1,335 MW(e).
Palo Verde 2 currently the Nation's largest
nuclear reactor, surpassing the South Texas
Project Unit 1 and Unit 2 reactors.
Unit 2 steam generator replacement successfully
completed. This is a large complicated gt 300
M task taking 1 year. Other large tasks include
maintenance and repair of reactor cooling pumps.
In fission power industry large primary
components are replaceable, as should be for IFE.
10Maintenance Operations - Requirements,
Similarities, Advantages
- No PWR maintenance or repair while reactor under
power or within confines of bio-shield. - Very little human activity inside the containment
building, when needed only at reduced power
(typically lt 50 ). - Need to operate for relatively long periods of
time 24/7 for up to 1.5 years. - Maybe possible to perform some IFE maintenance
activities while the reactor is running using
robotics. Robotics maintenance video. - Need to maintain occupational radiological doses
in accordance with 10CFR835 / 10 CFR part 20.
Including ALARA levels. Off-site consequences due
to misadventure at fission plant an issue. Ten
mile emergence planning zone (EPZ) with plans for
evacuation a condition of USNRC fission licensing
process. 50 mile ingestion pathway zone also
required as part of the licensing process. Should
be much less restrictive for fusion. - Need to conform to limits of Technical
Specifications, FSAR, and licensing conditions
and limiting conditions of operation(s).
11CANDU reactors capable of refueling on-line. New
fuel assemblies are added horizontally and the
spent fuel assemblies are pushed out to the spent
fuel storage area.
The fuel assemblies used in the reactor are 1.5
feet (0.5 m) long, consisting of individual
rods. The cladding is Zircaloy and the fuel
pellets consist of uranium dioxide.
12Components within the confines of the bio-shield
must last for the duration of the run. Components
within the confines of the containment should
last for the duration of the run.
- Primary nuclear systems
- need to be robust reliable and where possible
modular to support maintenance and replacement. - - GIMMs
- - Vacuum Pumping System
- First wall
- - Blankets
- - Magnets
- Dumps
- Cooling Systems
- - Target Injector
Please see poster presentations on sub-systems
and infrastructure - MI I. Zatz , et. al., -
Helium Brayton Cycle S. Wagner, et. al., - IFE
Structure, T. Kozub, et. al.
13ESH
- Conceptual design(s) can be evaluated for
regulatory requirements where applicable. - Level and sophistication of safety systems
presumed to be less in a IFE direct drive
environment due to limiting off-site consequence.
- ALARA systems engineered into the design.
T-cleanup systems, bio-shield, remote
maintenance, automated systems, evaluate the MTBF
for sub-system components. - Off-site doses from normal and off-normal
operations manageable. Although a large inventory
of T on a daily basis, T at risk can be
attenuated and managed between multiple MCA
locations.
14ESH
- Engineered containment and confinement systems
and strategy incorporated into conceptual
designs. Modular design important for maintenance
and replacement tasks. - Pre-Licensing components, in the form of a
regulatory compliance plan should be developed (
NEPA, FONSI documentation, PSAR, FSAR, Technical
Specifications, etc.)
15Conceptual View of the IFE Laser Driven Direct
Drive Power Reactor at the Existing Palo Verde
Nuclear Power Site. Builds upon existing
infrastructure
16 Summary
- Great advantage of IFE Direct Drive. Low cost
targets. No spent fuel. Level of safety class
systems most likely less (perhaps less than MFE
due to more stringent vacuum requirements in
torus). No refueling outages, only maintenance
outages. - Developing technology moving toward robotic
maintenance. - Robotic maintenance may preclude the need to shut
down the reactor to do repairs. - To be competitive with current (fission) nuclear
generation production maintenance periods need to
be comparable. Replacement energy costs are
expensive. - ESH issues need to be identified and considered
during the developing conceptual designs. - A dialogue with the US commercial fission
industry being put into place to establish open
lines of communication. - In the near future an IFE direct drive power
reactor information article in a main stream
fission publication.Nuclear News or Nuclear
Plant Journal may be valuable. -
17Advanced technology may not win the day if not
economical, not reliable, or has perceived
regulatory impediments
- Need to design and build a competitive
- power reactor for the production of commercial
electricity. - Faster or even better may not survive
- market forces if reliability, cost,
- effectiveness, and safety are not part of the
- package.
- IFE direct drive power generation is
- Green need to keep our fission colleagues
engaged in IFE direct drive fusion power
development. - no green-house gases
- no spent fuel no spent fuel storage
- - low proliferation threat
- produces its own fuel
- no critically - limited safety class systems
- but ( same as fission ) fusion power reactor
will be a capital intensive enterprise